Total Pageviews

Sunday, 8 September 2013

BASICS OF PIPING ERECTION IN THERMAL POWER STATION. PART -II


- In an isometric drawing of Piping following points may be looked into.

- BOM ( Bill of Material) , Pipe routing with General Arrangement Drawing , Supporting

  arrangement , Hydro test Pressure , Provision of drains and vents etc.

- All of the pipes will come in pieces and stubs are welded on it. The same is to be either

  pre-assembled or erected and assembled at site. When fluid is gas , steam or air connection

  will be from top and in case of water or fuel the connection will be at the bottom. This

  type of arrangement is being followed in general.

- We provide high point vent to remove air from the pipeline and low point drain to remove

   condensate or liquid after hydro test.

- When there is rise of  steam pipeline against the flow of pipelines we provide drip leg to remove

   condensate from the pipeline .This is to avoid water hammering in the pipe line .

- Steam lines with following lines come under the purview of Indian Boiler Regulation.

   line for which design pressure is > 3.5 kg/cm2 .

   line size above 10" with one 1.0 Kg/cm2 pressure.

- Normal upstream and down stream length required for an orifice flow meter is 15D

  and 5D respectively.

- The thumb rule of two consecutive  butt weld id  1D.

- Following hardness test are followed at site.

- Rockwell hardness test , Brinell Hardness test and Vickers hardness test.

- At site we carry out DE and NDE test. DE means destructive test such as bend test ,

  Impact and hardness test. NDE means non-destructive test such as Radiography ,

  Ultrasonic , Dye penetration test and Magnetic penetration test.

- In general Hydro test pressure is 1.5 times design pressure of the system.

  For design temperature above the test temperature minimum test pressure can be

  calculated as follows :-

  P( test) = ( 1.5 * P* St)/ S

  where P(test) = Minimum test Pressure ; P = internal design pressure.

  St = Allowable stress at test temperature  ; S =  Allowable stress at design temperature.

- Stress Analysis now a days are carried out through a software . Stress analysis is done

  at design stage to ensure that piping system stress is within limit and to solve dynamic

  problem like mechanical vibration , pulsation , fluid hammer etc. Stress analysis is also

  done to solve problems associated with temperature. This is designer domain and site

  never does it therefore only a glimpse is given.

- Name of the few stresses are Axial stresses ( Tensile/ Comprehensive) , Shear Stresses ,

  Radial Stresses and Hoopes Stresses.

- Stress formula due to thermal expansion is

  stress developed - E * e/L ; E= Young' modulus ; e = Increase in length due to thermal

  expansion  ; L = original length of pipe.

- For calculating thermal expansion following formula is used.

  E (expansion) = Co-efficient of expansion * L ( length of Pipe)* T ( temp differential).

- One of the major work of stress analysis is to locate hanger supports and anchor points.

  For calculating that different loads are considered ( primary loads , secondary loads and

  occasional loads ).

- Site has to locate the hanger accurately at the place marked in the drawing. Any displacement

  form the designed location due to interference should  promptly be reported to designer for his

  acceptance . He can do analysis and confirm about displacement. Number of instances known

  to me about failure in piping system due to above. All site engineer should  be cautious in this

 area.

-Pipe strain may distort the alignment of rotating equipment . Therefore it is customary

 before welding the last joint with the machine freeness of pipes has been checked with

 all supports are on line . This we did in case of Boiler Feed Pump and Turbines. Welding

 will not start until and unless competent authority checks the freeness.






continued for next part.


P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE















































No comments:

Post a Comment