THERMAL POWER PLANT PRESSURE PART ( BURNER PANEL ARRANGEMENT)


This picture shows the lifting of wind box duct before erection of pressure parts . Please

note this is only for super critical boiler and not required for any sub critical boiler up to

500 MW. It has been told that if we do not erect this duct now it will be extremely difficult

to erect the same after pressure part erections and that is true. I thought it is better to mention

the same here.




Burner panel in view . The same is generally erected after erection of vertical /spiral wall up to Burner

panel top. However like all sub critical boiler it is seen that one or two burner panel are getting delayed

due to various reasons . Here also all the burner panel was delayed and we can not wait further because

we have close the furnace . The wait of single burner panel is around 50 T . Now it has to be erected

on temporary supports and burner panel needs to be shifted horizontally to the position . The same

was done afterwards . However it is preferred to have Burner panel in time for erection. The reason for

delay has been explained  in the next photograph.




We are doing super critical boiler first time and the kind pressure parts arrangements to be done

around burner is enormous. This job involves huge pipe bending etc to make it a panel. Final

connection will be loose tube with walls. We are told Burner panel was delayed in manufacturing .