Total Pageviews

Saturday 3 May 2014

TURBINE GENERATOR PKG ERECTION PART-IX, ALIGHNMENT OF HP,IP AND LP TURBINE ,COUPLING ETC.- ABC OF THERMAL POWER PLANT.


PART- IX

PLACEMENT OF LP ROTOR

Measure journal diameter, spigot diameter and coupling hole sizes.

Ensure centring of temporary bearing support in the LP front pedestal for placement of LP

rotor.

Place LP rear bearing in position.

Prepare shaft seal compensator along with gaskets (Gasket to be installed in fully ring shape

only) and position them on LP rotor with the help of supplied supports of compensator.

Lift LP rotor with the supplied lifting beam in perfectly level condition and place it in

position. During lowering of rotor ensure radial clearance with the help of long feeler gauges



in the LP casing.
WELDING OF LP OUTER CASING
The welding of LP outer cover is to be carried out before placement of LP Rotor in position
to avoid damage to the rotor.
Colour match and remove all high spots of the matching flange of the LP outer casing.
Ensure good contact between parted diffuser of LP front and LP rear cover.
Colour match and remove all the high spots of the parted diffuser/vertical face to ensure
good contact with the compensator at a later stage.
Colour match and remove all burrs and high spots from parting plane of LP outer casing.
Side flange of LP front and rear cover are to be ensured in right angle to achieve good
contact with their matching flanges.
Place LP front LP rear cover along with parted diffuser and ensure feeler tight joint after
tightening the parting plane bolts. The joint must be feeler tight just after normal tightening
of bolts. Do not over tighten parting plane bolts.
Ensure matching of parted diffuser face on both side of LP casing. If necessary colour
matching may be carried out to achieve a feeler tight joint.
Drill/ream all the parting plane holes as per drawings and install all dowel pins.
After fixing of LP front and rear cover measure the dimension for positioning of both the
centre flanges. The dimensions are to be recorded in such a way that there is no clearance
after fitting of centre flanges in position on both side with the LP front and rear cover. The
centre flanges are supplied in extra length on both sides from the factory and final length
are to be maintained at site only.
Drill/ream dowel pin holes in centre flanges and install all dowel pins in position. Ensure
drilling and reaming of all dowel pin holes to equal depth.
Fit both the centre pieces of the cover in position.
Achieve the fitting clearances for welding as per laid down procedure.
Weld/lock LP upper half flange with respect to lower half casing with the help of metal
cleats to minimise the distortion during welding of LP cover. The cleats may be welded at an
interval of about one meter distance.
Carry out the welding as per the following welding procedure.
Follow the welding procedure and sequence of welding as suggested by manufacturer.
ALIGNMENT AND COUPLING OF LP-IP & HP ROTOR
LP rotor is to be aligned on pedestal seal bore and LP inner outer casing is to be centralised
in such a way that enough clearances are available to LP rotor, during alignment. Now this
alignment activity of all the three rotor can be divided as below :
-Preparation of HP rotor for alignment.
-Preparation of IP rotor for alignment.
-Preparation of LP rotor for alignment.
-Alignment of LP-IP & HP rotors.
-Reaming, honing of the coupling holes.
-Balancing of coupling bolts weight.
Alignment preparation of individual rotor ( i.e HP,IP and LP) to be completed as per OEM ‘s
instruction manual and this is not discussed here. I am going to the next step.
ALIGNMENT OF HP, IP AND LP ROTORS
-Ensure radial and axial run out of all the three rotors are individually in order. If necessary
Individual rotor module can be taken out for correction of coupling face run out. Any
Variation on radial run out of rotor is to be referred to the factory.
-Match coupling faces of two rotor as per the axial face reading of the rotor. Ensure that the
higher point of the rotor coupling face and lower point of another rotor coupling face are
matched together. This is to be compared with shop protocol also.
-Preliminary align (radial and axial) all the three rotors and shift them in spigot along with
the  casing to avoid fouling of rotor inside the casing.
-During alignment achieve left and right movement of the rotor with the help of shims in
spherical / torus piece of the bearing. The up and down movement of the rotor is to be
achieved with the help of shims in the cylindrical/spherical support of the bearing . The
adjustment of shims in the bearing should be within the permissible limits only. 
-Ensure during alignment that the catenaries of the shaft are maintained. 
-Check/record spigot clearance of HP-IP and LP-IP rotors by actually moving them in spigot.
Install four nos. supplied bolts along with one/two pins in HP-IP and LP-IP coupling. Hand
tighten the coupling bolts by keeping a gap of > 1.00 mm in coupling faces for alignment.
Rotate the rotor system and record the coupling gap at 90 Deg. intervals on left, right and
top position. Ensure that the coupling, bolts and pins remain free while recording the gap of
the coupling for the alignment purposes.
-Check swing check value of the HP rotor with alternate bolts in position. The above value
must be within the prescribed limit only otherwise a correction must be carried out at site in
consultation with designer.
-Ensure free movement of rotor on their bearing. Do not rotate the rotor if it is tight during
its rotation.
-Ensue that the coupling holes are properly aligned to avoid unnecessary enlargement of
holes.
-Ensure HP-IP-LP rotor radial run out after tightening with alternate clearance bolts. Release
the couplings for reaming / honing of couplings.
REAMING / HONING OF COUPLING
Ensure that there is no disturbance on coupling during reaming/honing operation.
First ream/hone two opposite holes of the coupling and install two pins/bolts with sliding fit
and then take up all other holes.
Enlarge coupling holes to the minimum possible diameter and try to make all the holes to
same dia.
Ensure that the finished holes are straight and there is no banana shape. This can be
ensured by checking hole with a straight ground finish pin having 0.02/0.03 mm clearance.
Reaming ,Honing of coupling holes is an expert job for machinist and not the job of erectors
. Therefore it will be better to engage professional service to do this job.
BALANCING OF COUPLING BOLTS
After fitting the coupling bolts in all the holes these are to be balanced within +/-5 gms
accuracy and an accurate balance which can take a load of about 20 kg. may be used. During
balancing of coupling bolts following points are to be taken care.
Final balancing of the coupling bolts are to be done along with the coupling nut of individual
bolt.
If all the coupling bolt hole sizes are same before/after reaming and honing then all the
bolts can be kept of equal weight.
If necessary adjust the weight of the bolts by machining the metal from the bolt head.
COLOUR MATCHING OF THRUST BEARING
After completion of reaming/honing and preliminary tightening of the coupling bolts, the
colour matching of the thrust bearing pad have to be carried out with respect to the thrust
collar of the HP Rotor. During colour matching a good contact on all the pads of front and
rear side are to be ensured with respect to rotor collar by moving the rotor in +/- direction
during its hand rotation.

CONTINUED TO PART-X

P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE

No comments:

Post a Comment