ABC OF THERMAL POWER PLANT

THIS BLOG IS WRITTEN FOR CONSTRUCTION SUPERVISORS AND ENGINEERS TO GAIN PRACTICAL KNOWLEDGE ON THERMAL POWER STATION BOTH ON SUB CRITICAL AND SUPER CRITICAL TECHNOLOGY.

Sunday, 13 November 2016

ELECTRICAL SYSTEM (LT) INSTALLATION , PRE-COMMISSIONING , COMMISSIONING OF DIFFERENT LTMCC -ABC OF THERMAL POWER PLANT

›
Besides HT cubicles other common electrical items are transformer , LTMCC ( Low tension Motor eontrol center ) , Different Power distribu...
2 comments:
Saturday, 5 November 2016

PRE CHARGING TEST AND COMMISSIONING OF HT SWITCH GEAR (TYPICAL) ( photoes) -ABC OF THERMAL POWER STATION

›
HT switchgear getting erected in the power plant. A portion of single line diagram of HT line at thermal power station. ...

PRE CHARGING TEST AND COMMISSIONING OF HT SWITCH GEAR (TYPICAL) -ABC OF THERMAL POWER STATION

›
CONCLUDING PART PRE – ENERGISING CHECKS & TESTS -Inspect any physical damage in the busbar, insulation, panel doors, power &...
13 comments:
Saturday, 22 October 2016

HT SWITCHGEAR ERECTION ,TESTING AND COMMISSIONING (PART-II) -ABC OF THERMAL POWER PLANT

›
In my last dispatch I have indicated the number of panels required to be installed for HT connection .A picture of the same was also atta...
6 comments:
Friday, 30 September 2016

ELECTRICAL SYSTEM ( HT ) PANEL 11KV FOR EQUIPMENTS AND SYSTEM (PART -I)- ABC OF THERMAL POWER

›
Till last dispatch basics electrical system discussed which are essential for the erection and commissioning of the Power system. Earthl...
15 comments:
Friday, 9 September 2016

220 VOLT DC SYSTEM-BATTERY CHARGER -COMMISSIONING PART -I I-ABC OF THERMAL POWER PLANT.

›
COMMISSIONING PROCEDURE:      TESTING OF BATTERY CHARGERS: The insulation value shall be checked with 500 V DC Megger. During thi...
Wednesday, 7 September 2016

220 VOLT DC SYSTEM-BATTERY CHARGER PRE-COMMISSIONING PART -I -ABC OF THERMAL POWER PLANT.

›
220 volt dc system with battery charger commissioning Till last dispatch I have discussed about the basic requirement of electrical sy...
‹
›
Home
View web version

About Me

Debasish Guha
I HAVE THIRTY FIVE YEARS OF EXPERIENCE ON BUILDING POWER STATIONS AT DIFFERENT PARTS OF INDIA. DURING ERECTION AND COMMISSIONING OF POWER STATION IT WAS FELT THAT CONSTRUCTION SUPERVISORS AND ENGINEERS KNOWLEDGE ABOUT A POWER STATION IS VERY LIMITED TO HIS OWN FIELD. CONSTRUCTION FIELD IS UNORGANISED IN INDIA. IT FELT PRUDENT TO GIVE THEM KNOWLEDGE OF ENTIRE POWERSTATION IN BRIEF SO THAT THEY CAN UNDERSTAND THE LINK OF THEIR WORK TO SYSTEM. ALSO NEW ENTRANTS WILL BE EQUIPPED WITH GOOD TECHNICAL KNOWLEDGE.
View my complete profile
Powered by Blogger.