Total Pageviews

Monday, 31 March 2014

ERECTION OF TURBINE GENERATOR PKG PART-IV, PEDESTAL, BASE PLATE ERECTION - ABC OF THERMAL POWER PLANT.


Part –IV

Once all the physical checks are over and shuttering has been removed then we can proceed for Ultrasonic Testing of foundation. This procedure is not followed in India at the beginning but if there is problem in casting then this is the only way to find out honeycomb in the concrete. But I strongly feel that such testing to be done at the very beginning and before the start of Mechanical Erection. In most of the cases civil works comes under the scope of customer and mechanical works are done by some other vendor. When problem arise at later date then it is very difficult to analyse the problem due to lack of scientific data . If ultrasonic test is carried out and found acceptable then one major side can be eliminated.  

PREPARATION OF FOUNDATION FOR PLACEMENT OF PEDESTALS AND BASE PLATES.

Foundation are to be cleaned and loose concrete are to be chipped off.

Maintain elevation of foundation to ensure correct thickness of non-shrink grout.
A reference point for elevation in respect of machine centre line (equivalent to LP rear pedestal) is

to be maintained at a proper place. This point is to be preserved with proper protection. For making


reference point a one side ground plate of about 200 x300 x20 mm  may be used. This may be welded on a I-beam near Generator. The ground position of the plate is to be kept on top side and all elevation are to be transferred from this point with the help of water level jar or by instrument like total station, dumpy level  . A correct elevation reading is to be punched on this plate. This reference point is to be used only during the turbine erection period. (this is an alternative procedure earlier discussed)

Clean and de burr piping sleeves of the foundation on ID/OD of the pipe.

Ensure all corners of the foundation remains perfect during chipping of extra concrete of foundation.

PLACEMENT OF PEDESTALS

Open the package and clean the pedestal.

Ensure there is no paint/oil/grease  on bottom face of the pedestal sole plate.

Ensure there is no paint on inside surface or the pedestal and if required sand blasting may be carried out at site.

Ensure correct fitting/clearance of locating rings of LP rear pedestal.
The half bore error of pedestals is punched by manufacturing unit however in case it is not there,


measure and punch half bore error of pedestal in left/right side of the pedestal. If the error is nil then this may be punched as zero-zero.

Ensure that the pedestal parting plane is feeler tight after tightening all the parting plane bolts. If required, colour matching may be carried out but scraping/cutting is to be done on upper half cover only.

Check proper colour contact of spherical/cylindrical supports of the bearing with the pedestal.

Check contact between spherical Torus piece of bearing and spherical/cylindrical seat. In case of any variation in contact no scraping/cutting to be carried out at site and this may be referred to manufacturing unit. Check centreing of individual bearing w.r.t. pedestal seal bores by fixing piano wire as stated earlier.

Ensure cleanliness of all pedestal oil lines. Close opening of oil lines of pedestal to avoid any foreign material entering in these pipe lines during erection at site.

Weld MOP suction and discharge pipe lines in HP front pedestal as per the drawing before placement.

Assemble protection sheet in the foundation bolt holes of pedestals.
Assemble anchor bolts along with anchor plate of the pedestals. Ensure that there is good contact


available to the backing plate with the foundation. If required colour matching/grinding may be carried out to achieve the contact.

Assemble protection sheet in the anchor bolt hole from bottom side of HP rear pedestal foundation to avoid entry of grout metal.

Ensure level of both anchor plate of H.P. rear pedestal with 70-90 mm gap for filling of grouting concrete.

Adjust height of the Anchor Bolts as specified in the drawing.
Picture of placement of Bearing pedestal for 660MW turbine.

Picture of recently finished TG deck and turbine hall.
continued to Part-v
 

 

Sunday, 23 March 2014

ERECTION OF TURBINE GENERATOR PKG PART-III, CHECKING OF TG FDNS PRE AND POST CASTING - ABC OF THERMAL POWER PLANT.


PART_III

Supervision during casting under progress for TG foundation

Check that there is  no disturbance to the insert etc. during pouring of concrete while vibrators are used.

About 15-20 mm extra concrete may be left on top on all the pedestals and LP base plate area for chipping/cleaning purpose at a later date. Surface of the concrete needs to be blue matched with the surface plate therefore chipping of top layer of concrete is to be removed.

Close all the pipe sleeve from top to avoid entry of concrete inside. Alternately the pipe sleeve should be filled with sand.

CHECKING OF FOUNDATION AFTER CASTING

Clean complete foundation and remove all shuttering etc.



Ensure there is no loose concrete layer in the region where the pedestal and base plates are to be laid. No repair should be done in this region without consulting the turbine erection engineer.
Cover all the opening before checking any dimensional measurement to avoid any accident.
Establish a suitable longitudinal axis considering the fixed point of the LP rear pedestal and various pipe sleeves / inserts.
Establish a transverse axis as 90 degree with the help of Total station.
Measure pitching/elevation of all the inserts and fixed points.
Measure elevation of all foundation on different pedestal and LP base plate area.
Check level of LP rear pedestal fixed points and if required correction may be carried out.
PREPARATION OF FOUNDATION FOR PLACEMENT OF PEDESTALS AND BASE PLATES.
Foundations are to be cleaned and loose concrete are to be chipped off.
Maintain elevation of foundation to ensure correct thickness of non-shrink grout.
A reference point for elevation in respect of machine centre line (equivalent to LP rear pedestal) is
to be maintained at a proper place. This point is to be preserved with proper protection. For making
reference point a one side ground plate of about 200 x300 x20 mm may be used. This may be
welded on a I-beam near Generator.
The cover all the opening before checking any dimensional measurement to avoid any accident.
Establish a suitable longitudinal axis considering the fixed point of the LP rear pedestal and various pipe sleeves / inserts.
Establish a transverse axis as 90 degree with the help of Total station.
Measure pitching/elevation of all the inserts and fixed points.
Measure elevation of all foundation on different pedestal and LP base plate area.
Check level of LP rear pedestal fixed points and if required correction may be carried out.
PREPARATION OF FOUNDATION FOR PLACEMENT OF PEDESTALS AND BASE PLATES.
Foundations are to be cleaned and loose concrete are to be chipped off.
Maintain elevation of foundation to ensure correct thickness of non-shrink grout.
A reference point for elevation in respect of machine centre line (equivalent to LP rear pedestal) is
to be maintained at a proper place. This point is to be preserved with proper protection. For making
reference point a one side ground plate of about 200 x300 x20 mm may be used. This may be
welded on a I-beam near Generator.

A typical TG Deck casting under progress. Shuttering ,supports , concrete pumps pipes are visisble
in the picture.

Pipe sleeves are positioned amongst the reinforcement rod for TG deck foundation. Checking

of verticality , position become problem due to approach.



Anchor bolts and anchor boxes are placed in a position for 660MW super critical TG deck

foundation.




Checking of anchor boxes positioning are being checked by engineer himself.


Continued to part-iv

P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE

Thursday, 20 March 2014

ERECTION AND COMMISSIONING OF TURBINE GENERATOR PKG PART-II ABC OF THERMAL POWER PLANT.


part-2 Turbine



Turbine foundation will be done by Main civil vendor.
In earlier days turbine foundation was casted as a single unit. But now a days springs are introduced in between . Therefore bottom portion of the turbine columns are casted then springs were installed after that top portion of the foundation are being casted. In India most of the spring are supplied by manufacturer called GERB. This technology introduced in India since twenty to twenty five years. Feedbacks are not available how the machine behaves in longer run.
The advantages of spring loaded foundation are given below.
1.  The vibration to the main column is isolated by the spring element resulting to small size base mat which reduces the construction cost and time.
2. The same column of TG deck may also be used to support surrounding floors at the building, so that the total numbers of columns are reduced and the space to accommodate more equipment is increased. This results in more rigidity of building structure of surrounding floors and further in cost saving.
3. Excessive settlement of column can easily be adjusted by inserting or removing shims in spring units.
4. It is possible to tune the foundation subsequently by replacing the spring elements having different load capacity of the springs.
5.
Machine will have more steadiness and stability in the event of earthquake compared to normal foundations.
FOUNDATION CHECKING BEFORE CASTING
Get centre line and elevation point both side of the turbine foundation and make arrangement for piano wire fixing.
Check positioning of all the inserts and fixed points with respect to centre  line in transverse and longitudinal direction as per manufacturer drawings and civil drawings. Discrepancy  if any to be resolved before casting. A typical inserts plate drawing was given on  part-I of this blog.
Check elevation of all points.
Check verticality of all the pipe sleeves with the help of plumb.
Ensure proper locking of all  insert and fixed points before grouting.
Ensure levelling on the fixed points of LP girder and LP rear pedestal.
Preserve machined surfaces of all the fixed points against any damages due to handling.
Ensure proper flatness of the bottom seating plate of all the inserts.
Ensure proper stiffeners in all the vertical and horizontal embedment provided for various purposes like hangers and supports etc.
Ensure proper cleaning of the area before casting.
Remove all unwanted material.
All data to be noted in tabular form for future reference.
Checking should be carried out after completion of all reinforcement fixing and completion of shuttering including supports of shuttering. It may one or two embedded part approach will be not be easy. Take suitable decision on the spot regarding checking. Transfer the reference point to adjacent column for future reference.
A typical picture of turbine top deck after casting is over. ( Picture of 660 MW)
continued to Part-iii
P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE



Tuesday, 18 March 2014

ERECTION AND COMMISSIONING OF TURBINE GENERATOR PKG PART-I ABC OF THERMAL POWER PLANT.

Turbine Generator Package of Thermal Power Plant

Turbine Generator Package consist of following packages and systems. 
Turbine  ( HP ,IP and LP casing and rotors) , Bearing Pedestal , cross over/cross around pipes, ESVs( Emergency Stop Valves ) and IVs ( intermediate valves )  Barring gear drives , anchor bolts  etc.
Generator stator and rotor , Exciter  , foundation bolts ,insulators etc.
LP heaters and HP heaters , Gland steam coolers , drain coolers etc.
Boiler feed pumps ( Motor driven and Turbine driven pumps in case power plant is more than 500MW)
Condensate Extraction Pumps and its accessories.
Miscellaneous tanks for  steam drain , oil ( main turbine and drive turbine of BFP)
CW System , ACW ( Auxiliary Cooling System) Pumps , heat exchangers ,piping etc.
Turbine lubrication oil system including cooler ,tank , pipelines ,oil purification unit.
Control oil system for Governing system .
Drive turbine lubrication oil system for BFP.
Lubrication system for Motor Driven BFP.
Stator Water System (Primary water system) for stator cooling including all accessories like cooler ,tank ,pipelines etc.
Seal oil system for Generator and its accessories.
Hydrogen Gas and other gas system.
De aerator ,Feed storage tank with all accessories.
Condenser  and its accessories.
Small system like Seal and leak off steam, condensate polishing unit , Vacuum Pump system , different hoist , turbine drain system
Vibration Isolation system for TG foundation and  drive turbine foundations.
Extraction systems , TG integral piping etc.
All the items ( except De aerator ) comes under the roof of A-B Bay.
All the items are lifted by 02 Numbers EOT crane for small units for bigger units like 500 MW and above stator is being lifted by Strand jack method /by portal crane.
Above picture shows two turbine deck ( for unit -1 and unit -2). One unit stator lifting has been 
completed and decks are already casted. In 2nd unit only bearing pedestal are erected ,aligned with
the centre line and secondary grouting has been completed. Stand for streching Piano wire is visible
at both end .

A typical drawing of turbine deck is attached herewith showing EP ( embeded parts) on the deck.
continued to part-II foundation checking before casting and after casting.

Thursday, 13 March 2014

BALANCE WORK OF BOILER PART -II SOOT BLOWER , CC PUMP -ABC OF THERMAL POWER PLANT


                                                    Installation procedure of BWCP or CC PUMP.

Generally this pump is getting erected under the supervision  of supplier’ s representatives. However all the necessary inputs and environment  to be provided by the client or customer. However a standard check list is given below for understanding.

Ensure pump was stored and rotated per manufacturer’s recommendations. If it is a long storage then this should be stored vertically as actual position.

Insulation resistance is measured periodically by HT insulation testing machine.

All connecting pipe are attached with proper cleaning. Any particle present may stall and damage the pump. One should be very particular about flushing and cleaning of the pipes.

Check the impeller wear ring clearance  diameter.

Check all the piping supports showing the drawing are erected ,set as per drawing.

Check all the PWHT and NDE data before commissioning.

Check the alignment  data of mating flange pre welding and post welding. The flange should be perfectly horizontal with known tolerances.

Check that motor orientation is as per drawing and Gasket are fitted as per drawing .

Compression of gasket is also an important data. Studs are fitted with anti seize compound ( as recommended by supplier).
Stud compression is to be done as per manufactures recommendation i.e sequence and value.
 Assure that the heat exchanger is completely flushed with warm water.
Connect heat exchanger and associated piping to circulation pump motor.
Assure welding/NDE has been completed per applicable code/contract requirements.
Install gauges and recorder for temperature and pressure.
Install temporary strainer in exchanger low-pressure system.
Assure that motor and heat exchanger are filled with inhibitor, treated water or condensate.

High Pressure water connection are taken from BFP discharge and condensate Pump discharge. Emergency water connection is taken from a small tank installed at height ( for our unit it is 77 metre). All lines connected to this and BWCP to completed and flushed and made ready for commissioning. This is emergency supply when there is total failure of power in the system.
Individual hoist are supplied with individual pump to facilitate module insertion. It is highly recommended to commission this facility before BWCP erection. As the pump is vertical and gap is very  low one should take extra precaution to erect it. On that time this facility will help to insert the module very slowly and in vertical position. Please note that the pump should be erected around 10 meter level from ground level. Approach for the same in coal fired  boiler is a problem.
COAL FEEDER
Other important equipment is called COAL Feeder.
Coal from coal bunker ( generally it holds 8 hours coal of per mill capacity. The sizes of bunker depends on calorific value of coal and mill size) fed to coal feeder connected to each mill. The coal feeder is belt type with weighing facilities and microprocessor controlled speed of the feeder belt ,amount of coal fed into mill etc.
Each coal feeder consists of inlet shut of gate and outlet shut of gate per mill. Speed of the feeder is controlled through Combustion control philosophy.
Number of coal feeder in a 500MW or above boiler varies from six to nine depend on coal caloric value ( Indian or imported or blended).
During commissioning and  operation two aspect may be noticed one No Coal alarm and coal bridge at bunker outlet ( hopper portion).
Continued to PART -I of Turbine Erection. ( TG island)


Saturday, 8 March 2014

BALANCE WORK OF BOILER PART -I SSOT BLOWER , CC PUMP -ABC OF THERMAL POWER PLANT

Till date I have covered important aspects of Boiler erection and commissioning item wise .

However there are few other items also which are needed for a Power Plant more than 500MW.

Items like soot blower system , Boiler water Circulating Pump system , steam blowing process,

safety valve setting process etc. There are many other process and items required for the Power

Plant which cannot be accommodated in blogs . However steam blowing and safety valve floating

will be discussed after I complete TG package .

SOOT BLOWING SYSTEM

There are three types of soot blower in a Boiler.

a. Wall Des lager - Small size soot blowers mounted on water wall to clean water wall externally

from the deposition of soot by using steam jet.

b. LRSB ( Long retractable soot blower ) mounted on water wall surface having long lance to

carry out soot clean process on different super heaters.

c. Air heater soot blowers for Air heater regions soot cleaning.

When Hydro test is over soot blowers are erected in the boiler . Pipe lines are connected after that.

During commissioning  rotary and transverse movement are checked . Distance between lance tip

head and pressure part wall is checked. In our case distance is 38 mm for wall soot blower.

Pressure setting is also done for individual air heater.

Air heater soot blower is required during Boiler light up as chances of soot deposition is high

at air heater basket. Oil is used during Light up and chances of oil soot deposition is high and

it is potential fire hazard afterwards.

Air heater soot blower operates once in 8 hour shift. Other soot blower operates once in 24 hours.

Soot blower controls commands the sequence of operation in the boiler.

Effective cleaning will give clean surface and good heat transfer.

Fuel consumption will be less and production cost will be less. 

CC PUMP

In a controlled circulation Boiler, circulating pumps plays an important role in the performance of the
Boiler.  For 500 MW Units, 3 Numbers of circulating pumps are given and these pumps are placed in
the down comer circuits to ensure proper circulation  of water through the four  water walls. For
250MW/300 MW and below waters moves in natural circulation but for 500MW and above forced
circulation is necessary. For supercritical boilers for initial stage one number cc pump is required.
Feed water entering the boiler drum via Economiser, flows from the drum through the down comers ( 6

Number) to the pump section manifold.  The boiler circulating pumps takes water from the suction

manifold and discharges via the pump discharge  lines in to the furnace lower front inlet header,

furnace lower water wall right and left side headers and rear headers.

In the water wall inlet header, the boiler water passes through strainers and then through orifices which
feed the furnace wall tubes, the economizer recirculating lines.
Associated systems are as follows
a)     Fill and purge line system

This system consists of supply lines from High Pressure water source and also low pressure water
source, removable strainer basket, HP fill and Purge cooler, filter, orifice and all connected lines
both inlet and outlet circuits.  The removable strainer basket and HP fill and purge cooler are

common for all the three circulating pumps.
b)Auxiliary cooling water system
This system is supplied with LP coolant from ECW System / station auxiliary cooling  water
system and also from a separate emergency cooling water from over head tank source.  This
supplier cooling water to

i)                LP Cooler for Pump Motor and
ii)              HP fill and Purge cooler.
The boiler circulating pumps are operated through H.T.Motors which are provided with cavity in which
DM Water is filled and this cavity filling is for cooling the motor while the motor is in operation.
continued to part-II




Saturday, 1 March 2014

COMMISSIONING BOILER ALKALI BOIL OUT ,ACID /EDTA CLEANING PART -VII CONCLUDING PART-ABC OF THERMAL POWER PLANT

In this dispatch I will give advantages of EDTA cleaning over conventional acid cleaning and a

few pictures.








Neutralising pit - During Neutralisation and De aeration.