ABC OF THERMAL POWER PLANT

THIS BLOG IS WRITTEN FOR CONSTRUCTION SUPERVISORS AND ENGINEERS TO GAIN PRACTICAL KNOWLEDGE ON THERMAL POWER STATION BOTH ON SUB CRITICAL AND SUPER CRITICAL TECHNOLOGY.

Wednesday, 13 August 2014

GENERATOR AUXILIARIES (SEAL OIL SYSTEM ) PART-I ABC OF THERMAL POWER PLANT

›
Till  last dispatch I have outlined the installation of turbine and generator of thermal power plant briefly with the help of photos. I ha...
8 comments:
Wednesday, 30 July 2014

ERECTION SEQUENCE AND PLAN FOR GENERATOR PART-III ( ROTOR INSERTION) CONCLUDING PART. ABC OF THERMAL POWER PLANT.

›
  ROTOR INSERTION PROCESS STARTED. PLEASE NOTE THE ARRANGEMENTS MADE ON THE ROTOR FOR FIXING LIFTING CEILING FROM EOT CRANE . ...
Wednesday, 23 July 2014

ERECTION SEQUENCE AND PLAN FOR GENERATOR PART-II ABC OF THERMAL POWER PLANT.

›
Some of the checks are to be carried out before rotor threading is  given below All electrical tests (dc resistance, IR value and impedan...
Thursday, 17 July 2014

ERECTION SEQUENCE AND PLAN FOR GENERATOR PART-I ABC OF THERMAL POWER PLANT.

›
-Foundation Checks  to be carried out. Generally this was done with turbine foundation checks. - Installing the Foundation Beams and t...
2 comments:
Monday, 7 July 2014

GENERATOR PKG ERECTION PART-IV,( CONCLUDING) LIFTING ARRANGEMENTS OF GENERATOR - ABC OF THERMAL POWER PLANT.

›
Final part of generator erection with strand jack system is given below through pictures. Process of genrator erection by strand jack or ...
Saturday, 5 July 2014

GENERATOR PKG ERECTION PART-III, LIFTING ARRANGEMENTS OF GENERATOR - ABC OF THERMAL POWER PLANT.

›
PART -III In continuation to my  last blog on erection of generator by strand jack method  part-ii more pictures now being added t...
Friday, 13 June 2014

GENERATOR PKG ERECTION PART-II, LIFTING ARRANGEMENTS OF GENERATOR - ABC OF THERMAL POWER PLANT.

›
PART- II Stator lifting by EOT Cranes:- In earlier days up to 210 /250 MW class the stator is being lifted by two EOT cranes of sim...
2 comments:
‹
›
Home
View web version

About Me

Debasish Guha
I HAVE THIRTY FIVE YEARS OF EXPERIENCE ON BUILDING POWER STATIONS AT DIFFERENT PARTS OF INDIA. DURING ERECTION AND COMMISSIONING OF POWER STATION IT WAS FELT THAT CONSTRUCTION SUPERVISORS AND ENGINEERS KNOWLEDGE ABOUT A POWER STATION IS VERY LIMITED TO HIS OWN FIELD. CONSTRUCTION FIELD IS UNORGANISED IN INDIA. IT FELT PRUDENT TO GIVE THEM KNOWLEDGE OF ENTIRE POWERSTATION IN BRIEF SO THAT THEY CAN UNDERSTAND THE LINK OF THEIR WORK TO SYSTEM. ALSO NEW ENTRANTS WILL BE EQUIPPED WITH GOOD TECHNICAL KNOWLEDGE.