In
our last dispatch I have discussed about the acid cleaning of steam generator
with HCL. Further steps are given below after acid cleaning.
DM RINSE
Re-fill
the boiler by running the boiler fill pump with DM water heated to a
temperature of 60 deg C – 65 deg C taking care of the operation of the drum
vent valves to maintain 0.5 kg/ cm2
of N2 pressure in the drum. Fill the water to
the centre of the gauge glass. Now raise the level in the drum by 100 mm, by
back flushing the super heaters. This will also remove, if any trace of acid
vapor lodged in the connecting links to the super heaters. Now run the boiler
water circulating pump, that was operated earlier for 5 minutes. Drain the
boiler under Nitrogen Capping as
earlier. Once the feed links, water walls and economiser draining is
completed, close the drain valves and retain Nitrogen atmosphere in the system.
Ammoniated Citric Acid Rinse
Prepare a solution of citric acid with the required quantity of
citric acid monohydrate and liquor ammonia in the chemical mixing tank. Keep
the solution under recirculation for better mixing.
Start
filling the boiler simultaneously through the Boiler circulating pump suction
header, water wall and the economiser with hot DM water restricted to a
temperature of 60 to 65 deg . C. Simultaneously start injecting ammoniated
citric acid solution.
Maintain
an uniform strength of 0.2% acid in the
water taken into the boiler. Adjust the PH. of the final solution entering the
boiler between 3.5 and 4.0. Continue the filling operation, till the level in
the upper drum is close to the bottom of the gauge glass. Raise the level in
the drum by another 30 to 40 mm by filling through the economiser by closing
the valve in boiler circulating pump suction header and continue filling through
bottom drum and economiser so as to fill economiser and water wall connecting
links. Further bring up the level in the drum to + 100 mm by back flushing the
super heaters. Start the same boiler water circulating pump that remained in
operation earlier, run it for 5 mts. and shut it down. Collect the sample from
CBD sampling provision and check for acid % and iron concentration. When lron
concentration attain a steady state value for 2 consecutive readings declare
citric acid rinsing is completed. In any case it will not be completed in less
than 4 Hrs. or more than 5 Hrs. Close the drum vents and establish nitrogen
supply. Drain the boiler under a positive nitrogen pressure.
DEMINERALISED WATER(DM) RINSE
After draining the citric acid solution, fill the boiler with DM
water heated to 60 deg – 65 deg C. Raise the level in the drum up to + 100 mm
mark. Operate the boiler water circulating pump for 5 minutes. Stop the pump
and drain the boiler under nitrogen capping. Repeat the filling and the dumping
operation under Nitrogen Capping till the iron content in the sample collected
is less than 50 ppm. It is preferable to lower the iron value to less than 25
ppm.
Maintain
the nitrogen pressure of 0.5 to 1 kg/ cm2 and maintain the nitrogen atmosphere in the system
till the next process of neutralisation is started.
NEUTRALISATION
This
process is employed to neutralize any acid/acidic pocket remaining in the
system and also to mildly passivity the acid pickled surface. This prepares the
base for achieving an effective final passivation. For this process, the boiler
system and the necessary instrumentation should be made ready to make firing
feasible. The ‘U’ tube manometer provided for the acid pickling in the drum
should be replaced by the gauge glass used for alkali boil out. All the boiler
water circulating pumps should be made ready for operation.
Prepare
the neutralizing solution in the chemical mixing tank with approximate
quantities of di-sodium phosphate and tri-sodium phosphate to get a concentration of 0.1% and 0.2%
respectively in the boiler. Re circulate the solution in the tank for better
mixing.
Start
filling the boiler with DM water, with simultaneous injection of phosphate
solution, maintaining uniform concentration throughout the filing period. Keep
the drum vents open while filling. The boiler filling is to be done as per
standard practice. Start the boiler water circulating pumps as per the O &
M instructions. Fire the boiler and gradually raise the pressure to 10kg/ cm2 . Follow the precautions as detailed out for
alkali boil out. Hold the pressure at 10 kg/ cm2
for about 4 hrs. Utilise this opportunity to
blow off all the instrument lines that might have come into contact during acid
pickling time, for better neutralization of those lines.
After
4 hours, kill the fire, allow the boiler to cool and drain the boiler as per
procedure explained earlier and O & M instructions. While draining back
flush the super heaters with DM water conditioned with hydrazine and ammonia.
The boiler is drained with the drum vents open to the atmosphere. Allow the
system to aerate. Prepare the boiler for passivation.
PASSIVATION
The
underlined idea is to form a protective magnetite coating on the steam
generating and water touched surfaces that were exposed to the picking process.
Prepare
a blended solution of hydrazine and ammonia with calculated quantities in the
chemical mixing tank in order to finally achieve a minimum residual amount of
200 ppm hydrazine and a solution PH. of 10.0 when filled in the boiler.
Fill
the boiler with DM water, with simultaneous injection of hydrazine – ammonia
mixture. Fill the boiler through bottom and economiser also up to the operating
level in the drum gauge glass.
Prepare the boiler for firing as per O&M
instructions. Start the boiler water circulating pumps as per O & M
instructions and fire the boiler at a slow rate. Raise the drum pressure to 40
kg/ cm2
and hold it for 24 hrs and maintain a residual
hydrazine content of 25 ppm & a solution PH. 10.0 in the feed water being
fed into the boiler during the entire passivation operation. Dose, hydrazine –
ammonia mixture in the feed water at the suction point of feed pump through L.P
dosing system.
After
24 hours of operation, shut down the boiler and allow it to cool slowly. Keep
the boiler water circulating pumps in service as per the O&M instructions.
Shut down the pumps when the metal temperature drops to 95 deg C. Back flush
the super heaters with conditioned DM water till the drum level raises by 25-30
mm.
Drain
the boiler under atmospheric pressure and aerate the system.
Open the upper and lower drums for inspection. Manually clean them.
Refit the drum internals and restore the boiler and prepare it for regular
operation for steam blowing, safety valve floating etc.
NEUTRALISATION OF EFFLUENTS
Alkali
Boil Out & Neutralisation of pickled surface:
Acid pickling
Effluent
is neutralized with caustic soda. PH of disposed effluent may be maintained
between 5.5 to 9.0 and fluoride less than 2.0 ppm.
Citric Rinse
Effluent
is neutralized with caustic soda & bleaching powder. PH of disposed
effluent to be maintained between 5.5 to 9.0.
Passivation
Hydrazine
& Ammonia will be neutralized with bleaching powder.
The
cleaning activity should be done with a
planning that the boiler start up could
be possible immediately after completion of cleaning process.
PH
of the solution is lowered to less than 9.0 by sufficient dilution with raw /
fire water.
(continued to part-vi EDTA
cleaning)
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
Thnq For Info Vasthi Gas Analyzers can provide product yield and fermentaton process insights relating to agitation efficiency, aeration, and feed distribution.
ReplyDelete