ABC OF THERMAL POWER PLANT

THIS BLOG IS WRITTEN FOR CONSTRUCTION SUPERVISORS AND ENGINEERS TO GAIN PRACTICAL KNOWLEDGE ON THERMAL POWER STATION BOTH ON SUB CRITICAL AND SUPER CRITICAL TECHNOLOGY.

Saturday, 16 November 2013

COMMISSIONING OF BOILER ( PART -V) PNEUMATIC VALVE ,PIPIING CHECKS

›
Pneumatic valve. Check the valve position with reference to PID. Check the availability of secure platform , operation flexibili...
2 comments:
Tuesday, 12 November 2013

COMMISSIONING OF BOILER ( PART-IV) ,VALVES

›
It is expected that after completion of Full Hydro ( except re heater) completion of stage1B next step is conducting Boiler Hydro test ...
1 comment:
Saturday, 9 November 2013

COMMISSIONING OF BOILER PART III-HT PROCEDURE- THERMAL POWER PLANT

›
The first activity commissioning engineer will associate is Hydraulic Test of the Boiler. Though the Hydraulic Test is erection activity...
5 comments:
‹
›
Home
View web version

About Me

Debasish Guha
I HAVE THIRTY FIVE YEARS OF EXPERIENCE ON BUILDING POWER STATIONS AT DIFFERENT PARTS OF INDIA. DURING ERECTION AND COMMISSIONING OF POWER STATION IT WAS FELT THAT CONSTRUCTION SUPERVISORS AND ENGINEERS KNOWLEDGE ABOUT A POWER STATION IS VERY LIMITED TO HIS OWN FIELD. CONSTRUCTION FIELD IS UNORGANISED IN INDIA. IT FELT PRUDENT TO GIVE THEM KNOWLEDGE OF ENTIRE POWERSTATION IN BRIEF SO THAT THEY CAN UNDERSTAND THE LINK OF THEIR WORK TO SYSTEM. ALSO NEW ENTRANTS WILL BE EQUIPPED WITH GOOD TECHNICAL KNOWLEDGE.