Total Pageviews

Monday, 20 January 2014

OIL FLUSHING ,STEAM BLOWING ,COMMISSIONING OF LDO,HFO SYSTEM OF BOILER PART III-ABC OF THERMAL POWER STATION.

In continuation of Part -I and II of FO,LDO system description and commissioning this article

will cover the oil flushing and Steam Blowing of the system.


To remove debris and clean the internal surface of oil lines in the LFO/HFO system,
including atomising steam lines and steam tracing lines oil flushing and steam blowing
are being carried out in systematic manner . This will prevent particle to be passed into
screw pumps and burner nozzle.
  

Auxiliary Boiler or Low temperature APRDS will be used for steam blowing the Fuel Oil
lines. Now -a days auxiliary boiler with requisite parameter is available on rent .They will
bring their boiler and cater all the pre-requisite steam for the system. APRDS can only be
used if there is an existing running boiler.
 
Steam blowing the Fuel Oil line by continuous blowing method for the duration of 20-30
minutes at a pressure of 10-12 Kg/cm2 and a super heat of at least 500C at source.
Depending upon the site conditions, the different sections / circuits for steam blowing may
be decided by consulting PIDs of the system ,equipment manufacturer's recommendation.
Following are pre-requisite for steam blowing
Hydraulic test ,support work and insulation completed on all the lines where steam blowing
is to conducted.
All safety precautions and emergency safety precaution are in place .


 
Auxiliary boiler is fully ready for supplying steam for steam blowing F.O. lines.
 
Steam drawn either directly from Aux. Boiler outlet through a temporary lines connected to
F.O lines or from APRDS. This is to be decided at site as per the erection readiness of
these system.
 
Trip valves, control valves, flow elements are not erected and suitable spool pieces are
erected at these places. A check list will be prepared for activities of their type which will be
used during restoration.
 
Filter elements and NRV internals are removed.
Temporary exhaust pipes lines are erected avoiding equipment and buildings.
 
All vents and drains are properly routed and supported.
Day Tanks and storage tanks for LFO and HFO are ready for operation.
All steam lines as well as oil lines are insulated.
No permanent instruments has been installed in the lines being steam blown/oil flushed.
They are totally isolated from steam blowing / oil flushing, in case erected.
SL.             PIPELINES                                         PR       DURATION    NO.OF BLOWS(min)
1.   Steam lines from Aux .Boiler/APRDS             10.0          20-30 min             3
2.  FO lines from Pump House to Boiler               10.0          20-30 min             3
3.  LFO lines from Pump House to Boiler             10.0          20-30 min             3
4.  Steam lines from Boiler to Pump House          10.0          20-30 min             3
5. Steam tracing & Condensate lines                     6.0           20-30 min             3
6. All the other FO /LDO Lines                              10.0          20-30 min             3
7. FO unloading Header                                         2.0           10  min                 3.  
Brief method of Steam Blowing
Auxiliary Boiler is lighted up as per O & M manual start up procedure after attaining steam
pressure about 10-12 kg/cm2  carry out the warnming of the line to be steam blown at a
lower pressure. Raise the steam pressure at the drum to 10-12 kg/cm2  and give the blow
for a duration of 20-30 minutes. Maintain the pressure during the blowing period.
 
Allowing it to cool down for 2 hours, above process is repeated for another one or two times
till it meets the completion criteria. Between every blows, 2 hours cooling time will be given.
Keeping the line pressure 5 kg/cm2  carry out the purging of drains/vents & instrument
taping points for 10 minutes each.
 
Similarly, repeat other loops/sections/sub-sections are steam blown.
 
Drains/vents of F.O lines are kept open as required during steam blowing and after, for
draining condensate. Allow to cool down the piping. Dry them with compressed air.
NOTE: During the cooling period of one section, other section as per convenience, will be steam blown.
After completion of steam blowing, all spool pieces are removed and Trip valves, control
valves and flow elements, filler elements and NRV internals are restored / normalized. Pipe
connections to LFO/HFO pumps are normalized and pumps are commissioned.











continued to Part -iv oil flushing and final commissioning


 P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE




1 comment:

  1. Great! your blog is very interesting and informative because of that this blog contains nice knowledge. If your are looking for these best Oil Boiler Servicing Shropshire services. Our company provides the best services in United Kingdom.

    ReplyDelete