Total Pageviews

Monday, 16 December 2013

ID ,FD ,PA FAN COMMISSIONING OF BOILER PART -X ABC OF THERMAL POWER STATION


Pre-commissioning Check List/activity to be carried out
Check the erection protocol /log sheet for foundation bolt tightness , clearance with respect to
impeller hubs ,blades casing etc.

Check fan shaft level , check the coupling arrangement , Different gaps measurement in protocol etc.
Check the calibration of power cylinder for blade pitches etc.
Once all the protocol checks are over then check the connection of water line and oil line at different
places.

Check the inlet /outlet duct position immediately before and after fan.
Check the commissioning of outlet dampers and inlet guide vanes.
Check the freeness of the rotor by hand before connecting to the motor.
Remove all temporary supports from inside the duct which comes under the flow path of fan
Agencies working in the boiler area / associated ducting system are informed about the test / cleared
from the test area (As per the actual requirement). Specially for the first time otherwise dust storm
can put any body into trouble .
All loose materials around the fan area are cleared.
Required approach stair cases, platforms and hand rails are erected prior to testing.
Erection of the following are completed.
Lube oil system
All the lube oil control oil pipe lines erected ,cleaned and flush as per procedure (acid cleaning)
described in my earlier blog 
DM.C.W lines for HT motors and oil coolers
Suction and discharge duct and their connection with fan.
L.T./H.T switch gears required for the fan.
Fan casing, Suction / Discharge ducts are cleared off men & temporary materials.
All permanent supports and guides of fan & duct  are erected.
All local  instrumentation of lube-oil system, motor and fan are erected. (Required list to be prepared
at site) )Pressure and temperature indicators are duly calibrated)
Remote indication at control room are made available (List to be prepared at site)
Recommended Blade pitch operation (for FD & PA fan) and inlet damper operation for ID fan)
verified at local and the same ensured from remote for correct opening / closing with respect to
position indicator at local and remote. Free movement of Blades & inlet dampers are ensured.
ACW lines are flushed and connected to the respective inlet points.
 ACW inlet / outlet connections to ID fan sleeve bearings are connected as per the indicated
markings.
 Ensure variable frequency Drive (VFD) system is made ready (In case of ID Fan for operation of the
Fan. (Refer to the procedure enclosed in Section 10.0.)
Insulation resistance of the motor measured and ensured that the values are at satisfactory level.
Final commissioning
Start lube-oil system and establish oil circulation at recommended oil pressures (Both lube-oil and
control oil, which ever is applicable)
After obtaining clearance from all agencies, start the motor in decoupled condition and check the
direction of rotation. If  direction found reverse, change the direction of rotation of the motor.
Refer to section 10.0 for details regarding checking and commissioning of VFD system. In addition
commissioning manual of VFD issued by supplier to be followed in the commissioning of VFD
system.
Start  the motor once again and put under 8 Hrs trial run (FD and PA motors). In the case of VFD
synchronous Machine, put the machine under 4 Hrs trial through channel I and under 4 Hrs trial
through channel II.
Performance of the motor to be monitored by logging load current, vibration and temperatures of
bearings and windings, whichever applicable.
After satisfactory completion of drive trial run, drive and the fan are coupled.
Start the fan and put under 8 Hrs trial run.
Blade pitch for FD and PA fan to be at minimum before starting the fan and after starting, fan to be
slowly loaded up to around 10-15% (Exact loading of the fan to be decided at site)
For ID Fan, keeping the inlet damper at minimum, Fan started and loading to be gradually increased
to 10-15% (Exact loading of the fan to be decided at site)
During 8 Hrs trial run, Fan performance observed by logging load current, vibration, temperatures of
the bearings, parameters of lub-oil system VFD system and draft values in PA,SA and Gas circuits
covered in single fan running condition.
Following parameters are recorded every hour in log sheet.
a. Starting time . b. Closing time (i.e time taken from running to standstill). c. Vane angle
d. Current and Voltage  e. Discharge Pressure . f. Motor Winding Temp . g. Oil level leakage of
oil. h. Cooling water flow Pressure and temperature. I. Lube oil and control oil Pressure and
temperature. j. Any other observation k. Vibration on all bearings.
All the fans commissioning process is same except the duct connection to be done . For FD and
PA suction chamber with silencer head should be available and discharge goes to furnace through
SAPH and PAPH.
For ID fan suction can be taken from ESP outlet bar or ESP can also be taken on line if ESP Air
tightness test is over . Discharge can be up to chimney. 
Above drawing shows the area to be covered during trial run. But it will be best if total ducting work
gets completed before the trial run.
 PA fan distribution up to mill including PAPH.
 P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE




Friday, 13 December 2013

ID,FD,PA FANS COMMISSIONING OF BOILER PART -X -ABC OFTHERMAL POWER


In my last blog I have discussed about the lube oil supply unit for fans ,Air heaters and Mills.
Construction features and item including control and instrument in the lube oil system is
more less same .Therefore observing one lube oil commissioning will help to learn the other.

Now we will discuss the commissioning of FANS. The commissioning of six numbers of
FANs are similar however system requirement for commissioning of FANs are different. We
will discuss the common system requirement and the individual requirement of FANs.


Induced Draft Fan



No of Fan                                :  2

Flow   (Approx)                       : 558.2 cu.m/Sec


Pressure (Approx)                  :  485 mmwc

Temperature                           :  1500C to 154 0C


Drive                                       :  Motor

Speed                                     :  580 RPM

Motor Rating                           :  3650

Control                                    :  Inlet Damper plus variable  / Hydraulic coupling

                                                   Frequency Drive. (VFD).

Forced Draft Fan



No. of Fan                                                   :  2
Flow    (Approx)                                          :  246 cu.m/Sec
Pressure    (Approx)                                    : 351 mmwc
Temperature                                               :  50 degree C
Drive                                                            : Motor
Speed                                                           : 980 RPM
Control                                                         : Variable Blade Pitch control.
Motor Rating                                               :  1175 KW

The boiler   is also equipped with primary air fan, which form a part of the coal preparation a
and firing system.
PRIMARY AIR FAN


 
No. of Fan                                               :  2
Flow       (approx)                                   :  170.5 cu.m/Sec
Pressure   (approx)                                 :  1183 mmwc
         
Temperature                                           :  50 degreeC
Drive                                                       :  Motor
Speed                                                      :  1480 RPM
Motor Rating                                          :  2450 KW.
Control                                                   :  Variable Blade Pitch
                                                                  control.
(****- All the values given here are of 500MW set of BHEL Make.)

 
All the fan are mounted on concrete deck with suction and discharge duct. Connected to the
Fan flanges. FD Fans and PA fans are provided with Silencer at the suction duct. 
Regulation of Fan from no load to full load is performed by changing the pitch angle of blade
profile on all blades simultaneously during operation. This is achieved through a
sophisticated servo mechanism (Hydraulic Servo Motor externally actuated by a power
cylinder and forced lube-oil system.
In the case of ID Fan, the equipment is driven by variable frequency drive motor coupled
with soft coupling. The regulation of the fan is effected through the inlet dampers located at
the inlet of the fan and variable speed by VFD.
In FD and PA fans, the rotor is supported in antifriction  bearings and cooled by forced
lubricating oil. A thrust bearing is provided to absorb axial loads. Thermometers (RTD &
TI ) are provided in the bearing housing for temperature monitoring.
In ID Fan, the bearings are while metal sleeve type with forced oil lubrication. Fixed bearing
near drive end is designed to absorb the Axial forces. Thermometers are provided in the b
earing housing for temperature monitoring.
Respective O & M manuals to be referred for typical drawing of each fan.
Common Facilities Required for Fans
Safety Rules clearance certificate to be signed at site by all concerned engineers

before commissioning of the fans.
 
It is proposed to commission the fans as per the following proposals.


Oil flushing of lube-oil system is completed in all respect and fresh oil has been filled in the tank.(****)

 (***)- Presently using electronic centrifuge flushing oil can be cleaned up to required
parameter and can be reused as fresh oil. 

Trial run of H.T. Motor carried out for  8 Hrs as per agreed protocol.

Auxiliary cooling water line connected ,flushed with all instrumentation and ready for use.

LT /HT Power supply available and Minimum protection is tested and ready.

Availability of lighting, communication facility at the test area.

 Availability of portable fire extinguishers

Servo control mechanism / VFD system / Hydraulic coupling commissioned and calibrated.

Instruments for Pressure ,Temperature , Blade Pitch Position etc are commissioned and put
in place.


 P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE




 



Saturday, 7 December 2013

ID, FD,PA FANS,AIR HEATER , MILLS LUBE OIL BOILER COMMNG PART IX -ABC OF THERMAL POWER


I am going to describe the commissioning procedures of ID<FD and PA fans for a boiler.
As  the procedure of commissioning is more or less same therefore commissioning
procedure will be common.
While writing  it was felt that before start commissioning procedures of fans ,the

commissioning procedures of lubrication units to be discussed . As these lubrication units

are more or less same for all the fans therefore any one can be discussed out of all

lubrication units. These units are also same for AH (air heater) and Mills. So if we discuss

one lubrication unit then other units are automatically covers.




Number of lubrication units used in Boiler


-  One Number /Fan /unit – Total requirement is six numbers ( ID-2 ,FD-2 and PA-2)


-  One Number / Mill /unit- Total number 9 or 10 as per number of Mills.

-  Two Number /Air Heater/Unit ( Support & Guide bearing) – Total 8 numbers ( SAPH and
PAPH).
Rotary equipment in Boiler like Fans ( except scanner and seal air) ,Air heaters and Mills
are provided with external lube oil system for supplying lubrication to the bearings. This
lubrication units also serves as coolant for equipment bearings.
The external lubrication system consists of Oil Tank , Pumps (02 nos) , suction
strainers ,duplex filters , oil coolers , connecting pipelines valves (isolating and relief),
instrumentation for local measurement and remote logic and measurement etc. Logic of
auto changeover and emergency change over by hand are also been provided.
Generally all  the lubrication unit comes as a skid (i.e totally fabricated with input / output
connection at the end.
Our main objectives will be clean the lube oil unit pipeline and associated equipment free
from dust and foreign materials so that lube oil going to bearing  is very clean.
All the equipment and pipelines to be erected as per drawing . Drain oil pipes ( from Bearing
to tank should have minimum slope towards  the tank).
Site erected pipelines are dismantled from flange joints ,end connection etc to make it
smaller pieces. Then these pipelines are manually cleaned and air blown. Then wooden
plugs placed in one end tightly and flushed with DM water number of times to check that      
there is no leakage from wooden plugs.
 All the coolers to be hydro tested 1.5 times  of the design pressure.
 Following chemicals are required for acid cleaning of pipeline ( soaking method)
 a. HCL 30% b. Rhodine 213 SPL  c. Sodium Nitrite d. Liquor ammonia 25%
 e. Lime Power.
 
5% hydrochloric acid with 0.2% inhibitor ( Rodine 213 SPL) is filled in the pipes.
The solution is allowed to soak in the pipes for four hours and then drain to pit and with
plenty of service water and lime to neutralized.
The pipes are flushed with DM water for 5 to 10 minutes .
Pipes are again filled with DM water containing 2.0% sodium nitrite and 5% liquor
ammonia . The solution is allowed to soak for 30 minutes and then drained to pit.
The pipe is rinsed with DM water till PH of discharged water is between 6.5 and 7.5.
 The internal surface is dried with compressed air.
 The line filled with lube oil and then drain . This will fill the pipeline with a uniform fill of oil.
 ( Any cutting ,welding after acid cleaning of the pipe is strictly prohibited. )
 Oil Flushing is carried out in two stages
 Stage-I - without bearing in circuit
 stage –II – Bearings included in the flushing circuit.
 The Oil Tank is filled with recommended oil
 Direction of motor is checked by dismantling the pump and again assembled.
 Centrifuge also placed in position and connected with temporary lines.
 Start the pumps with recirculation valves wide open.
 Pressure to lube oil lines is brought to 1.0 to 1.5 kg/cm2 by throttling recirculation valve.
 The system is checked for leakage. Flushing should continue with one pump in service .
Both the pumps should be tried alternatively. Centrifuge should be on service to clean the
oil.
Time to time DP filter is checked and if required cleaned/replaced.  DP across filter should

be less than 0.2 Kg/cm2
Mechanical impurities should be less than 100 ppm in flushing oil for three consecutive

reading taken at interval of four hours.
Before taken Bearing into circuit clean the oil tank again so that all sludge accumulated

during stage –I flushing gets cleaned.
All the measurements during commissioning to be recorded and protocoled.




 P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE