Pressure Part items are required at the beginning of starting of pre-assembly
Works.
If we assume start of erection of Boiler structure is Zero date. Then these
materials are required at site from 5th month of structural
erection. It has been observed
that Ceiling Girder with Welded beams and Rolled beams erection gets completed
within
six month. Completion of C.G erection is the starting
date of Pressure
Part erection.
Super Heater Final spaced inlet header
Super Heater Platen inlet header
Super Heater Final spaced outlet
header
Super Heater Platen outlet header
Super Heater final spaced assembly – Terminal Tube.
Super Heater Vertical Platen – Terminal Tube
Super Heater final spaced assembly – Terminal Tube
Super Heater Vertical Platen Coil -Terminal Tube
Re Heater vertical platen inlet header
Low Temperature Re Heater outlet
header
Re Heater Vertical Platen outlet header
Re Heater Vertical Platen Inlet & Outlet - Terminal tubes ( L &
R)
Low Temperature Re Heater Outlet terminal tubes
Following items will be required
sequentially on Pre-assembly bed. This will help
to maintain pace for Pressure Part
erection. Material required 2nd month onwards
are given below.
Furnace upper Rear outlet Header
Furnace front wall and side wall
interim header.
Furnace spiral upper front & rear
wall panels.
Furnace upper spiral wall panels - L
& R.
Furnace screen tube and hanger tube
SH front wall outlet header.
SH Radiant wall roof panel +
attachments.
SH rear roof panels left & right
Furnace vertical wall panels rear
LTRH upper coil and LTRH intermediate
Coil
Furnace rear wall interim header
Furnace upper wall
SH extended side wall
LTRH inlet header
Economiser outlet header
Economiser coil assembly- outlet
terminal tubes
Economiser coil assembly –upper ( L
& R )
Economiser interim plain tube (L &
R )
Furnace front ,Rear and side header.
Furnace Bottom supports
Economiser inlet header
Economiser coil assembly lower – inlet
terminal tubes.(L&R)
Above materials are required at site
from 2nd month to 7th month so that pre-assembly
works can be completed.
In India for a sub critical Boiler ( 500 MW) takes 09 to 11 months for readiness of drainable
Hydraulic test from start of Pressure Part erection. For other developed countires Hydraulic
test is being done for non- drainble and drainable portion. There are advantages and dis advantages
for both the system. The same will be elaborated afterwards. Materials requirement for super
critical boiler is based on 12 month cycle for drainable Hydraulic test.
To achieve this we need to start preparing pre-assembly bed from 5th month of structural erection.
At least four beds are required outside the boiler cavity and two number bed inside cavity. The
bed area should be near to the actual space of erection with the facility of transporting 18 M
panels ,coils , headers etc . Four numbers hydra cranes , one number 18 MT crawler crane , one
number 50 MT crawler crane to be deployed for the job at both the places. If it is possible a
temporary rail line can be laid to transport the material from outside bed to boiler cavity area.
Therefore a proper layout plan to be prepared before start of pressure part erection. There will
be lot of space problem and conflict with other works . Few photographs are being attached .
We have not been able to establish railway line but we have achieved to create nuber of beds
for pre-assembly outside boiler .
This pre-assembly bed is inside cavity. otherwise it is impossible to transport the same from outside.
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
No comments:
Post a Comment