PART-I
Before
starting the pre-commissioning activities of BFP ( TD – TURBINE DRIVEN) equipments need to be individually checked
for readiness upto a limit point.
Booster pump, Gearbox, Turbine, BFP and
associated system are erected as per recommended drawing and
readings are recorded for ready reference.
Acid cleaning and oil flushing completed for
lube oil and working oil, Jacking oil and governing oil piping as per test
procedure and lines are normalized. The procedure has already
been discussed in my earlier blogs.
Detergent flushing of feed water suction,
discharge and recirculation piping are completed and all piping normalized.
These flushing is being done in parts as MDBFP comes first at initial stage that
time pipelines for TDBFP may not be ready. Therefore a scheme to be made to
undertake this job without interrupting the commissioning activities. This
should be kept in mind. Otherwise to complete the line and do the cleaning in
one go is the best.
All piping supports are loaded to the rated
value
and all temporary supports removed from the pipeline.
Deaerator
and FST filled with Fresh DM water. FST level switches and Deaerator level
switches are checked. In fact these switches are calibrated during MDBFP trial
run. Rechecked during TDBFP commissioning.
Flushing
of following pipe lines completed.
Cooling water lines of Booster pump and BFP
(Seal Water cooler and seal body)
Balancing leak off lines of main
pump.
Turbine exhaust hood spray line.
Turbovisory instruments for turbine ( i.e expansion measurement of
turbine
Vibration
, temperature ,pressure etc calibrated and installed .
Steam
blowing of pipelines again in phased manner is to be completed. It is noticed
that steam lines of TDBFP are not get ready during steam blowing activity of
the unit. This is to be done at later date therefore a scheme of drawing steam
and drain to condenser /flash tank to be made and executed as per the scheme.
Insulation
of turbine and pipelines is completed.
Erection
of gland steam supply piping complete. Supports, steam blowing and insulation
complete.
Turbine
drain piping and all steam piping drain lines are complete. For initial rolling
orifice plates in drains are removed to avoid chocking.
Turbine
exhaust piping complete with supports upto condensor.
Bursting
diaphragm is erected and healty.
Gland
leak off piping erection complete to condensor (including supports and
insulation)
All
motorized valves related to turbine including live steam isolation valves,
turbine drain valves are commissioned.
Gland
steam pressure controller commissioned available for operation.
Governing
valves erected and protection devices like overspeed trip device, hand trip
device are mounted properly.
Feed
water suction strainer erected in position in clean condition with DP indicator
commissioned.
Instrument
and service air line for the Feed pump system erected and the air is made
available for operation.
P.S If you are looking to earn few legitimate extra money/MONTH from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
to know about PTC please read my other blog "common man"
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
to know about PTC please read my other blog "common man"
CONTINUED TO PART-II
Thanks for sharing! Got some value out of it. Keep sharing more related to thermal turbine. Will be soo helpful.
ReplyDeleteFind here best thermal steam turbine manufacturers in India at @ nconturbines.com.
Thanks for sharing this informative post. It's very helpful. Keep it up!
ReplyDeleteBursting Strength Tester - Digital Pneumatic | Laboratory Testing Equipment & Instruments
Hi..
ReplyDeleteI appreciate your Informative post and thanks for sharing.
Bursting Strength Tester–Digital | Packaging Testing Instruments | Box Compression Tester
We are a Professional Turnkey Project Management company. We supply plants and machinery for Lube Oil Blending Plant, Grease Manufacturing Plant, and various other Petrochemical Industries. On the other hand, , we have got expertise in different plants such as Cooking Gas Cylinder mfg. Blow Moulding plant, etc.
ReplyDeleteWe have supplied plants and Machinery around the globe such as Africa, Asia, the Caribbean, Central America, Europe, North America, etc lube oil plant
Nice articles and your informatin valuable and good artices thank for the sharing information
ReplyDeleteMid Back Office Chair
Nice articles and your information valuable and good articles thank for the sharing information GREASE MANUFACTURING PLANT
ReplyDeleteNice articles and your information valuable and good articles thank for the sharing information Lube Blending
ReplyDelete