In my earlier post erection of heaters ,de aerators were discussed . beside that in Turbine package there are other auxiliaries both static and rotary such as different coolers , CEP ( condensate extraction pump ) , vacuum pumps , CPU ( condensate polishing unit) etc. Except CEP erection of other auxiliaries need not require any special strategy. For CEP erection foundation checking and canister erection is slightly crtical. CEP is a vertical pump therefore canister is to be erected before erection of CEP. It is sometimes noticed that CEP foundation is full of water at bottom most area and prevent canister erection . It is recommended to repair the foundation so that leakage can be stopped or draining the pit before erection.
It was decided that next topics will be steam blowing as we have covered all the major equipment . However i received mails from young engineers to cover electrical system erection and commissioning . I am an electrical engineer but did not work with the system. Therefore what i have seen at site is written down. Value addition is to be done by individual.
Earthing system is the mother of electrical system. You can not run an electrical machine without earthing.
Earthing system is the mother of electrical system. You can not run an electrical machine without earthing.
The earthing system consists of following. Earthing is the basic requirement
of any Good electrical system. This is
essential to protect human lives and also help us to detect fault in the system
. Good earthing provides smooth
electrical operation and avoid spurious
tripping.
i. Earth Pit
ii. Subsidiary conductors
iii. GI Flats
1. EARTH PIT : Each
earth pit must be made as per their design normally that will be either pipe or
rod electrode type earth pits. In pipe electrode
earth pit the depth will be 3.5 Mtr . Where as in rod electrode the depth will
be 3 Mtr only. In pipe electrode, the earth pit must be made with different
layers of sand, coal, salt and gravel
whereas in rod electrode, the rod will be inserted into the earth soil.
BTG area earth mat was laid after doing
the PCC of the area. Risers were raised along the column foundation from two
sides. Rods are welded at least 250 mm overlap so that firm contact is made. Special earth pits are made for electronic
panels and skids which are separated from electrical earthing.
2. SUBSIDIARY CONDUCTORS :
The conductors connects between earth pit and various equipments are
subsidiary conductors. They are
connected with main earth mat which
is 600 mm depth by means of raiser
and will be connected to each earth pit through test links. The other end of the earth pit will be
connected to the equipment.
3. GI FLATS : All the
test links and equipment connections of the switch yard are done with GI flats of 75 x 12 mm . Inside the control building, the earthing
connection is provided by 50x6 mm GI flats.
Testing
- To test
the individual earth pits of 400 KV switch yard
- To test
the continuity of the earth mat
- To
measure the resistance of total earth
mat.
Testing Equipment
-
Earth
Megger calibrated.
- Calibrated digital multimeter.
State of the plant
Erection of 400 KV Switch yard earthing network completed.
Test links
and connections to various equipments disconnected for test.
Clearance from erection department for carrying out various tests
obtained.
continued part -ii
Please post all erection details of electrical system of thermal power plant as soon as possible