During the acid cleaning process, all the permanent boiler instruments are isolated except
providing a temporary pressure gauge of        0 to 5 kg/ cm2 in the drum for monitoring
nitrogen pressure in the drum during nitrogen capping. 

For alkali boil out, neutralizing and passivation processes, essential control and instruments
viz. Protections, interlock, alarms, measurement, annunciation etc. required for  light up
of boiler are made available.  

Boiler is flushed thoroughly including the temporary pipe lines and system. Pre boiler
flushing to be completed for the availability of Boiler Feed Pump ( same will be discussed
during turbine commissioning). 

For chemical cleaning process, the internals of the non-return valve provided in the
economiser recirculation line is removed in order to facilitate fast filling and draining of the
boiler. 

All the boiler auxiliaries are made ready and available for boiler light up. This includes
Auxiliary steam, chemical dozing pumps, tanks, boiler circulating pumps, fans, oil pumps
etc. 

Drum vent lines, Nitrogen capping lines are properly tagged and taken to suitable location
for easy operation. 

Drum internals including primary and secondary separators, orifices at the bottom drum are
to be installed after the chemical cleaning process. The baffle plates inside the bottom
drums are to be installed before the alkali boil out. 

In addition to drum metal temperature 04 number metal temperature to be provided at
the corners of ring header and wired up to control room.  
Instruments are installed as per schemes. 
Various drains from the system at different operations during the process are to
be connected to a common drain leading to neutralizing pit. 
Boiler tube coupons placed at two ends inside the drum and bottom ring header to see the
effectiveness of the cleaning. 
Proper neutralising arrangement is available at site to neutralize and dispose off the effluent
in line with statutory authority of the state.
Chemical dosing system is ready in all respect.
 
MD-BFP is available for regular operation.
ALKALI BOIL OUT
The boiler (steam generating surfaces and economiser) is filled with an alkaline solution
containing 500 ppm of disodium phosphate  and 1000 ppm of Tri sodium phosphate  then
fired to raise the pressure to 40 kg/ cm2, following the specified operational procedures.
During the process, rotation of boiler circulating water pumps should be done as per
operating instructions. 
Procedure
Prepare the boil out chemical solution in hot demineralised water in the chemical mixing
tank. The solution is formulated by dissolving the following proportionate quantities of
chemicals, depending on the volume of the system to be cleaned. 
1.       0.05% Na2  HPO4       12 H2O
2.       0.1  % Na3 PO4         12 H2O 
Hold the solution prepared as above in the tank and homogenise the same by recirculating
the solution by operating chemical injecting pumps. 
Start filling the boiler with demineralised water, with simultaneous blend filling of already
prepared boil out chemical solution. 
Light up the boiler as per O & M instructions and gradually raise the pressure to 40 kg/
cm2 .  Hold the pressure for four hours. Obtain boiler water sample from CBD sampling point
and analyse for alkalinity, phosphate content, dissolved silica and oil content. Prescribe
blow down every 2 Hrs. once, after killing the fire; Duration the blow down shall be for one
minute  Ensure that the drum level does not go out of gauge glass vision. Repeat the
operation of raising the pressure to 40 kg/ cm2
 .
The boil out is declared completed when the oil value is no longer detected or minimum
eight blow downs are completed whichever is later.
Drain the boiler, when it is cooled, as per O & M instructions. Once the draining is
completed, fill the boiler with demineralised water, heated to 80 deg C, through boiler fill
pump. Back flush the super heaters with DM water containing 200 ppm hydrazine and pH
10.0 with NH3  till it overflows into the drum. Drain the boiler to the waste disposal system.
Inspect the lower and upper drum. Manually clean them.
Usual procedure of light up and shut down as described in O&M manual should be followed.
Temporary Piping arrangements and other arrangements at the boiler.
Continued to Part-IV for acid cleaning /edta cleaning procedure.
 P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below


8 comments:

  1. its to work and so interesting and i like it. thanks for sharing us.

    Boil Out Chemical

    ReplyDelete
  2. I have no idea what a temporary boiler even is. I have heard about them before, but never have I seen one. I just am uncertain as to how they work.
    Jak Manson | http://www.nationwideboiler.com/boiler-rentals/mobile-boiler-rooms.html

    ReplyDelete
  3. I have been trying to get settled into my new home but I can't seem to figure out my boiler room. I totally forgot to take care of that and haven't gotten it installed. I am hoping that I can get one just to last me short time until my real one comes. http://www.nationwideboiler.com/boiler-rentals/mobile-boiler-rooms.html

    ReplyDelete
  4. Thanks for sharing this blog, it's a really wonderful article, keep sharing such blogs.
    Boiler rental

    ReplyDelete