Check clearances of Thrust bearing of
BFP and Booster Pump-Feller Gauge / Dial Gauge.
Ensure specified clearances between
guide slips & key (at the bottom of pump casing), and then
welding of key
block on base frame-Vernier/ Tape.
Hydraulic testing of coolers
(waterside) - Pressure Gauge. should be calibrated
Note: Coolers if already hydro tested
at manufacturing works and test certificates available, need not be hydro
tested at site.
Completion of welding and NDE of
welds of following lines:
a.
a BFP discharge line.
. b. BFP suction line.
c
.
c. Booster Pump Suction line.
d.
d. Booster Pump discharge line
Ensure pre heat treatment and
post-weld heat-treatment of weld
Ensure that the entire pipeline is
supported by permanent supports before making the last four joints
of BOOSTER PUMP & MAIN PUMP suction and
discharge.
Ensure that the piping doesn’t exercise any pull on pump nozzles. This is extremely important in the
case of BFP suction & discharge, which are welded joints). This is true for any nay major or minor
rotating machine . That means final connection to be done when piping is in free float. This can be
achieved if all the pipelines are erected as per drawing and permanent supports are adjusted as per
drawing value. In fact in BFP we check that pipe lines can be moved by hand only without any
difficulty. Same philosophy is applicable for BOOSTER PUMP also . However BOOSTER PUMP
connection is through fastners only therefore can be manipulated easily so not critical as MAIN
PUMP. Instances are available that after final connection alignment was disturbed so much that
pipeline was cut and re-weld after necessary correction. This area is major bone of contention
between piping engineer and pump engineer.
Distances and alignment readings between coupling
half faces of Booster Pump & Gear box, Gear
box & Drive turbine shaft, Drive turbine shaft
& BFP after completing pipe connections.
Welding of key block on base frame after ensuring specified clearance between
guide slips & key (At
the bottom of pump casing.
Small bore pipeline connection of oil lines of drive turbine , Cooler
lines oil and water , Sealing lines
of pumps Govering system
installation and other steam lines to be connected and completed. Final
connection to be done after ensuring , oil flushing ,steam blowing
,water flushing ,chemical cleaning
etc is completed as per requirement under laid down procedure .Any short
cuts will bring problems
afterwards .That is during stabilisation of units.
Necessary instrumentation on oil tank ,oil lines , bearings ,gear boxes
and pumps are calibrated and
installed as per drawing.
Specially Turbovisory instruments for drive turbine , governing control
system are installed carefully.
PROCESS FOR PRE COMMISSIONING AND COMMISSIONING
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
to know about PTC please read my other blog "common man"
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
to know about PTC please read my other blog "common man"
continued to part -iii
Ncon turbine in India is one of the leading Power turbine manufacturers with standard quality. You can check them out or contact their expert turbine engineers.
ReplyDelete