Air preheater erection can be started just after erection of last ceiling girder and can be continued
along with Pressure Part erection. However approach for pressure part should be kept open.
For Boiler where Air heaters are installed in second pass approach from rear and both sides
should be available. Two other issues may crop up i) Construction of fan foundations ( PA & FD)
ii) Erection of ducts just above Air heater. It is noticed that approach area at the rear gets
congested early because of multi- discipline starting of erection work like ESP , SG , coal
gallery , Ash handling work , duct support , electrical tray work etc. Therefore it needs good
planning and idea about the priorities for all the above work otherwise conflict bound to happen
and derails the time schedule.
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
Thank you for sharing such a great information about Air Preheater for more information you can visit at arrow-energy.com.
ReplyDelete