BOILER FEED PUMP ERECTION AND COMMISSIONING FINAL PART-ABC OF THERMAL POWER PLANT

TYPICAL INTERLOCK & PROTECTION REQUIRED FOR BFP COMMISSIONING

Ensure completion, installation and readiness of all instrumentation works, as per instrumentation

schedule, on BFP/ Booster pump/ Motor/ Hydraulic coupling/ de- aerator.                         
                                               
Calibration, setting and testing of primary instruments.                
                  
 Pressure gauges/ switches/ transmitters calibration and installation and wiring up to JB.                              

 Temp gauges/ switches/ transmitters calibration and installation up to JB.                           
                  
 Level gauges/ switches/ transmitters.                  
               
Limit switches.                 

Installation of JBs, cabling & termination in local and control room.                          

Readiness of control supply to Panels:                                                                  

Availability of LT & HT supplies   and readiness of electrical protection instruments.         

Readiness of mechanical system.                                                                                            

 Oil system                         

 De=aerator                       

Compressed air system.               ( Compressed air is required for pneumatic valve operation.     

Charging and testing of panels.                 

Commissioning of motorized  valves,  actuators & pneumatic re circulation valve.                              

Checking of Interlocks, protections & Alarms:                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                    .                              
                (i)   Calibration of speed control device like scope tube /thyrister control etc                       
                (ii)  Oil pressure low                       
                (iii)  Suction valve open                                
                (iv)  De-aerator level low                             
                (v)   Feed pump suction/ discharge temperature high.                   
                (vi)  Balancing leak off pressure. high                     
                (vii)  Re circulation valve open                    
                viii)  Bearings vibrations high (wherever provided)                          
                ix)   Remote/ local tripping          

                TRIAL RUN OF HYDRAULIC COUPLING
               
               
Readiness of lubrication oil & working oil coolers and availability of cooling water.

Charge lubrication  oil and working oil coolers.

Checking of HC interlocks & protections

Ensure alignment of Hydraulic coupling with BFP motor.

Ensure proper  earthing of Hydraulic coupling.

Check oil level in hydraulic coupling sump.

Start AOP and monitor lubrication oil header pressure.

Start trial run of Hydraulic coupling.

Check regulating oil pressure and set, if required.

Monitor all parameters of hydraulic coupling; Gauges are available /mounted on the equipment

                   I.   Lubrication oil and Regulating oil pressure.
                   ii.   Motor current.
                   iii.  Hydraulic coupling bearings temperatures.
                   iv.  Lubrication oil temp at L. O. cooler inlet and outlet.
                   v.   Working oil temp at W.O. cooler inlet and outlet.
                   vi.  Motor winding temps.        

TRIAL RUN OF BFP
               
               
1      Ensure free rotation of BFP by hand before coupling.                                                                                                                               

2      Ensure completion of alignment:                                                                                                                              
                     I.    Motor & Booster pump
                     ii.    Motor & hydraulic coupling.
                     iii.   Hydraulic coupling & BFP

Special attention to be given on pipe line final connection.Pipes to be ensured as free body  through

hanger adjustment.  No tension on pipes is permitted otherwise alignment  will be disturbed.

3              Flushing of mechanical seal cooling water lines for BP as well as BFP & Mechanical seal water

cooler cooling water lines.

4              Optimisation of oil flow through bearings by using orifice plates

5              Running of AOP

6              Charging of all system:  
                (i)  Lubrication oil/ working oil coolers
                (ii)  Seal water coolers
                (iii) Suction valve opening 
                (iv)  Re circulation valve (Isolation  valve) opening
                (v)  Charging of C&I local panels

7              Fill de=aerator and maintain normal level.  


 8              Interlocks & protections checking.

9              Start BFP.

10           Monitor all parameters of BFP and motor;
                    I.    Current
                    ii.    BFP suction pressure.
                    iii.   BFP discharge pressure.
                    iv.   Balancing leak off pressure.
                    v.    De-aerator level.
                    vi.   BFP suction/ discharge Differential Temperature.
                    vii.   Lubrication oil/ working oil pressures and temps.
                    viii.  Booster pump/ BFP/ Motor/ Hydraulic Coupling bearings and drain oil temps. 
                    ix.   Cooling water temps.
                    x.    Seal water/ seal water coolers temps.
                    xi.    Motor winding temps.
                    xii.   Bearing vibrations.




2 comments:

  1. NCON Turbine in India is also one of the leading thermal turbine manufacturers with standard quality. You can check them out or contact their expert turbine engineers.

    ReplyDelete
  2. Heya i’m for the first time here. I found this board and I find It truly useful & it helped me out much. I hope to give something back and help others like you helped me.Alexandr Shcolyar

    ReplyDelete