During the acid cleaning process, all
the permanent boiler instruments are isolated except
providing a temporary
pressure gauge of 0 to 5 kg/ cm2 in the drum for
monitoring
nitrogen pressure in the drum during nitrogen capping.
For alkali boil out, neutralizing and
passivation processes, essential control and instruments
viz. Protections,
interlock, alarms, measurement, annunciation etc. required for light up
of
boiler are made available.
Boiler is flushed thoroughly including
the temporary pipe lines and system. Pre boiler
flushing to be completed for the availability of Boiler Feed Pump ( same will be discussed
during turbine commissioning).
For chemical cleaning process, the
internals of the non-return valve provided in the
economiser recirculation line
is removed in order to facilitate fast filling and draining of the
boiler.
All the boiler auxiliaries are made
ready and available for boiler light up. This includes
Auxiliary steam,
chemical dozing pumps, tanks, boiler circulating pumps, fans, oil pumps
etc.
Drum vent lines, Nitrogen capping lines
are properly tagged and taken to suitable location
for easy operation.
Drum internals including primary and
secondary separators, orifices at the bottom drum are
to be installed after the
chemical cleaning process. The baffle plates inside the bottom
drums are to be
installed before the alkali boil out.
Various drains from the system at
different operations during the process are to
be connected to a common drain leading to neutralizing pit.
Boiler
tube coupons placed at two ends inside the drum and bottom ring header to see
the
effectiveness of the cleaning.
Proper
neutralising arrangement is available at site to neutralize and dispose off the
effluent
in line with statutory authority of the state.
Chemical
dosing system is ready in all respect.
MD-BFP is available for regular operation.
ALKALI
BOIL OUT
The boiler (steam generating surfaces and
economiser) is filled with an alkaline solution
containing 500 ppm of disodium
phosphate and 1000 ppm of Tri sodium phosphate then
fired to raise the pressure to 40 kg/ cm2, following the specified operational procedures.
During the
process, rotation of boiler circulating water pumps should be done as per
operating instructions.
Procedure
Prepare the boil out chemical solution
in hot demineralised water in the chemical mixing
tank. The solution is
formulated by dissolving the following proportionate quantities of
chemicals,
depending on the volume of the system to be cleaned.
1. 0.05%
Na2 HPO4
12 H2O
2. 0.1
% Na3 PO4 12 H2O
Hold the solution prepared as above in
the tank and homogenise the same by recirculating
the solution by operating
chemical injecting pumps.
Start filling the boiler with
demineralised water, with simultaneous blend filling of already
prepared boil
out chemical solution.
Light up the boiler as per O & M
instructions and gradually raise the pressure to 40 kg/
cm2 . Hold the pressure for four hours. Obtain
boiler water sample from CBD sampling point
and analyse for alkalinity,
phosphate content, dissolved silica and oil content. Prescribe
blow down every
2 Hrs. once, after killing the fire; Duration the blow down shall be for one
minute Ensure that the drum level does
not go out of gauge glass vision. Repeat the
operation of raising the pressure
to 40 kg/ cm2
.
The boil out is declared completed when
the oil value is no longer detected or minimum
eight blow downs are completed
whichever is later.
Drain the boiler, when it is cooled, as
per O & M instructions. Once the draining is
completed, fill the boiler
with demineralised water, heated to 80 deg C, through boiler fill
pump. Back
flush the super heaters with DM water containing 200 ppm hydrazine and pH
10.0
with NH3 till it overflows into the
drum. Drain the boiler to the waste disposal system.
Inspect the lower and
upper drum. Manually clean them.
Usual procedure of light up and shut down as described in O&M manual should be followed.
Temporary Piping arrangements and other arrangements at the boiler.
Continued to Part-IV for acid cleaning /edta cleaning procedure.
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
its to work and so interesting and i like it. thanks for sharing us.
ReplyDeleteBoil Out Chemical
Thank you for any other excellent post.
Deletedosing pump manufascturer in india
I have no idea what a temporary boiler even is. I have heard about them before, but never have I seen one. I just am uncertain as to how they work.
ReplyDeleteJak Manson | http://www.nationwideboiler.com/boiler-rentals/mobile-boiler-rooms.html
I always look for such type of blogs. Thanks for your sharing.
Deletedosing metering pump manufacturer in india
I have been trying to get settled into my new home but I can't seem to figure out my boiler room. I totally forgot to take care of that and haven't gotten it installed. I am hoping that I can get one just to last me short time until my real one comes. http://www.nationwideboiler.com/boiler-rentals/mobile-boiler-rooms.html
ReplyDeleteGood to sharing I have read this post and in this post i got so many knowledge. Thanks for the posting.Battery Wholesale Dealer Qatar|Vehicle Service Center in Qatar|Best Car Service Center in Qatar|
ReplyDeleteStorage and Warehouse Rack Suppliers in Qatar |Mezzanine Floor in Doha Qatar | Tyre Dealers In Doha
Thanks for posting your blog.
ReplyDeletePlastic Pallets Supplier In Qatar | Mobile Shelves Supplier Doha | Storage And Warehouse Racks Suppliers In Qatar
Thanks for sharing this blog, it's a really wonderful article, keep sharing such blogs.
ReplyDeleteBoiler rental