ABC OF THERMAL POWER PLANT

THIS BLOG IS WRITTEN FOR CONSTRUCTION SUPERVISORS AND ENGINEERS TO GAIN PRACTICAL KNOWLEDGE ON THERMAL POWER STATION BOTH ON SUB CRITICAL AND SUPER CRITICAL TECHNOLOGY.

Saturday, 3 May 2014

TURBINE GENERATOR PKG ERECTION PART-IX, ALIGHNMENT OF HP,IP AND LP TURBINE ,COUPLING ETC.- ABC OF THERMAL POWER PLANT.

›
PART- IX PLACEMENT OF LP ROTOR Measure journal diameter, spigot diameter and coupling hole sizes. Ensure centring of temporary b...
Friday, 25 April 2014

TURBINE GENERATOR PKG ERECTION PART-VIII, PLACEMENT OF LP TURBINE- ABC OF THERMAL POWER PLANT.

›
Part –VIII Some measurements are taken during assembly of modular IP Turbine. Journal diameter and corresponding Bearing-bore. Rec...
3 comments:
Thursday, 10 April 2014

ERECTION OF TURBINE GENERATOR PKG PART-VII, PLACEMENT OF HP MODULE ,IP MODULE- ABC OF THERMAL POWER PLANT.

›
PART- VII PLACEMENT OF HP MODULE IN POSITION Ensure matching of all the four palms of the module where it is resting on the pedesta...
1 comment:
Sunday, 6 April 2014

ERECTION OF TURBINE GENERATOR PKG PART-VI, PEDESTAL, BASE PLATE ERECTION, INSTRUMENTS - ABC OF THERMAL POWER PLANT.

›
Part –VI GROUTING OF PEDESTALS AND LP BASE PLATES   Technical Requirements of Grout material used for turbine pedestal grouting. ...
2 comments:
‹
›
Home
View web version

About Me

Debasish Guha
I HAVE THIRTY FIVE YEARS OF EXPERIENCE ON BUILDING POWER STATIONS AT DIFFERENT PARTS OF INDIA. DURING ERECTION AND COMMISSIONING OF POWER STATION IT WAS FELT THAT CONSTRUCTION SUPERVISORS AND ENGINEERS KNOWLEDGE ABOUT A POWER STATION IS VERY LIMITED TO HIS OWN FIELD. CONSTRUCTION FIELD IS UNORGANISED IN INDIA. IT FELT PRUDENT TO GIVE THEM KNOWLEDGE OF ENTIRE POWERSTATION IN BRIEF SO THAT THEY CAN UNDERSTAND THE LINK OF THEIR WORK TO SYSTEM. ALSO NEW ENTRANTS WILL BE EQUIPPED WITH GOOD TECHNICAL KNOWLEDGE.