CRANES FOR THERMAL POWER PLANT # 4


The above crane is 1200 MT crane towering above the boiler. The crane has been kept on side of the boiler and does erection.The boiler structure is such that crane positioning  should be at site. In that site same capacity units are getting erected however erection strategy for both the companies are different . One company 's strategy is do the erection in U-formation thus high capacity crane to be placed in the cavity.

The ultimate capacity of crane( crawler) for Power house is guided by size and type of Boiler we are having. In all practical purposes ceiling Girder wt and size play crucial role on deciding the size. Height of the boiler / ceiling girder placement height plays significant role in this issue. There is other
method of ceiling Girder ( strand Jack ) method but that is never been popularised. In fact one of the
site this was followed but due it was noticed that placing jack on and above the girder huge amount of structural member  has to be lifted earlier to place the jack. All in all big crane was necessary to lift the members of strand Jack.

Now we will discuss about the system on which high capacity cranes with other major construction
equipments are used. However at present we will restricted our discussion only on cranes.

1. Steam Generator : 600MT /1200MT - One number ; 250T/350T crane two numbers ; 120MT/150MT capacity -two numbers , 100MT/ 75 MT class -04 nos . Out of which one number crane will be tyre mounted  with telescopic boom.

(We assume that Power House is having 2x660MW capacity and having phase gap of 06 months between the units)

2. ESP ( Electrostatic Precipitator )  - 2 nos 100MT crane.

3. Coal Handling Plant - 250MT/350MT crane -two numbers ; 120MT/150MT class 02 nos and 100MT /75 MT class -three nos . out of which one should tyre mounted telescopic boom.






to be continued.

P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE

2 comments:

  1. Thanks for sharing this useful information.I was looking for this type of blog so thank you for sharing this information with us.
    click here

    ReplyDelete
  2. Sealand Support Crane Load Test Services in Cameroon for davits and boats rescue performer to assure safe operations of ships loading and handling in the gulf of guinea. it uses calibrated load cells and class approved water bags of capacities above 50 & 100 tons for ships and cranes used on construction sites.

    ReplyDelete