Part –VI
GROUTING OF PEDESTALS AND LP BASE
PLATES
Technical Requirements of Grout material used
for turbine pedestal grouting.
Compressive Strength, Non-Shrink - the compressive strength at 28 days must be
not lower than 50 N/mm² .
The early compressive strength at 24
hours must not be lower than 24 N/mm²
- the grout may not shrink. In
addition a certain swell-rate is desired (volume increase within 24 hours: atleast
0.2%; according to ASTM C 827-95a). The grout must be water and oil resistant.
The basis of the grout must be
cement. It may not contain metallic components and added chloride or other
admixtures that may corrode steel.
After adding of water the
grout must be in fluid state .In order to improve the flow a high water content
should be preferred within the admissible range specified by the manufacturer. The
grout should be workable for approximately 45minutes and shall not segregate
after grouting.
The specified range of suitable grouting heights
must be considered for each application. In case of a too wide grouting height cracks may occur due to strong heat development. If the grouting height
is too narrow the flow of the grout may be not sufficient and air pockets may form. Where grouting
heights cannot be complied with, a different grout type suitable for the grouting height shall
generally be used. In exceptional cases, a grout may be used for a larger-than-specified grouting
height if a stone aggregate (e.g. quartz) with a specified maximum grain size is
added. The manufacturer's
instructions should be followed exactly. In our case
we generally keep the
heights between 50 to 70 mm.
The processing instructions and
specifications of the grout manufacturer must be complied with. Particularly
with regard to the amount of water to be added, the processing temperature, the
mixing process, as well as the permissible grouting height. Only drinking water
may be used for adding to the grout. Concrete mixers shall be suitably sized .The
duration and intensity of the mixing process must also be sufficient .No vibrator
shall be used in pouring the grout. Grout should be free flow (working into place) may be aided by
manual.
Fill 3 to 8 mm washed Pea-gravel in
all the anchor bolts sleeves. These gravel are necessary to give damping effect
to the anchor bolts during operation of the machine.
Seal anchor bolts holes after filling
of gravel to avoid any entry of grout metal.
Cap ,tapes etc may be used for sealing .Clean foundation with compressed
air. Make shuttering of all the pedestal and LP base plates. Use thick
polythene sheet inside the shuttering to give better finish and avoid moisture
absorption by shuttering.
Shuttering should be made with
maximum care to avoid any leakage of grout concrete. All sides of the
shuttering are to be sealed either with some sealing compound or with thick
mixture of grout material to avoid leakage of grout material.
Foundation are to be kept wet for
about 6 hrs. before grouting.
Non shrinkage cement duly approved by
turbine manufacturer is to be used for grouting of the pedestals and base
plate. In India we generally use Pagel cement from Pidilite , Conbextra GP 2
from Fosroc , SIKA 214 (ACC) and Five star cement company.
Use fresh stock of the grouting
material only and check the strength of the material before use. Every batch of
the supply should be tested through cube test if the supply is not of same
batch. No material ( grout cement) to be used without testing.
During grouting, the mixture has to
be poured from one end only and it has to flow to opposite end to avoid any
blockage of air pocket.
Water curing is to be carried out for
about 10 days duration.
All anchor bolts are to be stretched
minimum after 21 days of grouting.
HP, IP & LP module placement work
can be taken up after 24 hours of grouting of the pedestal and base plates.
For individual pedestal and base
plate, grout mixture should be poured in one lot only.
It is recommended that supplier
representative (technical) is present during grouting of pedestal and LP Base
plates and grouting is to be done under their technical supervision.
BRIEF TECHNICAL SPECIFICATION OF BHEL
MAKE 500MW (TURBINE)
LOAD ( RATED) 500
MW
MAX. UNDER VALVE WIDE OPEN (VWO)
CONDITION 524.2
THREE CYLINDER REHEAT CONDENSING
TURBINE 500 MW
SINGLE FLOW HP TURBINE WITH 17
REACTION STAGES
DOUBLE FLOW IP TURBINE WITH 12
REACTION STAGES PER FLOW
DOUBLE FLOW LP TURBINE WITH 6
REACTION STAGES PER FLOW
2 MAIN STOP AND CONTROL VALVES ( ESVs
and HPCVs)
2 REHEAT STOP AND CONTROL VALVES (IVs
and IPCVs)
1 SWING CHECK VALVE IN COLD REHEAT
LINE
2 BYPASS STOP AND CONTROL VALVES
EXTRACTION SWING CHECK VALVES :
EXTRACTION-1 NO VALVE
EXTRACTION-2 1 SWING CHECK
VALVE WITH ACTUATOR
EXTRACTION-3 1 SWING CHECK VALVE WITH ACTUATOR
& 1 SWING
CHECK VALVE
WITHOUT ACTUATOR
EXTRACTION-4.1 2 SWING CHECK VALVE WITH ACTUATOR
EXTRACTION-4.2 2 SWING CHECK VALVE WITH ACTUATOR
EXTRACTION-5
1 SWING CHECK VALVE WITH ACTUATOR
& 1 SWING CHECK VALVE WITHOUT ACTUATOR
EXTRACTION-6
NO VALVE
SPEED (RATED SPEED)
50.0 /S
RANGE
47.5 TO 51.5 /S
STEAM PRESSURES RATED*
INITIAL STEAM 166.7 BAR
BEFORE 1st HP DRUM STAGE 154.4 BAR
HP CYLINDER EXHAUST 44.9 BAR
IP CYLINDER STOP VALVE INLET 40.3 BAR
EXTRACTION 6
44.9 BAR
EXTRACTION 5 17.5 BAR
EXTRACTION 4 7.2
BAR
EXTRACTION 3 2.58 BAR
EXTRACTION 2 1.329 BAR
EXTRACTION 1 0.257
BAR
LP CYLINDER EXHAUST 0.1013
BAR
PRESSURE IN SEAL STEAM HEADER (ABOVE ATMOSPHERIC) 35 MBAR
STEAM TEMPERATURES RATED
INITIAL
STEAM 536.0
IP
CYLINDER STOP VALVE INLET 536.0
HP
CYLINDER EXHAUST 340.0
EXTRACTION
6 340.0
EXTRACTION
5 413.9
EXTRACTION
4 292.1
EXTRACTION
3 187.3
EXTRACTION
2 128.3
EXTRACTION
1 66.5
LP
CYLINDER EXHAUST 46.1
CONTINUED TO PART -VII
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
Very informative post.
ReplyDeleteFor more information on grouting chemicals: click here
We Supply Pagel V1, Pagel V1/50, Sika Grout 214 and Conbextra GP2 grouts to all over India in Industrial plants for Grouting work. Kindly contact us on: concretecare@gmail.com
ReplyDelete