Pre-commissioning
Check List/activity to be carried out
Check the erection protocol /log sheet for
foundation bolt tightness , clearance with respect to
impeller hubs ,blades
casing etc.
Check fan shaft level , check the coupling
arrangement , Different gaps measurement in protocol etc.
Check the calibration
of power cylinder for blade pitches etc.
Once all the protocol
checks are over then check the connection of water line and oil line at
different
places.
Check the inlet /outlet duct position
immediately before and after fan.
Check the commissioning of outlet dampers
and inlet guide vanes.
Check the freeness of the rotor by hand
before connecting to the motor.
Remove all temporary supports from inside the
duct which comes under the flow path of fan
Agencies working in the boiler area /
associated ducting system are informed about the test / cleared
from the test
area (As per the actual requirement). Specially for the first time otherwise dust storm
can put any body into trouble .
All loose materials around the fan area are
cleared.
Required approach stair cases, platforms and
hand rails are erected prior to testing.
Erection of the following are completed.
Lube oil system
All the lube oil control oil pipe lines erected ,cleaned and flush as per procedure (acid cleaning)
described in my earlier blog
DM.C.W lines for HT motors and oil coolers
Suction and discharge duct and their
connection with fan.
L.T./H.T switch gears required for the fan.
Fan casing, Suction / Discharge ducts are
cleared off men & temporary materials.
All permanent supports and guides of fan
& duct are erected.
All local
instrumentation of lube-oil system, motor and fan are erected. (Required
list to be prepared
at site) )Pressure and temperature indicators are duly
calibrated)
Remote indication at control room are made
available (List to be prepared at site)
Recommended Blade pitch operation (for FD
& PA fan) and inlet damper operation for ID fan)
verified at local and the
same ensured from remote for correct opening / closing with respect to
position
indicator at local and remote. Free movement of Blades & inlet dampers are
ensured.
ACW lines are flushed and connected to the
respective inlet points.
markings.
Fan. (Refer to the
procedure enclosed in Section 10.0.)
Insulation resistance of the motor measured
and ensured that the values are at satisfactory level.
Final commissioning
Start lube-oil system and establish oil
circulation at recommended oil pressures (Both lube-oil and
control oil, which
ever is applicable)
After obtaining clearance from all
agencies, start the motor in decoupled condition and check the
direction of
rotation. If direction found reverse,
change the direction of rotation of the motor.
Refer to section 10.0 for details regarding
checking and commissioning of VFD system. In addition
commissioning manual of
VFD issued by supplier to be followed in the commissioning of VFD
system.
Start
the motor once again and put under 8 Hrs trial run (FD and PA motors).
In the case of VFD
synchronous Machine, put the machine under 4 Hrs trial
through channel I and under 4 Hrs trial
through channel II.
Performance of the motor to be monitored by
logging load current, vibration and temperatures of
bearings and windings,
whichever applicable.
After satisfactory completion of drive
trial run, drive and the fan are coupled.
Start the fan and put under 8 Hrs trial
run.
Blade pitch for FD and PA fan to be at
minimum before starting the fan and after starting, fan to be
slowly loaded up
to around 10-15% (Exact loading of the fan to be decided at site)
For ID Fan, keeping the inlet damper at
minimum, Fan started and loading to be gradually increased
to 10-15% (Exact
loading of the fan to be decided at site)
During 8 Hrs trial run, Fan performance
observed by logging load current, vibration, temperatures of
the bearings,
parameters of lub-oil system VFD system and draft values in PA,SA and Gas
circuits
covered in single fan running condition.
Following parameters are recorded every hour in log sheet.
a. Starting time . b. Closing time (i.e time taken from running to standstill). c. Vane angle
d. Current and Voltage e. Discharge Pressure . f. Motor Winding Temp . g. Oil level leakage of
oil. h. Cooling water flow Pressure and temperature. I. Lube oil and control oil Pressure and
temperature. j. Any other observation k. Vibration on all bearings.
All the fans commissioning process is same except the duct connection to be done . For FD and
PA suction chamber with silencer head should be available and discharge goes to furnace through
SAPH and PAPH.
For ID fan suction can be taken from ESP outlet bar or ESP can also be taken on line if ESP Air
tightness test is over . Discharge can be up to chimney.
Above drawing shows the area to be covered during trial run. But it will be best if total ducting work
gets completed before the trial run.
PA fan distribution up to mill including PAPH.