Total Pageviews

Tuesday 27 May 2014

TURBINE GENERATOR PKG ERECTION PART-XII, SPRING ERECTION AND RELEASE - ABC OF THERMAL POWER PLANT.


Earlier days up to 250 MW most of the foundation was rigid and casted along with the main column foundation. But now a days all the TG deck foundation are casted having Spring /viscous dampers in between. This type of foundation has some added advantage on turbine erection and size of turbine column. All the foundation above 500MW and above is having such type of foundation. In BHEL we use GERB spring as our standard spring supplier wherever I worked.

 The spring element in 500MW machines and further higher rating machines are used with visco dampers. The springs units are not supplied to site with required pre-tension values through these are supplied with some amount of pre-tension. The required pre-tension of the spring units are done at site before its installation in position. A special device for pre-compression of these springs units is also supplied by spring supplier.

The shuttering of RCC slab of TG deck is furnished before installation of these spring units. The top surface of individual column where these spring units are mounted should be within accuracy of +00 mm to -3.00 mm. If necessary these may be corrected by chipping before installations of the spring units. The level deviation among various columns is permitted +00 mm to -5.00 mm in total including individual column variation of +00 mm to -3.00 mm.
The bottom shuttering of pedestal must be cut over the column head for lowering the spring units.

After lowering the spring unit the cover steel plates are placed in position with shuttering supports.

An air gap of about 5.00 mm to 10.00 mm is left between cover plate and spring units for

settlement of deck during casting. The visco dampers are also filled up at site only with visco liquids

supplied by spring supplier. Each spring units are placed over the resistance pad to avoid movement

of the spring units during operation of the machine. Similarly the resistance pad is given on top of the steel shim to avoid the shifting of the shim during operation of the machine. Each spring unit is provided with 10.00 mm of steel shim for future adjustment.


The TG deck springs are released after installation of all Turbine Generator components including piping and the condenser has to be filled up to operating level including CW pump in operation for full load condition. The shims provided for additional compression of the spring units are also adjusted during this stage, the final alignment of various rotors and turbine casing are done after release of the spring unit. The Generator hydrogen cooler & LP heater if any inside the condenser are to be filled up in cooling water space for their operating condition before release of TG desk spring. The insulation of various casing / pipe lines including cladding if any are also to be installed otherwise the equivalent weight is to be incorporated before release of desk spring. All the pipe lines connected with the Turbine and Generator should be made available on permanent hangers and supports to avoid any additional load on the TG deck afterwards. The TG deck should also be made free all- around to avoid any obstruction in its movement.


During release of TG deck springs and final alignment of rotors the condenser spring is also to be kept in floating condition considering that condenser neck welding is already done. Similarly the condenser spring measurement should be with in + 1.00 mm otherwise the shims may be adjusted in condenser springs. No adjustment of TG deck springs or condenser springs are permitted after final alignment of the rotors. During any subsequent adjustment of TG deck spring the final alignment of all rotors are to be checked.
There are finer points of spring installation and releasing but we need not to discuss now. Basics of installation and releasing are given above. There are few important activity  needs to be performed which will be indicated very briefly.
- Condenser neck welding having spring loaded foundation.
- Assembly of breach nut.
-Turbine Insulation
- Turbine Integral piping and other piping. It is better to identify the scope of piping between IBR/Non IBR. This demarcation should be available with construction man. Any deviation from IBR norms will attract problems from statutory authority. Therefore system wise identification is needed. In general oil lines ,water lines ,air lines and Gas lines are not under IBR but some of the steam lines are under the scope of IBR. Interpretation of IBR authority varies from state to state therefore one should take state IBR authority in confidence.
For above works it is advised to follow the OEM’s practice in vogue. All the OEM ( original Equipment Manufacturer)  detailed it in there erection manual.
One should follow the approved FQP ( field Quality Plan)  for measurement and records of various reading in the log sheets of FQP . This will help in analysing any future problem.
PS:- I have a eight page technical document given by M/s GERB with supplied spring. Interested person to receive the document as reference may send request to my mail
dguha1952@gmail.com
Civil protocol for placement of VIS. Please note the number of reading.




 

1 comment: