Part –XI
Sealing and anti seizing compound used
in turbine as per BHEL ‘ s Turbine manual.
========================================================================Joint plane of hpt ipt & valve casings, gland boxes & strainer housings, breech nut mating face.
- Metal to metal joint in high temperature zone
- Use − Birkosit ,− Stag B ,− Magnesite compound of
bhel standard.
================================================================
Joint plane of LP outer casing
(without rubber sealing chord).
-Metal to metal joint in low
temperature zone
-Use Holdite and Loctite 574
================================================================Joint plane of bearing pedestals, mop casing, valve servomotor
Metal to metal joint in oil
environment
- Hylomer , Golden Hermetite and Victor
Shellac .
=================================================================
Threaded fastners including,
breech nut threads, keys, packers,
Dowel pins u & i - seal
rings in high temperature zone.
high temperature ( < 350°c)
antisiezing . Use molykote p37 and oks 255
=================================================================
Threaded fastners, keys,
packers, dowel pins in low temp. zone, coupling bolts seal
segments, hp/ip casing palm
packers, hp front & rear bearing pedestal packers (other
than self lubricated lubrite
packers . i.e low temperature ( <
350°c) antisiezing
use Molykote d 21, Oks 511, Mgs 400
=================================================================
Tips on different aspect of Main
Turbine Erection.
-When ever JOP is not available,
use always thick oil during rotation of shaft over
bearing.The type of oil may be
used as servo cylinder 1000 grade of IOC.
The bearing parting plane bolts
are to be tightened to required torque only no other
method of tightening of these
bolts may be used.
-Alignment and coupling of HP-IP
and LP rotors are to be completed before starting the
rolling test of the casing in
normal case but this can be done without coupling of LP rotor
-No inlet and outlet pipes are to be welded with the
casing till completion of rolling test
and installation of final keys and packer of the
casing.
After completion of the rolling test the installation
of final keys and packers of the H.P.
and I.P. casing, the same can be cleared for welding
of inlet and outlet pipelines. The
main steam inlet line from main steam strainer to the
control valves and then from
control valves to the H.P. casing need much more care
during erection / welding of the
pipelines. Similarly the Hot Reheat lines between two
Hot Reheat strainer to the control
valves and from control valves to the I.P. casing
also need equal care during erection /
welding of these pipelines.
- Projections of these axes in the corresponding drgs. shall be as
under :
X axis = view toward generator
Y axis = view upward generator
Z axis = view to the right
-The breech nut assembly used in between connection
of main steam inlet line and HP
module. A special care is must while making the breech nut
assembly first time at site
during erection stage. Follow the OEM instruction
carefully.
ERECTION SEQUENCE (For 500 MW Fixed pedestal type
Turbine with spring loaded
foundation) – BHEL MAKE TURBINE
1. Cleaning and checking of Turbine
and Generator foundations as per the transverse and
longitudinal axis including their
elevation.
2. Prepare and install LP base plates,
HP front pedestal, HP rear pedestal, LP front pedestal,
LP rear pedestal along with their
anchor bolts and anchor plates.
3. Provisionally align and level all
the pedestal and LP base plates as per the transverse and
longitudinal axis including their
elevation.
4. Matching of anchor plates of
pedestal and LP base plates to ensure their perfect seating.
5. Finally align and level HP front,
HP rear, LP front and LP rear pedestals along with LP base
plates as per the transverse and
longitudinal axis including their elevation and catenary as
per the design.
6. Prepare and install steel bars for
LP casing centralising keys in foundation slab as per the
required centre line .
7. Weld locating ring of LP front
pedestal and steel bars of LP front and LP rear centralising
keys.
8. Prepare shuttering and grouting of
the pedestals and LP base plates including anchor
plates of HP rear pedestal.
9. Prepare, install, align/ level both
the LP girder along with their carrier plates.
10. Prepare , install and assemble LP
front and rear end walls with the LP girders.
11. Level / align LP outer casing
lower half as per the transverse and longitudinal axis of the
machine.
12. Install permanent packers of LP
outer casing including their radial and ax14. Align LP inner outer
casing lower
half and level it. Install LP casing parting plane platform .
13. Prepare and install LP inner outer
casing along with gusset plates in position
14. Align LP inner outer casing lower
half and level it. Install LP casing parting plane platform.
15. Prepare and install LP front and
LP rear lower half shaft seals housing and align it provisionally.
16. Prepare and install LP rotor along
with their bellows in position.
17. Align LP rotor radially and
axially in position and record free run out of rotor.
18. Record/ Ensure radial and axial
clearances of the LP casing including rotor float including
fitting of final axial keys of the LP
inner casing .
19. Box up LP inner inner casing and
heat tighten the parting plane bolts.
20. Box up LP inner outer casing.
21. Prepare and place HP module in
position on temporary packers.
22. Transfer the load of HP rotor on
bearings from the transport device and align it radially
and axially.
23. Check free run out of HP rotor on
journal and coupling face including its float.
24. Prepare and place IP module in
position on temporary packers. (In case IP module is sent
to site in disassembled condition.)
25. Loading of IP rear end of the
shaft on bearing and removal of transport device.
26. Provisionally align HP, IP and LP
rotor.
27. Couple HP / IP rotor on temporary
Bolts and align rotor / casing radially and axially.
28. Record/ Ensure IP rotor float by
shifting HP casing axially.
29. Conduct Horn drop test of HP
casing without any radial and axial keys and pipe lines.
30. Conduct Horn drop test of IP
casing without IP inlet upper half pipe lines.
31. Assembly of breech nut of HP
casing and Main Steam Stop & Control valve assembly.
32. Erection of Reheat Stop &
Control valve assembly.
33. Weld IP inlet upper half pipe and
record Horn drop values without radial-axial keys.
34. Alignment of HP/IP/LP rotors and
their coupling on temporary bolts including its couple
run out.
35. Swing check of HP rotor on its
front end with temporary alternate bolt tightened on
HP/IP coupling.
36. MOP alignment and its doweling.
37. Reaming/honing of HP/IP and LP/IP
coupling including fitting of final coupling bolts.
38. Fixing of axial position of shaft
and assembly of thrust bearing including its colour
matching.
39. Roll check of HP/IP casing and
fixing of radial and axial keys of the casing (Casing final
packers need not to be put at this
stage).
40. Assembly of bearings and checking
of all clearances including fittings of side pads of
bearing, yoke keys etc.
41. Turbine Supervisory Instrument works in all the
pedestal i.e. assembly and calibration of thrust
bearing axial shift, LP rotor expansions pick up,
Hall generator and thermocouples of bearing .
42. Preparations of the bearing for
oil flushing.
43. Oil flushing of the machine and
normalizing the bearing after oil flushing.
44. Preparation and floating of TG
deck as per OEM instruction.
45. Decoupling of HP / IP, LP/IP,
LP/Gen., Gen./Exciter coupling and rechecking of
alignment/catenary after floating of
TG deck spring.
46. Final tightening of HP/IP, IP/LP ,
LP/Generator and Generator / Exciter coupling after
correcting the alignment including
their couple run out and swing check of rotor on HP Front
and exciter rotor.
47. Checking /Correction of LP shaft
seal clearance after floating of TG deck with CW pump
in operation and water in the hot well
of condenser up to operating level.
48. Roll check of HP, IP casing in up
and down direction only with TG deck in floating
condition and CW pump in operation
including water in hot well up to normal level.
49. Assembly of final packers of the
HP, IP casing after completing the roll check in up and
down direction.
50. Recording of final Horn drop of HP
and IP casing after completing the welding of HP
inlet, HP exhaust , IP inlet and Cross
around piping.
51. Preparation and boxing up of LP
casing after competing the full Roll check of LP casing
and fitting of final casing packers
and radial keys.
52. Barring gear.
Continued to Part -XII
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
This is such an amazing site! I really enjoyed reading the content. Thanks!
ReplyDeleteBearing House in India