OIL FLUSHING
After
steam blowing is completed, Fuel oil system is normalised for commissioning the
LFO
and HFO pumps.
LFO
and HFO Pumps are commissioned with pump re-circulation and ready for oil
flushing.
LFO
pumps of auxiliary boiler are commissioned and available for regular operation.
LFO Lines
Fuel
lines are lined up for LFO flushing through LFO return line from Boiler.
LFO
Pump started and line flushed for 24 hours. Pump suction filter is taken out
and
cleaned.
Again
flushing continued for 8 hours. If condition of the filter remains clean,
flushing can be
terminated.
LFO
lines are subsequently normalized and released for regular operation.
HFO
LINE FLUSHING:
HFO
pump started and first section of the line flushed for 24 hours. In between
from time to
time, filter is cleaned.
Again
flushing continued for 8 hours. After every 8 hour or as per requirement,
filter is
cleaned. Depending on the condition of the filter remains clean,
flushing can be terminated.
Oil flushing can be declared completed after minimum of 24 hrs flushing or minimum of
8 hours running without filter chocking.
HFO /LDO COMMISSIONING INCLUDING OIL GUNS AND CORNER STATIONS
Following equipment and system will be under commissioning.
Air cooled Oil Gun Assembly :-
No. of burners : 20
nos. per boiler arranged in 5 elevations. All Burners will be suitable for
firing heavy
oil/LSHS/HPS and bottom most elevation will be suitable for firing light oil also.
LDO Supply & Return Trip Valves
Corner Trip nozzle (Air, Oil & Steam)
Valves
High energy arc ignitors assembly
Discriminating Scanner Assembly
Fuel Oil Heaters
Fuel oil lines from HFO/LDO Pump to
Burners
Atomizing steam line from Aux. PRDS to
burners
HFO Steam Tracing Lines
Pressure Filters are provided before HFO
Heating Station and HFO Trip Valves
Plant Completion List to be prepared at
site prior to commissioning of oil firing system for
mechanical, electrical and
C&I areas.
All manpower ( operation) is in position .Necessary safety precaution is taken oil will be
charged and possibility of fire increases.
As per the normal starting/ operating procedure initially LFO firing is taken up for warming
up the boiler before firing HFO fuel.
All manpower ( operation) is in position .Necessary safety precaution is taken oil will be
charged and possibility of fire increases.
As per the normal starting/ operating procedure initially LFO firing is taken up for warming
up the boiler before firing HFO fuel.
Hydraulic Test,
Steam blown and oil flushing of LDO/HFO and atomising steam line
completed.
After few minutes of operation, trip the burner and observe and ensure that shutdown
sequence take place as envisaged.
With the Commissioning of LFO/HFO System,
boiler is ready to commence all pre-
mmwc- mili meter of water column
SCAPH - steam coil air preheater.
SAPH - Secondary Air pre heater.
FSSS- Furnace Safeguard Supervisory System ( Burner Management System.
typical PID of LDO/HFO SYSTEM
completed.
The Fuel Oil Burner Assembly with
Scanners and Ignitors are erected as per required
drawing. (Oil Gun ‘dimension, scanner orientation etc are checked from outside and inside
the furnace & Igniior Advance / Retract mechanisation
checked).We termed as Burner
alignment i.e to check the fireball position. It is major and important activity to be completed
before light up.
Steam tracing lines are erected and
terminated to suitable outlet point.
Power supply system to scanner, ignitor and trip
and corner nozzle valve solenoids are
commissioned and available for operation
Require local/remote I&C input are
made available. (List to be prepared at site).
Filter elements in the system are erected
in position
Corner station are steam blown and corner
nozzle valves and burner flexible hoses are
fitted
Trial run of LDO/HFO Pumps through pump
RC completed.
Steam blowing of LDO, HFO, Atomising
Steam Line from Pump House to Ring Header
completed.
Steam Tracing lines are completed with steam traps station.
24 V DC, 220 V Dc supply with UPS are in
charged condition
Dry simulation of FSSS System for LDO/HFO
oil elevation (AB-LDO & CD-HFO) completed
with required permissive and
interlocks (List to be prepared at site)
Scanners and ignitors are mounted as per
drawing.
Trial run of ID/FD Fans System and
Scanner Air fans completed and released for normal
operation of plant.
Trial run of SAPH and availability of ESP
to be ensured.
Boiler cleared for light up (Refer to
Boiler O&M for other preparatory checks to be made
prior to light up)
Boiler expansion constraints are removed
and ensured for free expansion. Expansion Trans
erected at pre-determined
locations.
Availability of instruments and service
air to be ensured
Boiler filled up to normal operating level.
Ash handling system erected and provides
required sealing at all required locations / areas.
Method
Start ID/FD/APH
Systems as per normal start up procedure. (Respective Testing
Schedules or
O&M to be referred) and establish required furnace draft (Around –5 to –10
mmwc).
Depending on the availability of SCAPH,
it can be charged (SCAPH charging is optional
during trial light up of LFO
burner, which is done to prove the burners)
Start the LDO Pump and ensure charging up
to fireman’s floor
Adjust the boiler airflow and wind box DP
to the required level
Put the RC valve operation of LFO Pump on
‘auto’
Give command for “start” of LFO burners
and watch for flame establishment
Once the flame is established, ensure
a.
Oil combustion is proper and
b.
Flame scanner pick up the
flame.
After few minutes of operation, trip the burner and observe and ensure that shutdown
sequence take place as envisaged.
Repeat the above procedure for other LFO
Oil Guns
HFO
Firing
Start ID/FD/APH Systems as per normal
start up procedure. (Respective Testing Schedules
or O&M to be referred)
and establish required furnace draft (Around –5 to –10 mmwc)
Charge SCAPH and raise the air
temperature to around 600C.
Adjust the boiler airflow and windbox DP
to the required level
Charge
a. Atomising Steam System and
b. Steam Tracing System
Start any one of the HFO Pump and after
charging HFO Heater, charge HFO line up to
boiler and put under short recirculation
first and then long recirculation for raising HFO
temperature.
After attaining HFO firing temperature
(around 1150C -- 1200C), give command for HFO
burner
“start”. Watch the flame establishment.
Once the flame is established, ensure
a.
Oil combustion is proper and
b.
Flame scanner pick up the
flame.
After few minutes of operation, trip the
burner and observe and ensure that shutdown
sequence take place as envisaged.
Repeat the above procedure for other HFO
Oil Gun, in that elevation.
Oil Gun, in other elevations are
commissioned on similar lines as explained above.
commissioning activities, such as alkali
boil-out, steam blowing, safety valve floating, steam
dumping etc.
LFO/HFO - Light diesel oil /Heavy fuel oilmmwc- mili meter of water column
SCAPH - steam coil air preheater.
SAPH - Secondary Air pre heater.
FSSS- Furnace Safeguard Supervisory System ( Burner Management System.
typical PID of LDO/HFO SYSTEM
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
gun cooling fan and its operation philosopy
ReplyDeleteVery informative article which is ready the engineering and i must bookmark it, keep posting interesting articles. wrong fuel in hampshire
ReplyDeleteI read this post and found detail about LDO Trader's. I appreciate this beneficial information you shared with us, Thank you!
ReplyDeleteGreat! your blog is very interesting and informative because of that this blog contains nice knowledge. If your are looking for these best Oil Boiler Servicing Shropshire. Our company provides the best services in Shropshire.
ReplyDelete