COMMISSIONING
PROCEDURE:
TESTING OF BATTERY CHARGERS:
The insulation value shall be checked with 500 V DC Megger.
During this test, all low voltage circuits
& Relays etc, shall be
bypassed ( shorting)
The panel shall be switched on at no load. For this, first make input switch ON & check the voltages at all phases indicated by lamps & voltmeter by selector switch . Now the voltage is connected to the primary of the Main transformer which steps the voltage down as required for the specific DC output Voltage & isolates AC Input line from Battery circuits. The transformer's secondary is connected to the Full wave rectifier assembly.
The bridge is standard three phase full wave half controlled silicon bridge. The voltage control is accomplished by the application of a positive pulse to the gate terminals of the SCR at the desired time. Before the pulse is applied , the SCR is open and no current flows in the circuit. As soon as SCR is fired, it operates as a standard silicon rectifier until the forward current is reduced to almost zero.
Check the no load output voltage at the output terminals.
Ensure the
output voltage is steady without any trouble for 15 minutes.
Check for
annunciation interlocks etc.
If load is
available, the equipment shall be loaded progreesively upto rated value
Check for
voltage regulation, free from oscillation, ripple etc.
Check for
dropping characteristics at higher loads.
Run the
equipment for 4 hours and observe of stability and check for local
heating. When unit is loaded the ripple
voltage level (peak to peak) may be observed . Follow the advice of Service
engineer.
II FIRST CHARGING OF BATTERY:
Thumb
rule says DC Voltage needed for battery
charging will be 2 times the no of cells in battery bank. The initial charging
will take approximately 16 to 24 hours since the batteries are already charged
and sent as maintenance free ones.
k board is
firmly coIt is of utmost importance that the terminal of the battery is
connected to +ve load of charging source. So polarity should be ascertained.
Commence
charging not later than 24 hours after connecting all battery cells.
Give the
first portion of charge at a rate of 100 Amps for 10 Hours
Discharge it
using Water resistance or halogen lamps as recommended by supplier
Give the
second charging at the rate of approximately 20 Amps till the signs of
completion of charge observed.
Select any
one cell (except the end cell or regulating cell) as pilot cell out of every
rack as given in the layout of the battery bank.
Voltage and
specific gravity reading from pilot cells will indicate the state of charging
of the whole battery system. Follow supplier’s recommendation
All cell
terminals & connections are to be applied with pertroleum jelly to reduce
contact resistance. No adjustment should be made which will disturb charging.
When all the
cells have been greasing freely and when voltage and specific gravity of pilot
cell has been constant over 3 successive hour readings, the cells can be deemed
to be fully charged and the charging may be terminated. Then wipe down outside
of all cells and clean the floor.
Put the
battery system on trickle charging when charging completes.
The trickle
charge should be adjusted to give optimum battery voltage of 1.53 - 1.67 volts
per cell.
III ENERGISING OF DISTRIBUTION BOARD:
Take final
I.R. value of the board. Check ea
ethi ected with earth through wire or strip as shown in the drawing.
ethi ected with earth through wire or strip as shown in the drawing.
Ensure that
all outgoing circuits are locked in OFF position.
Ensure that
all safety procedures have been observed.
Check that
polarities of D.C switch board battery charger and battery are matching.
Close the
incomer switch of board to charge it.
Measure D.C
Voltage at the Input.
Observe D.C
board for any abnormality.
If board
condition is satisfactory, check that all remote end fuses of outgoing circuits
are removed.
Switch ON
outgoing feeders one by one. Record the following for each circuit.
i.) Polarity at both ends of circuit
ii.) Voltage at both ends of circuit.
IV EARTHFAULT RELAY ON LOAD TEST:
To
carry out on load test for the Battery
E/F relay, connect variable resistance box of the range of 15 to 150 K Ohms
between +ve pole of the board and earth
Keep
selectivity setting plug of E/F relay at
3 ms setting.
Cut out
resistance slowly to simulate an E/F and
observe the current in milli ammeter when the relay operates.
Record
resistance and current in mA
Carry out
this test on each available setting on relay.
While doing
test observe and record the direction of deflection in the ammeter. Check
whether it confirms the pole on which the fault is simulated.
Repeat once a again on -ve pole of the board.
The test is
satisfactory if the operation of the relay confirms with the setting.
Note :
Electrical commissioning demands cool approach not rushed to wards the job. Any
mistake may cause permanent damage and that was witnessed many a time.
All
instrument need to calibrated so that during dispute you can rely. This is also
a common problem.
All hand tool
should be insulated one and value checked before using.
Electrical
signboard /safety signboard should be displayed .
No comments:
Post a Comment