Steam blowing of MS lines, CRH,HRH,SH,RH,HP & LP bypass
pipe lines of turbine is carried out in order to remove welding slag, loose
foreign materials, iron pieces, rust etc. from the system, generated during
manufacturing, transportation & erection.
EFFECT OF BLOWING DEPENDS ON
1) Thermal shock
2) Removal force of steam
3) Cleaning force
of steam
In earlier days steam blowing was done in puffing method .
Boiler is being pressurized up to 40 kg/cm2 then blowing valve was opened and
blowing starts . It gets completed when pressure drops down to 20 kg /cm2.
Target plate was kept after some initial blows. Steam blowing operation starts
in early morning to late evening. Night is being kept for cooling. In this operation fire was killed during blowing
and lighted up after one cycle of blowing is over. Drum level has to be watched very minutely during
blowing.
Around four year back before my retirement we conducted steam
blowing on a 660MW boiler I will describe the same. Steam blowing procedure
will be more or less same for an utility boiler. Now a days engineering
software is available with the consultant to calculate disturbance factor etc
of the blowing.
The Steam Generator is a once through supercritical plus
Radiant Reheat Boiler. Major auxiliaries of the Boiler are Pulverisers,
Feeders, Fans and miscellaneous valves. Boiler Recirculation Pump is provided
to ensure proper circulation of water in the furnace wall circuits during
initial subcritical mode operation.
The circuits which are subjected to steam
blowing are Superheat sections of Boiler, Main steam lines up to HP Turbine
inlet, Cold Reheat lines up to Reheater inlet,
Reheater sections, Hot Reheat lines upto IP Turbine inlet, HP and LP bypass
sections and all auxiliary steam lines.
Line Sizes
1. SH Outlet Pipes : ID 350 x 60
2. MSL : ID 460 x 85
3. CRH :
864 x 29
4. CRH to Reheater inlet : 660
x 23
5. RH to HRH :
711 x 42
6. HRH : 864
x 50
7. HP BP line :
323.9 x 48 / 508 X 27
8. LP BP line : 711
x 42
To remove scales, loose material, iron cuttings etc that
might have remained entrapped in Super heaters , Reheater & Steam pipings
during manufacture, storage and erection. Failure to remove the debris may
result in damage to Turbine blades, valves etc.
Steam blowing shall be done in eight stages viz Stage 1a, 1b,
1c, 2a, 2b, 3a, 3b, 4.
Electrically Operated Temporary Valves (EOTVs) shall be
located as shown in the scheme. Loop pipes from ESV and IV (if any) to Turbine
shall not be steam blown. Hence proper care shall be taken for cleanliness of
these pipes before erection.
All critical pipelines covered in stages 1a, 1b, 1c, 2a, 2b
shall be steam blown using EOTVs.
Puffing method shall be adopted for carrying out Steam
blowing of stages 1a, 1b, 1c, 2a, 2b in
which Boiler Separator pressure shall be raised to 50 Kg/cm2 and released
through a quick opening valve and steam blowing done till the Separator
pressure drops from 50 Kg/cm2 to 25 Kg/cm2.
Steam blowing for stages 3a, 3b and 4 shall be carried out by
continuous blowing method. Steam blowing by continuous method shall be done at
50% of normal operating pressure of the respective system. .Duration of each
blow shall be 20 to 30 minutes. The time gap between two blows shall be 1 ½ to 2 hours.
The effects of steam blowing shall be evaluated and steam
blowing concluded as per the completion criteria given .
Stage 1a --
Superheaters, Main Steam Lines upto ESVs, temporary lines from ESVs to
EOTVs, temporary lines from EOTVs to CRH lines, CRH lines upto Reheater inlet
and temporary lines upto exhaust. Tap off lines from CRH for Deaerator, TDBFPs,
PRDS, HP Heaters 6A & 6B, Gland sealing etc., shall remain closed /
isolated. Blowing of this stage shall be concluded by observing the indents on
the target plates.
CONTINUED PART-ii
Sir
ReplyDeleteDisturbance factor is a term commonly associated with steam Blowing Operations.Are there details available on this ? What is the importance of this factor for steam blowing operations.
Biranchi Swain
Sir
ReplyDeleteIn 210/250 Mw Sets, the steam blowing was done by raising the pressure to 40 Kg/Cm2 and blowing till 19 to 20 Kg/Cm2.But In 500Mw/600 Mw/660 Mw sets, the system pressure is raised to 50 Kg/Cm2 and blowing is carried out till the system pressure drops to 20-25 Kg/Cm2 as you have mentioned. Why is this difference in pressure in different rating of sets.
For steam blowing information check out http://www.steamblowcompany.com/ they have all the information that you require.
ReplyDeleteThanks for posting the useful information to my vision. This is excellent information,.
ReplyDeletehydraulic road blockers
boom barriers
Good Post! Thank you so much for sharing this pretty post, it was so good to read and useful to improve my knowledge as updated one, keep blogging…
ReplyDeletenebosh course in chennai
Thanks for nice information about cranes. Your blog focuses on every detailed aspects which boosted my knowledge
ReplyDeleteclick here
Steam blowing of MS lines, CRH,HRH,SH,RH,HP & LP bypass pipe lines of turbine is carried out in order to remove welding slag, loose foreign materials, iron pieces, rust etc.
ReplyDeleteThermal Power Stations in Pakistan from the system, generated during manufacturing, transportation & erection.
I am impressed with your post. Your post is very informative. Keep sharing. Ultimate ABC Cables Manufacturers.
ReplyDeleteRead About Nuka World Plant Link Here
ReplyDeleteNuka World Power Plant
Your blog is so informative! However I would suggest people to call expert steam turbine engineers from Nconturbines.com if you get any issues with your turbines. You could also try them out! They are best in India.
ReplyDeleteI am really impressed with your writing skills as well as with the layout on your blog. Is this a paid theme or did you customize it yourself? Anyway keep up the nice quality writing, it’s rare to see a great blog like this one today..alex shcolyar
ReplyDeleteThanks for sharing this informative post. It's very helpful. Keep it up!
ReplyDeleteSalt Spray Chamber | Box Compression Tester | Bursting Strength Tester Digital | Digital Tensile Testing Machine Cap 2500KG | Wall Thickness Gauge - MagnaMike 8600 | Testing Instruments | Laboratory Hot Air Oven
In a typical process plant, there is a high demand of saturated steam for numerous heating applications. Since saturated steam has good heat transfer proficiency. However, the boiler generates superheated steam. We are specialized Desuperheater Manufacturer . Contact Us: 8100355155
ReplyDelete