CEILING GIRDER FABRICATION PART V OF STRUCTURAL ERECTION.

Above picture shows the position of ceiling girders on boiler Top with welded beam connected position.

Picture showing ceiling girders getting assembled at ground floor for welding. Supporting of ceiling

girders is needed to avoid distortion during welding.



Ceiling Girders  02 nos are placed  inside the cavity

after taking support from Boiler columns . Two nos

each are positioned both sides and two numbers are

near front cavity. Postioning of ceiling Girder should

made carefully otherwise crane and material move

 -ment will be big problem. If this is not followed

carefully then we may have to do fabrication of

ceiling Girder outside cavity.







Ceiling Girder fabrication

under progress. The details

C.G will be given in next

slide































contd to page VI