As
stated in earlier posts there are three Boiler Feed Pumps (3x 50%) in a
thermal power station of 500MW and above. 2x50% turbine driven BFP ( normally
working when unit is running above certain load ) and other is 1x50 %
MDBFP which usually runs during start up
.
We have already explained in last few
blogs about erection and commissioning of MDBFP . For TDBFP pumps are same
whether it is booster pump or main pump. Instead of MOTOR driven we have variable
speed turbine with disconnecting coupling both sides . In this blog we will
discuss only the turbine as pumps are similar.
Technical data of Turbine
a.
Maximum output
7575
KW
b.
Design rating
(Economical rating) 5732 KW
c.
Speed 5275 RPM
d.
Speed range
1494-5750 RPM
e.
Initial Steam Pressure
6.33 ata.
f. Initial steam Temperature 289.6 0 C.
g.
Exhaust pressure
0.1064 ata.
Oil System
a.
Lube oil pump 2 Nos
b.
Emergency Oil pump 1 No.
c.
Jacking Oil Pump 1 No.
d. Oil vapour extractor fans 2 Nos
PROCESS : ERECTION CHECK
Foundation checking of elevation
,plan that is different pocket holes and other measurable items as per given
approved drawing . This the protocol for taking foundation from civil vendor
for erection purpose .(elevation
within+5mm/-10mm).
Check that depth and verticality of each pocket is OK.
Checking to be done by water level /dumpy level/ total station.
Distance from fixed reference axis
e.g. A-row, B-row Columns. (1mm / metre,
5mm Max.)- Establishing centre line as given in the drawing by putting
distances from fixed point . This can be done by measuring tapes or by total stations
.
Marking of equivalent axes on
foundation. Plumb Bob / total station.
Fitting of half couplings to all
equipment after ensuring corresponding fits.
For taper coupling, ensure around 80% contact between shaft &
coupling.
Blue matching the top surface of
foundation frame with corresponding bottom surfaces of equipment with around
80% contact.
Positioning and alignment of all
equipment on the foundation. Measure distance between coupling half faces of
following equipments by Vernier / Micrometer / Tape
Booster
Pump and Gearbox
Gearbox
and Drive turbine
Drive
turbine and BFP.
Grouting of Foundation Bolts. Check
that nut has full contact with foundation frame after tightening.
Leveling and alignment of equipment by jack bolts (within 0.1 mm / M). Dumpy / Precision
Spirit level) and different thickness packer plates.
Foundation frame grouting. Now a days grouting
is done with ready mix concrete of 25kg bags main supplier is ACC, PAGEL
,FOXROC etc. This is a specialised job it is advisable to do concreting in
presence of suppliers representative to avoid any complicacy afterwards. Please
insist on test certificate and cube testing on one day and three day sample.
This may delay the process however by passing
any of the test may complicate the situation afterwards. Major checks of
equipment are already told during my earlier blog. Please go through it.
Alignment (lateral and angular) between
booster pump & gearbox, gearbox & Drive turbine shaft, Drive turbine
shaft & BFP, Measure distances between coupling flanges. This is done
without any pipe connection ( water line ,oil line and steam line ). This is
pre final reading and after doing final connection final reading to be taken.
However during course of erection this reading is checked to find the effect of
connection. Dial Gauge/Micrometer.
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
to know about PTC please read my other blog "common man"
Continued to part –ii ( TDBFP)
i thank you sir for such a great useful practical info
ReplyDeletePls hindi में बताए
ReplyDeleteThe post is useful and it would really help for those who search for
ReplyDeleteSendhamarai Engineering Aluminium Scaffolding Manufacturer