about Boiler feed pump commissioning as a whole. BFP( MDBFP) is one of the
first major equipment need to be commissioned before Boiler light up.
Commissioning
includes checking of following activities completion as per drawing and quality
plan.
1 Erection completion of feed water
lines.
2 Instrumentation stub parts
completion.
3 Completion of Alkali/ detergent
flushing of feed water system, as well as condensate system and heaters drip
system.
4 Cleaning and normalisation of
deaerator and feed lines
5 Checking & setting of hangers
and supports of feed water lines including BFP suction lines, recirculation
lines.
6 Deaerator filling with DM water.
7 Final flushing of the suction
lines of Booster Pump & BFP .
Readiness of
cooling water system
1 Erection completion of cooling water lines of,
BFP Motor
Lubrication oil coolers and working oil coolers
Seal water
coolers of BP & BFP
2 Commissioning of the motorised actuators of motor cooling
water valve..
3 Checking &
setting of hangers & supports of CW lines of CW system and motor cooler.
4 Availability
& readiness of cooling water/ system.
5 Flushing of
all cooling water lines of CW system and motor cooler.
Completion of ACW system and heat exchangers ,Pumps, tanks ,pipelines with instrumentation.
Electrical and C&I work completion of Feed Pump , Feed station , control valves
,actuators etc.
1 Meggering of
BFP motor
2 Availability
of HT supply
3 Ensure proper
earthing of BFP motor and instruments panel..
4 Completion of
instrumentation (bearing oil press & temp) impulse piping and mounting of
press/ temp gauges, and winding, temp RTDs
5 Filling of Hydraulic
coupling sump with fresh oil after oil flushing & cleaning of sump
6 Oil pressure optimization
at motor bearings.
7 Ensure
de-coupling of motor with booster pump and hyd. Coupling.
8 Ensure free
rotation of motor by hand.
9 Checking of
BFP motor protections and CW valve interlock.
10 Charging of CW
system and lubrication oil cooler.
11 Bumping of motor
and checking DOR
12 Trial run of BFP
motor
13 Monitoring of
motor parameters.
I.
Motor current and voltage.
ii.
Motor winding temperatures.
iii.
Bearing temperatures.
Continued to concluding part
Hey your blog is so informative. Got some ideas on pumps. Very thankful!
ReplyDeleteGet quote from thermal Steam turbine suppliers and manufacturers in India.