TURBINE GENERATOR PKG ERECTION PART-XII, SPRING ERECTION AND RELEASE - ABC OF THERMAL POWER PLANT.

›
Earlier days up to 250 MW most of the foundation was rigid and casted along with the main column foundation. But now a days all the TG d...
3 comments:
Saturday, 17 May 2014

TURBINE GENERATOR PKG ERECTION PART-XI, ERECTION SEQUENCE ,TIPS ETC.- ABC OF THERMAL POWER PLANT.

›
Part –XI Sealing and anti seizing compound used in turbine as per BHEL ‘ s Turbine manual. ==========================================...
1 comment:
Saturday, 10 May 2014

TURBINE GENERATOR PKG ERECTION PART-X, DIFF.CHECKS BUMP ,SWING ,HORN DROP ,CATENARIES ETC.- ABC OF THERMAL POWER PLANT.

›
Part – X After colour matching axial zero position is achieved and this will be reference point of future axial measurement of HP,I...
28 comments:
‹
›
Home
View web version

About Me

Debasish Guha
I HAVE THIRTY FIVE YEARS OF EXPERIENCE ON BUILDING POWER STATIONS AT DIFFERENT PARTS OF INDIA. DURING ERECTION AND COMMISSIONING OF POWER STATION IT WAS FELT THAT CONSTRUCTION SUPERVISORS AND ENGINEERS KNOWLEDGE ABOUT A POWER STATION IS VERY LIMITED TO HIS OWN FIELD. CONSTRUCTION FIELD IS UNORGANISED IN INDIA. IT FELT PRUDENT TO GIVE THEM KNOWLEDGE OF ENTIRE POWERSTATION IN BRIEF SO THAT THEY CAN UNDERSTAND THE LINK OF THEIR WORK TO SYSTEM. ALSO NEW ENTRANTS WILL BE EQUIPPED WITH GOOD TECHNICAL KNOWLEDGE.
View my complete profile
Powered by Blogger.