In continuation of Part -I and II of FO,LDO system description and commissioning this article
will cover the oil flushing and Steam Blowing of the system.
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
will cover the oil flushing and Steam Blowing of the system.
To
remove debris and clean the internal surface of oil lines in the LFO/HFO system,
including atomising steam lines and steam tracing lines oil flushing and steam blowing
are being carried out in systematic manner . This will prevent particle to be passed into
screw pumps and burner nozzle.
Auxiliary
Boiler or Low temperature APRDS will be used for steam blowing the Fuel Oil
lines. Now -a days auxiliary boiler with requisite parameter is available on rent .They will
bring their boiler and cater all the pre-requisite steam for the system. APRDS can only be
used if there is an existing running boiler.
Steam
blowing the Fuel Oil line by continuous blowing method for the duration of
20-30
minutes at a pressure of 10-12 Kg/cm2 and a super heat of at
least 500C at source.
Depending upon the site conditions, the different sections
/ circuits for steam blowing may
be decided by consulting PIDs of the system ,equipment manufacturer's recommendation.
Following are pre-requisite for steam blowing
Hydraulic test ,support work and insulation completed on all the lines where steam blowing
is to conducted.
All safety precautions and emergency safety precaution are in place .
Auxiliary
boiler is fully ready for supplying steam for steam blowing F.O. lines.
Steam drawn either directly from Aux. Boiler outlet
through a
temporary lines connected to
F.O lines or from APRDS. This is
to be decided at site as per the erection readiness of
these system.
Trip
valves, control valves, flow elements are not erected and suitable spool pieces
are
erected at these places. A check list will be prepared for activities of
their type which will be
used during restoration.
Filter elements
and NRV internals are removed.
Temporary exhaust
pipes lines are erected avoiding equipment and buildings.
All vents and
drains are properly routed and supported.
Day Tanks and
storage tanks for LFO and HFO are ready for operation.
All
steam lines as well as oil lines are insulated.
No
permanent instruments has been installed in the lines being steam blown/oil
flushed.
They are totally isolated from steam blowing / oil flushing, in case
erected.
SL. PIPELINES PR DURATION NO.OF BLOWS(min)
1. Steam lines from Aux .Boiler/APRDS 10.0 20-30 min 3
2. FO lines from Pump House to Boiler 10.0 20-30 min 3
3. LFO lines from Pump House to Boiler 10.0 20-30 min 3
4. Steam lines from Boiler to Pump House 10.0 20-30 min 3
5. Steam tracing & Condensate lines 6.0 20-30 min 3
6. All the other FO /LDO Lines 10.0 20-30 min 3
7. FO unloading Header 2.0 10 min 3.
Brief method of Steam Blowing
Auxiliary
Boiler is lighted up as per O & M manual start up procedure after attaining
steam
pressure about 10-12 kg/cm2
carry out the warnming of the line to be steam blown at a
lower pressure.
Raise the steam pressure at the drum to 10-12 kg/cm2 and give the blow
for a duration of 20-30
minutes. Maintain the pressure during the blowing period.
Allowing
it to cool down for 2 hours, above process is repeated for another one or two
times
till it meets the completion criteria. Between every blows, 2 hours
cooling time will be given.
Keeping
the line pressure 5 kg/cm2
carry out the purging of drains/vents & instrument
taping points for
10 minutes each.
Similarly,
repeat other loops/sections/sub-sections are steam blown.
Drains/vents
of F.O lines are kept open as required during steam blowing and after, for
draining condensate. Allow to cool down the piping. Dry them with compressed
air.
NOTE:
During the cooling period of one section, other section as per convenience,
will be steam blown.
After
completion of steam blowing, all spool pieces are removed and Trip valves,
control
valves and flow elements, filler elements and NRV internals are
restored / normalized. Pipe
connections to LFO/HFO pumps are normalized and
pumps are commissioned.
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
Great! your blog is very interesting and informative because of that this blog contains nice knowledge. If your are looking for these best Oil Boiler Servicing Shropshire services. Our company provides the best services in United Kingdom.
ReplyDelete