Total Pageviews

Thursday, 10 April 2014

ERECTION OF TURBINE GENERATOR PKG PART-VII, PLACEMENT OF HP MODULE ,IP MODULE- ABC OF THERMAL POWER PLANT.


PART- VII

PLACEMENT OF HP MODULE IN POSITION

Ensure matching of all the four palms of the module where it is resting on the pedestals.

Ensure matching and paralleling of front and rear key block of the HP casing.

Assemble all four jacking screw of HPC and ensure their free movement.


Clean journals and coupling of the HP rotor.
Record journal diameter, coupling hole sizes and spigot diameter of HP rotor.
Lift module in level condition and place it in position by keeping it 3 to 5 mm toward front pedestal side.
During placement of module use temporary packers similar to permanent and additionally support it by four jacking screws.
Ensure load on all four packers with the help of some additional shims if required.
Install temporary radial and axial keys of the casing.
Prepare HP rotor for alignment
PLACEMENT OF IP MODULE IN POSITION
Ensure matching of all the four palms of the module where it is resting on the pedestals.
Ensure matching and paralleling of front and rear key block of IP casing.
Assemble all four jacking screws of IP casing and ensure their free movement. If these jacking screw holes are provided with the bolts from factory then same are to be removed before placement of module.
Clean IP rotor on both sides including coupling and journal.
Record spigot /recess, journal diameter, and coupling hole sizes.
Lift the module in level condition and place the module in position by moving about 7 to 8 mm towards generator end. Use temporary packers for placement of module in position and additionally support the module with jacking screws.
Ensure load on all four packers with the help of some additional shims if required.
Provisionally align the casing on front and rear pedestal bore. Install temporary radial and axial keys of the casing with some shims.
Prepare IP rotor for alignment
Following measurements are carried out during positioning ,alighnment of  HP cylinder module.
Journal diameter and corresponding Bearing-bore.
Spigot and Recess dimensions of Couplings.
Out of flatness of coupling Faces (within 0.02 mm concave) & Coupling hole diameter.
Transverse & Axial alignment of HP Rotor with Bearings & seal bores during its Placement on the Bearings
Centring and axial position of HP casing w.r.t. rotor

Check parallelism during tightening of Breech-nut on HP Inlet Insert.
Assembly of Hydraulic turning Gear with HP Rotor. Check Clearances . Assembly of Emergency Governor.
HP rotor float and Roll check.
For measurements we use instruments ( calibrated to national standard)  Vernier Caliper, Micrometer , Dial gauge , Straight Edge , Depth Micrometer , Filler Gauge etc.
HP module of 660MW turbine is under placement.

660 MW IP module under placement.
Continued for Part-viii
P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE





1 comment:

  1. sir, could you please give me your E-mail ID??

    ReplyDelete