It is expected that after completion of Full Hydro ( except
re heater) completion of
stage1B next step is conducting Boiler Hydro test
within 21 days . But there may be
some problem to achieve that then one should
proceed for wet preservation of the Boiler.
The
Boiler is pressurized to 5-10 Kg/cm2 with hydrazine and Ammonia treated DM
water
containing not less than 200 ppm of Hydrazine and sufficient quantity of
Ammonia to have pH value of 9.5-10.0 and retained at this value for
preservation.
Boiler water
samples can be collected periodically say once a week or fortnight,
depending
on the pressure holding worthiness of the system, and tested for
pH and
hydrazine content. Sampling point will be low point drain.
In case the sample
water does not meet the criteria for preservation of Boiler
the same is to be
boosted up using Boiler fill pump and dozing arrangement and
at the same time
venting sufficiently through the air vents in the top
level of the boiler.
Alternatively,
preservation can also be done under nitrogen capping at
0.35 Kg/cm2
at vents of separator and Super-heaters.
Next
system commissioning will be Pre- boiler flushing with temporary pumps
and
piping . Same facility will be used for acid cleaning/ alkali boil out
operation.
However
we will first discuss about the individual items like valves ( manual,
electrical ,Hydraulic ) , Pipe installation ( oil ,air ,steam ) hanger supports
,misc.
accessories of the system.
A
commissioning engineer should look for the technical deficiency in the
erection
and get it rectified before commissioning the system. If it is not possible
then same is to be recorded in the register so that early action can be taken
to
resolve the issue.
Manual
Valve ( only big valves are considered)
Following
common aspect to be looked after by commissioning engineer
before he starts any
activity. Deviation from that may lead to unsafe condition
for commissioning.
Access to the
plant item is adequate
Illumination in the plant area is adequate.
Any other requisite safety provision
is adequate for the immediate
commissioning activity.
Plant item is in a clear condition.
All
necessary locks and keys for padlocks, interlocks etc. are available.
Hot surfaces lagged or
screened or screened sufficiently to provide protection for personnel.
Ensure that manual valves installed correctly as per latest PID.
Heavy valves are supported properly and independent of the pipe
line. Valve should
not carry the load of the pipe line.
Direction of flow marked and correct.
Also see that valve position is such that it is easy for repair,
replacement and maintenance.
Ensure that if limit switches are available then they are set by
physically moving the valve
open or close.
No fouling with near by structure or equipment noticed. After
commissioning, valve
should be kept in closed condition and protocol to be made
and kept as future reference.
Motor operated valve.
Ensure that motorised valves installed correctly as per latest
PID. Check the Tag No.
and name plate.
Heavy valves are supported properly and independent of the pipe
line. Valve should
not carry the load of the pipe line.
Direction of flow marked and correct.
Also see that valve position is such that it is easy for repair,
replacement and maintenance.
Adequate space is available for setting of limit switches of the
valve.
Ensure that limit switches are set and position transmitters are
also set. Indication
on the valve is available. For small bore valve the valves
can be set manually but same
can also be set electrically by keeping the valve in middle
position. Before checking
with electrical please ensure that direction of
rotation of motor is checked.
It is a thumb rule that set the valve open position with position
limit switch and
set close position with torque switch.
Each motorised valve has minimum two position limit switches and
two torque
limit switches. Torque limit
switches are factory set should not to be disturbed.
Before commissioning of motorised valve please talk to senior
about the valve
position. I remember in my early days I was commissioning a
motorised valve and
about to break the wet preservation of the Boiler.
Commissioning protocol to be made that is current take by motor,
limit switch
setting , manual operation, clutch – gear operation, indication,
local /remote operation etc.
You need good communication
set up as manpower required to assist
you in MCC ,
control desk , logic panel /DCS simultaneously all the place.
After commissioning keep the valve in closed condition.
continued to part-v
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
This is my great pleasure to visit your website regularly and to enjoy your excellent post here. Thank you for sharing with us.
ReplyDeleteCheck Reputed Turbine Manufacturers in India at @ Nconturbines.com.