OTHER
IMPORTANT MISC. INTEGRAL PIPING SYSTEM IN TURBINE ISLAND
A.
Control Oil system.
In
500 MW Units, fire Resistant Fluid (FRF) used for the control systems and LP
Bypass system
mainly to
avoid fire accident in case of leakage of working fluid over high temperature
parts of turbine.
This system consists of
following equipment.
a. A FRF tank with pumps
mounted .
b. Oil vapour exhausters.
c.
Filters and FRF coolers.
The process pertains to
FRF system is similar to TG lube oil system.
However Piping size of control oil system is
small bore piping with some
exception.
The
fluid circulated in the system is divided for different purposes. Such as
control fluid,
secondary
fluid, Trip fluid and start up fluid etc. Control oil transmits signal from
Governing
Rack ,LP Bypass rack , Spray water racks etc to equipments like Control
valves
,IPCV , Extraction valaves , LP Bypass valves etc.
Precaution
needed during erection stage for small bore piping.
A.
Control oil piping is small bore piping that includes pipes , gasket ,
different size “ O –
ring”
, fastners and other assorted fittings
for sealing purpose. Therefore it is requested to
make
a check list of each line and supervisor should monitor the completion by using
proper
material
at proper place. This will reduce time during HT of the line and also save time
and
money
during flushing. Please remember FRF is very costly fluid.
B.
Piping erected as ascending radient should have minimum 67 mm(1:15) slope.
C.
Descending gradient should have minimum 175 mm slope.
E.
Maintain gradient as far as possible if high point is unavoidable then provide
venting
provision
with orifice.
SEAL STEAM SYSTEM
Seal
steam system comprises of following sub systems :
Seal
Steam Lines, valve Stem Steam Leak-Off Lines and Seal Ring Steam Leak-Off
Lines.
In
laying these lines, provide sufficient compensation for thermal expansion. The
service
temperature
for all lines can be assumed to be approximately 450 degC. These pipes expand
by
approximately 6 mm/m between the cold state (initial temperature 20 degC) and the
hot
state.
Seal
pipelines to be connected to the cylinder only after full assembly.
Seal
and leak off steam pressure is very very low therefore impulse line for
pressure
measurement
should carefully laid to avoid pulsation of signal.
DRAIN SYSTEM
One
of the important integral piping system contains small bore to large bore
piping
including
numerous motorised valves , manual valves and pipe fittings. Insulation of the
line
is also an important criteria for drain
piping.
All drain lines shall have as steep a gradient
as possible, an all cases at least 20
mm/m.
In erecting these lines, provide sufficient
compensation for thermal expansion. The
service
temperature in plant can be assumed to be approximately 450 deg C.
These pipes expand by approximately 6mm/m
between the cold state (initial
temperature
20 OC) and the hot state.
On drain lines made from thick-wall piping,
ensure straight pipe sections at least 500 mm
long
between the drain sockets (on casings and pipes) and the first bend in the
pipe.
A few PID diagrams of different system ( of BHEL make set) are attached .
P.S If you are looking to earn few extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
thank u!!
ReplyDeleteThe article gives a detailed description with images on oil seals. for more information on fluid power seal systems check out this website http:/www.darcoid.com
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteNice Share... If you could discuss more about Integral Seals will be more appreciable. Thank You
ReplyDeleteThanks for the information. Hope devotes will be careful after reading this post.Regards
ReplyDeleteSlop fired Boiler Power Plant
Thanks for sharing such a nice article on oil seal systems. Keep sharing. Check out here at @ nconturbines.com for more details on steam turbine engines from the expert engineers.
ReplyDelete