ERECTION AND COMMISSIONING OF TURBINE GENERATOR PKG PART-II ABC OF THERMAL POWER PLANT.


part-2 Turbine



Turbine foundation will be done by Main civil vendor.
In earlier days turbine foundation was casted as a single unit. But now a days springs are introduced in between . Therefore bottom portion of the turbine columns are casted then springs were installed after that top portion of the foundation are being casted. In India most of the spring are supplied by manufacturer called GERB. This technology introduced in India since twenty to twenty five years. Feedbacks are not available how the machine behaves in longer run.
The advantages of spring loaded foundation are given below.
1.  The vibration to the main column is isolated by the spring element resulting to small size base mat which reduces the construction cost and time.
2. The same column of TG deck may also be used to support surrounding floors at the building, so that the total numbers of columns are reduced and the space to accommodate more equipment is increased. This results in more rigidity of building structure of surrounding floors and further in cost saving.
3. Excessive settlement of column can easily be adjusted by inserting or removing shims in spring units.
4. It is possible to tune the foundation subsequently by replacing the spring elements having different load capacity of the springs.
5.
Machine will have more steadiness and stability in the event of earthquake compared to normal foundations.
FOUNDATION CHECKING BEFORE CASTING
Get centre line and elevation point both side of the turbine foundation and make arrangement for piano wire fixing.
Check positioning of all the inserts and fixed points with respect to centre  line in transverse and longitudinal direction as per manufacturer drawings and civil drawings. Discrepancy  if any to be resolved before casting. A typical inserts plate drawing was given on  part-I of this blog.
Check elevation of all points.
Check verticality of all the pipe sleeves with the help of plumb.
Ensure proper locking of all  insert and fixed points before grouting.
Ensure levelling on the fixed points of LP girder and LP rear pedestal.
Preserve machined surfaces of all the fixed points against any damages due to handling.
Ensure proper flatness of the bottom seating plate of all the inserts.
Ensure proper stiffeners in all the vertical and horizontal embedment provided for various purposes like hangers and supports etc.
Ensure proper cleaning of the area before casting.
Remove all unwanted material.
All data to be noted in tabular form for future reference.
Checking should be carried out after completion of all reinforcement fixing and completion of shuttering including supports of shuttering. It may one or two embedded part approach will be not be easy. Take suitable decision on the spot regarding checking. Transfer the reference point to adjacent column for future reference.
A typical picture of turbine top deck after casting is over. ( Picture of 660 MW)
continued to Part-iii