One of the major job in Boiler Erection is ducting of Air and Flue Gas. Around 20% of
Boiler weight comes from ducting and dampers ( excluding support structures). In our
country ducts are fabricated at site and erected. Duct plates manufactured from 6mm to
8 mm steel plates. It requires considerable space to store and to fabricate. Because of its
volume it is not easier to transport. Therefore it is advisable to create a space very near
to boiler for fabrication of Ducting. Ducting job can be subdivided into following groups.
- Prefabrication of ducting to be carried out in two to three places.
- Erection of Ducting inside Boiler area that wind box , FD discharge , Flue gas etc. up to
Boiler Outlet Flange ( BOF)
- Boiler Outlet Flange to ESP inlet Funnel
- ESP Outlet Funnel to Chimney through ID Fan.
Out of the above erection of duct inside Boiler is most challenging. It requires pre planning
to execute in a sequence otherwise erection in assembled condition is not possible . A few
areas ducts were erected piece by piece because of its size. There are approach problem in
Boiler . Ducting erection starts with pressure part erection with 03 months lag. During that
time prefabrication starts. Therefore pre fabrication area near boiler to be used for boiler
ducting and to be followed in a sequence . FD , PA fan ducting to be taken up later as
that place will not be available for erection. Priorities to be given ducting which are
coming at height .
Boiler Outlet flange to ESP inlet ducting is extremely crucial because it comes late. It
will have fixed duration it varies from 60days to 90 days . It is advisable to start
erection from the centre line of the boiler move sideways to extreme end . This will
reduce the requirement of higher capacity of crane. If it starts from end higher capacity
crane more than 250MT class will required. Please note that area involves lot of
interface with other work like ..CHP gallery , Ash handling structure, Cable and pipe
line structures , civil work of ash trench, Mill rejects Silo. etc. It has also interface
with suction chamber erection of FD and PA. All these need to be coordinated to
erect these ducts.
ESP outlet funnel to ID fan inlet and ID Fan outlet to Chimney does not have any
interface with other work and can be started at the earliest if foundations and material
are available. These ducts specially after ID fan are very big ducts and need to be
fabricated near erection point. Only point to be taken into account is completion of
Chimney outer shell otherwise debris from the top may disturb this erection.
A few photographs are attached herewith.
Above picture shows duct fabrication is going on by side of the ESP .
Duct erection inside boiler area is under progress.
Plan view of ducting from BOF to chimney.
PA fan discharge ducting../
to be continued.
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
Boiler weight comes from ducting and dampers ( excluding support structures). In our
country ducts are fabricated at site and erected. Duct plates manufactured from 6mm to
8 mm steel plates. It requires considerable space to store and to fabricate. Because of its
volume it is not easier to transport. Therefore it is advisable to create a space very near
to boiler for fabrication of Ducting. Ducting job can be subdivided into following groups.
- Prefabrication of ducting to be carried out in two to three places.
- Erection of Ducting inside Boiler area that wind box , FD discharge , Flue gas etc. up to
Boiler Outlet Flange ( BOF)
- Boiler Outlet Flange to ESP inlet Funnel
- ESP Outlet Funnel to Chimney through ID Fan.
Out of the above erection of duct inside Boiler is most challenging. It requires pre planning
to execute in a sequence otherwise erection in assembled condition is not possible . A few
areas ducts were erected piece by piece because of its size. There are approach problem in
Boiler . Ducting erection starts with pressure part erection with 03 months lag. During that
time prefabrication starts. Therefore pre fabrication area near boiler to be used for boiler
ducting and to be followed in a sequence . FD , PA fan ducting to be taken up later as
that place will not be available for erection. Priorities to be given ducting which are
coming at height .
Boiler Outlet flange to ESP inlet ducting is extremely crucial because it comes late. It
will have fixed duration it varies from 60days to 90 days . It is advisable to start
erection from the centre line of the boiler move sideways to extreme end . This will
reduce the requirement of higher capacity of crane. If it starts from end higher capacity
crane more than 250MT class will required. Please note that area involves lot of
interface with other work like ..CHP gallery , Ash handling structure, Cable and pipe
line structures , civil work of ash trench, Mill rejects Silo. etc. It has also interface
with suction chamber erection of FD and PA. All these need to be coordinated to
erect these ducts.
ESP outlet funnel to ID fan inlet and ID Fan outlet to Chimney does not have any
interface with other work and can be started at the earliest if foundations and material
are available. These ducts specially after ID fan are very big ducts and need to be
fabricated near erection point. Only point to be taken into account is completion of
Chimney outer shell otherwise debris from the top may disturb this erection.
A few photographs are attached herewith.
Above picture shows duct fabrication is going on by side of the ESP .
Duct erection inside boiler area is under progress.
Plan view of ducting from BOF to chimney.
PA fan discharge ducting../
to be continued.
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
Thanks for This useful Information.Your Knowledge about Manufacture, Supplier and Installation is very good. Follows this link
ReplyDeletethanks for these useful tips about ducting work and other manufacturer works.
ReplyDeleteHeating and Cooling Toronto
Great post! I am actually getting ready to across this information, It's very helpful for this blog.Also great with all of the valuable information you have Keep up the good work you are doing well.
ReplyDeleteUsed cranes Qatar
very good camera work and these detail about insulation work are so informative thanks.
ReplyDeleteHeating and Cooling Toronto
Thanks you very much for sharing these links. Will definitely check this out.. attic insulation removal and replacement
ReplyDeleteHi my company name is Sree Lakshmi enterprises insulation contractor Hyderabad
ReplyDelete