Total Pageviews

Saturday, 10 May 2014

TURBINE GENERATOR PKG ERECTION PART-X, DIFF.CHECKS BUMP ,SWING ,HORN DROP ,CATENARIES ETC.- ABC OF THERMAL POWER PLANT.


Part – X

After colour matching axial zero position is achieved and this will be reference point of

future axial measurement of HP,IP and LP casing. During Turbine supervisory  instrument calibration

rotor is given to instrument group at axial zero position .

 After completion of colour matching of the thrust bearing pads the casing alignment work

can be taken up. In case of spring loaded foundation after completing all other works the HP /

IP , IP/LP , LP/GEN , GEN/EXCITER couplings are to be reopened and realigned after completing

the reaming /honing . The rotors alignment are to be checked with TG deck in floating condition

as per the laid down procedure. After checking of alignment /catenary the final couplings are to

be tightened including their coupled run out and swing check of rotors on HP front and Exciter

end of the shaft.

The boxing up of LP inner inner and LP inner outer casing can be taken up before starting

the alignment of HP-IP & LP rotor for coupling work.

After completing the welding of HP inlet, HP exhaust, IP inlet, IP exhaust and other piping of

HP/IP casing the final horn drop readings are recorded as per the laid down procedure

mentioned in the manual for horn drop check. However the IP casing horn drop is also to be

recorded with IP inlet upper half pipe welded with casing alone.


ASSEMBLY OF BEARING AT SITE

The KWU/BHEL design machine are supplied with four bearings out of which three are the

journal bearing and one is combined thrust and journal bearing on H.P. rear end of the

shaft. All the turbine bearing are self aligning type and they adjust themselves as per the

catenary of the machine.

The function of a journal bearing is to support the turbine shaft , but the thrust bearing

support the shaft as well as work as a fix point for the turbine shaft. The contact

arrangements between bearing and bearing supports are of two types i.e. sphere to sphere

in HP front and HP rear bearing and torus to cylindrical in other bearings.
The bearings are supplied to site after ensuring their contact at works. During erection all
the bearing are supplied to site in aligned and assemble condition in their individual
pedestal from the works. After alignment of the bearing in their pedestal the seat of the b
earing are doweled before dispatch to site.
In case of Thrust and Journal bearing the seat of the bearing neither doweled from the
works nor it is recommended to be doweled at site. The bearings need preparation before
placement of module in position at site. This can be done even before the placement of
pedestal in position for grouting.
Assembly Procedure is available in the erection manual of 500MW turbine.
CRITICAL CHECKS OF TURBINE ERECTION.
BUMP TEST
The axial clearance check is determined after radial clearance measurement has been
completed.
In this case the shaft is shifted in the “+” and “-” directions from its operating position and
the dimensions with the shaft in limit position are measured using a depth gauge.
ROLL CHECK
In KWU machine the minimum radial clearances HP, IP and LP casing are measured by
actual by moving the casing radial direction at site while rotor is rotated by hand. This is a
very  accurate and fast method of measuring the minimum radial clearance of any of the
casing.
The major variation in these reading may cause vibration in the machine and obstruction in
barring gear operation etc. Such facilities are not available in many other designs of machine
and causes longer duration in erection and overhauling of the units.
After completing the alignment of rotors the casing alignments are carried out by roll check
method but equal importance should also be given to the centering of HP and IP casing.
The centering of casing may not be fully sacrificed in comparison of rolling test readings and
a compromise between these two readings should be made. The roll

 

CATENARY AND ALIGNMENTS

The catenaries of the machine are very important for a turbine and Generator assembly to
achieve proper alignment of various rotors and loading on their bearing. Any deviation may
lead to various operational problems in the machine like high shaft vibration, high bearing
vibration, high Babbitt metal temperature of the bearing etc. To avoid these problems it is
necessary to maintain the catenaries of the machine during erection and subsequent
realignment/overhaul of the unit. Many times it is observed that though the alignment of
rotors are within limit but the catenaries as a whole get deviated from the prescribed design
value of the machine. In order to avoid such derivation a need is felt to devise a procedure
which shall ensure rotors alignment along with proper catenaries of the machine.
During first few years of the operation of the unit the possibility to the disturbance of the
catenaries are much more due to settlement of the foundation frame.
In each overhaul of the unit the catenaries of the machine is to be corrected. The L.P. front
and L.P. rear pedestal are directly grouted here without any separate base plate. As such
any correction on lifting or lowering. These pedestals are not very convenient so if necessary
the rotor may be lifted or lowered with respect to pedestal seal bore and required
catenaries may be achieved. In extreme cases these pedestals may be even re grouted
during major overhauls of the unit to correct the catenaries of the machine.
HORN DROP TEST
By horn drop test the loading of the casing on each corner is determined. The horn drop test
is repeated at various stages in individual casing i.e. first without connection of any pipe
lines the horn drop readings are recorded then it is compared after welding of inlet, outlet
and extraction pipe lines etc. The horn drop readings are very important in HP & IP casing.
First the proper horn drop readings are made without connection of any pipe lines and then
the reading are taken after welding of all pipe lines on HP & IP casing. As such the influence
of these major pipe lines are notices on each corner of HP/IP casing by comparing the horn
drop test readings. The horn drop test will indicate the quality of work during
assembly/welding of pipe lines with the HP & IP casing.
This is a very important check and may cause serious problem in operation of the machine
like high vibration in the machine failure of barring gear in hot/cold machine, obstruction
during expansion of machine etc. In horn drop test a drop is measured on an individual
corner of the casing with the help of a dial indicator by removing the support of individual
corner and then it is compared with the opposite corner. As such this gives an indication of
indifferent loading of the casing. In Russian design machine the value of direct dynoxmetre
loadings are recorded in place of this horn drop test.
SWING CHECK
The swing check is the measurement of radial throw caused due to coupling face geometric
form of the two rotor coupled together. This is measured on opposite end of the coupling
and at the free end of the rotor. The higher swing check value may cause higher shaft
vibration, higher bearing shell temperature etc. The value of swing check depends on axial
run out of coupling faces, the diameter of the coupling and the length of the rotor. During
the machining of rotors in the works some tolerances are permitted by Designer's on the
coupling faces of the rotor resulting to some swing check values. The maximum swing check
values permitted caused due to the above tolerance for different diameter and length of the
rotor can be worked out from the enclosed graph. However it is recommended to keep the
minimum swing check values for better results during operation of the machine.
In a multi rotor Turbine-Generator system it is essential to measure the swing check value in
both extreme end and where the weight of the rotors are light. For example 200/210 M.W.
KWU machine with Russian Generator and static excitation system the swing check values
are measured on HP rotor front end only. In 500 M.W. machine the swing check values are
measured in H.P. front end and on exciter rear end. After having general experience of
number of 200 MW & 500 MW units, a necessity is felt to measure swing check value on IP
rotor front end also for better results during operation of the units. This can be done initially
during erection with temporary coupling bolts on LP-IP coupling before reaming/honing of
coupling. Any variation in swing check values may be corrected without any hesitation
during erection of machine. Any compromise at erection stage may cause serious problem
during operation of the unit and any correction becomes much more tedious a later stage.
The correction may be carried out either by interchanging the coupling position or by
correcting the coupling faces by scrapping/cutting in consultation of Designers.
 CONTINUED TO PART -XI

PS; I HAVE ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST
660 MW LP TURBINE IN PDF FORMAT. THOSE WHO WISH TO SEE MAY SEND REQUEST
ON MY EMAIL . THE SAME WILL BE SENT TO THEM FOR KNOWLEDGE PURPOSE.

P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE


28 comments:

  1. Dear Sir,
    Please send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
    My Email ID:phani.bhushanarao@gmail.com
    With regards,
    K.P.B.Rao.

    ReplyDelete
  2. Dear Sir,
    Please send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
    My Email ID:alokranjantpp@gmail.com
    With regards,
    alok ranjan

    ReplyDelete
  3. Hello Sir,
    Please send me the pictorial presentation of LP erection. I wish to see the horn drop test photos. please mail me ankush.tomar@yahoo.com.
    Thanking you

    With best regards,
    Ankush

    ReplyDelete
  4. Respected sir,
    Please send me the Assembly report of LP Turbine mentioned in this page.
    Thanks & Regards
    R.Nageswara Rao

    ReplyDelete
  5. Respected Sir,
    Please send the Assembly report of 660MW LP Turbine mentioned in this page end

    Thanks & Regards
    R.Nageswara Rao

    ReplyDelete
  6. Dear Sir,
    Please send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
    My Email ID:sha23nk@gmail.com
    With regards,
    Shashank

    ReplyDelete
  7. Dear Sir,
    Please send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
    My Email ID:bhavparmar@gmail.com
    With regards,

    Bhavesh

    ReplyDelete
  8. This comment has been removed by the author.

    ReplyDelete
  9. Dear Sir,

    Please share the "assembly report (pictorial) as prepared by BHEL engineer for 660 MW, we have come across the situation of failure of LP last stage blade in our unit-3 of BHEL SIEMENS design and undergoing overhauling at early stage.

    Your pictorial presentation will add knowledge of assembling LP Turbine and serve as a guide.

    My email'id is "ashutosh580@gmail.com", waiting for your quick response and thanks a lot in advance.

    With Regards,

    Ashutosh Gupta
    TPP- SR. Engineer

    ReplyDelete
  10. Dear please send me the report at Ashwani.nitk@gmail.com
    Regards

    ReplyDelete
  11. Dear Sir,
    Please send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
    My Email ID: swarupkumar2489@gmail.com

    With regards,

    Swarup

    ReplyDelete
  12. Dear Sir,
    Please send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
    My Email ID:yogeshyadav430@gmail.com
    With regards,

    yogesh

    ReplyDelete
  13. Dear Sir,

    please send me the report at patelchirag0011@gmail.com
    Regards

    ReplyDelete
  14. Please send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
    iamrangasamynew2018@gmail.com

    ReplyDelete
  15. This comment has been removed by the author.

    ReplyDelete
  16. Pls send checks conducted and procedures during turbine overhauling

    ReplyDelete
  17. Sir please send me 660 mw bhel steam turbine o&m manual in pdf for my best knowledge .Kamleshsaharan4@gmail. Com

    ReplyDelete
  18. Dear Sir,
    Please send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
    My Email ID: nga_ahirrao@yahoo.com
    With regards,
    Ahirrao

    ReplyDelete
  19. Please Send me the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST 660 MW LP TURBINE IN PDF FORMAT, to mbujairp@gmail.com
    Thanks in advance

    ReplyDelete
  20. Dear Sir,
    Please send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR 500 MW HP IP LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
    My email:dcm10287+500mwvtps@gmail.com
    With regards,
    Chaitanya Durga

    ReplyDelete
  21. Sir pl send assembly PDF pictorial
    With regards,
    Suraj

    ReplyDelete
  22. For above my e-mail is
    Surajrnr10@gmail.com

    ReplyDelete
  23. SIR PLS SEND INFORMATION ABOUT ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST 660 MW LP TURBINE.
    MY MAIL SHANMUKHARAO011@GMAIL.COM
    With regards,
    SHANMUKHARAO

    ReplyDelete
  24. Pl send me assembly report prepared by bhel engineer for first 660 me ko turbine
    Regards
    abhaidvc@gmail.com

    ReplyDelete
  25. Dear Sir,
    Please send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR 500 MW HP IP LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement. Also if possible then please send C&I documents related to 500MW and 660MW BHEL turbine.
    My email: mondal.ebay03@gmail.com
    With regards,
    A MONDAL

    ReplyDelete
  26. Dear Sir,

    May please share the Assembly Report of 660 MW Turbine on SKMANCHAL@GMAIL.COM.

    Regards,
    Sanjay Kumar

    ReplyDelete
  27. Nice Post! Ncon turbine in India is one of the leading Power turbine manufacturers with standard quality. You can check them out or contact their expert turbine engineers.

    ReplyDelete
  28. Please send me the Assembly report of LP Turbine. turbine rotor

    ReplyDelete