Total Pageviews

Saturday, 3 May 2014

TURBINE GENERATOR PKG ERECTION PART-IX, ALIGHNMENT OF HP,IP AND LP TURBINE ,COUPLING ETC.- ABC OF THERMAL POWER PLANT.


PART- IX

PLACEMENT OF LP ROTOR

Measure journal diameter, spigot diameter and coupling hole sizes.

Ensure centring of temporary bearing support in the LP front pedestal for placement of LP

rotor.

Place LP rear bearing in position.

Prepare shaft seal compensator along with gaskets (Gasket to be installed in fully ring shape

only) and position them on LP rotor with the help of supplied supports of compensator.

Lift LP rotor with the supplied lifting beam in perfectly level condition and place it in

position. During lowering of rotor ensure radial clearance with the help of long feeler gauges



in the LP casing.
WELDING OF LP OUTER CASING
The welding of LP outer cover is to be carried out before placement of LP Rotor in position
to avoid damage to the rotor.
Colour match and remove all high spots of the matching flange of the LP outer casing.
Ensure good contact between parted diffuser of LP front and LP rear cover.
Colour match and remove all the high spots of the parted diffuser/vertical face to ensure
good contact with the compensator at a later stage.
Colour match and remove all burrs and high spots from parting plane of LP outer casing.
Side flange of LP front and rear cover are to be ensured in right angle to achieve good
contact with their matching flanges.
Place LP front LP rear cover along with parted diffuser and ensure feeler tight joint after
tightening the parting plane bolts. The joint must be feeler tight just after normal tightening
of bolts. Do not over tighten parting plane bolts.
Ensure matching of parted diffuser face on both side of LP casing. If necessary colour
matching may be carried out to achieve a feeler tight joint.
Drill/ream all the parting plane holes as per drawings and install all dowel pins.
After fixing of LP front and rear cover measure the dimension for positioning of both the
centre flanges. The dimensions are to be recorded in such a way that there is no clearance
after fitting of centre flanges in position on both side with the LP front and rear cover. The
centre flanges are supplied in extra length on both sides from the factory and final length
are to be maintained at site only.
Drill/ream dowel pin holes in centre flanges and install all dowel pins in position. Ensure
drilling and reaming of all dowel pin holes to equal depth.
Fit both the centre pieces of the cover in position.
Achieve the fitting clearances for welding as per laid down procedure.
Weld/lock LP upper half flange with respect to lower half casing with the help of metal
cleats to minimise the distortion during welding of LP cover. The cleats may be welded at an
interval of about one meter distance.
Carry out the welding as per the following welding procedure.
Follow the welding procedure and sequence of welding as suggested by manufacturer.
ALIGNMENT AND COUPLING OF LP-IP & HP ROTOR
LP rotor is to be aligned on pedestal seal bore and LP inner outer casing is to be centralised
in such a way that enough clearances are available to LP rotor, during alignment. Now this
alignment activity of all the three rotor can be divided as below :
-Preparation of HP rotor for alignment.
-Preparation of IP rotor for alignment.
-Preparation of LP rotor for alignment.
-Alignment of LP-IP & HP rotors.
-Reaming, honing of the coupling holes.
-Balancing of coupling bolts weight.
Alignment preparation of individual rotor ( i.e HP,IP and LP) to be completed as per OEM ‘s
instruction manual and this is not discussed here. I am going to the next step.
ALIGNMENT OF HP, IP AND LP ROTORS
-Ensure radial and axial run out of all the three rotors are individually in order. If necessary
Individual rotor module can be taken out for correction of coupling face run out. Any
Variation on radial run out of rotor is to be referred to the factory.
-Match coupling faces of two rotor as per the axial face reading of the rotor. Ensure that the
higher point of the rotor coupling face and lower point of another rotor coupling face are
matched together. This is to be compared with shop protocol also.
-Preliminary align (radial and axial) all the three rotors and shift them in spigot along with
the  casing to avoid fouling of rotor inside the casing.
-During alignment achieve left and right movement of the rotor with the help of shims in
spherical / torus piece of the bearing. The up and down movement of the rotor is to be
achieved with the help of shims in the cylindrical/spherical support of the bearing . The
adjustment of shims in the bearing should be within the permissible limits only. 
-Ensure during alignment that the catenaries of the shaft are maintained. 
-Check/record spigot clearance of HP-IP and LP-IP rotors by actually moving them in spigot.
Install four nos. supplied bolts along with one/two pins in HP-IP and LP-IP coupling. Hand
tighten the coupling bolts by keeping a gap of > 1.00 mm in coupling faces for alignment.
Rotate the rotor system and record the coupling gap at 90 Deg. intervals on left, right and
top position. Ensure that the coupling, bolts and pins remain free while recording the gap of
the coupling for the alignment purposes.
-Check swing check value of the HP rotor with alternate bolts in position. The above value
must be within the prescribed limit only otherwise a correction must be carried out at site in
consultation with designer.
-Ensure free movement of rotor on their bearing. Do not rotate the rotor if it is tight during
its rotation.
-Ensue that the coupling holes are properly aligned to avoid unnecessary enlargement of
holes.
-Ensure HP-IP-LP rotor radial run out after tightening with alternate clearance bolts. Release
the couplings for reaming / honing of couplings.
REAMING / HONING OF COUPLING
Ensure that there is no disturbance on coupling during reaming/honing operation.
First ream/hone two opposite holes of the coupling and install two pins/bolts with sliding fit
and then take up all other holes.
Enlarge coupling holes to the minimum possible diameter and try to make all the holes to
same dia.
Ensure that the finished holes are straight and there is no banana shape. This can be
ensured by checking hole with a straight ground finish pin having 0.02/0.03 mm clearance.
Reaming ,Honing of coupling holes is an expert job for machinist and not the job of erectors
. Therefore it will be better to engage professional service to do this job.
BALANCING OF COUPLING BOLTS
After fitting the coupling bolts in all the holes these are to be balanced within +/-5 gms
accuracy and an accurate balance which can take a load of about 20 kg. may be used. During
balancing of coupling bolts following points are to be taken care.
Final balancing of the coupling bolts are to be done along with the coupling nut of individual
bolt.
If all the coupling bolt hole sizes are same before/after reaming and honing then all the
bolts can be kept of equal weight.
If necessary adjust the weight of the bolts by machining the metal from the bolt head.
COLOUR MATCHING OF THRUST BEARING
After completion of reaming/honing and preliminary tightening of the coupling bolts, the
colour matching of the thrust bearing pad have to be carried out with respect to the thrust
collar of the HP Rotor. During colour matching a good contact on all the pads of front and
rear side are to be ensured with respect to rotor collar by moving the rotor in +/- direction
during its hand rotation.

CONTINUED TO PART-X

P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE

Friday, 25 April 2014

TURBINE GENERATOR PKG ERECTION PART-VIII, PLACEMENT OF LP TURBINE- ABC OF THERMAL POWER PLANT.


Part –VIII


Some measurements are taken during assembly of modular IP Turbine.

Journal diameter and corresponding Bearing-bore. Records the value.

Spigot and Recess dimensions of Couplings. Record the value

Out of flatness of coupling Faces (within 0.02 mm concave) & Coupling hole diameter. 

IP Casing Assembly clearances. Record the value and compare with shop result

Alignment of IP Outer Casing w.r.t. Pedestal.

Alignment of Lower Halves of IP Outer and Inner Casing (with Radial & Axial Keys)

Parting Plane gap in Inner Casing after tightening of alternate Bolts (0.02 to 0.03 mm).

Alignment of bearings w.r.t. Rotor. Record shim thickness.

Spring setting of IVCV. Ensure mechanical cleaning of Piping from IVCV to IP Inlet.

Heat tightening of IP Inlet connection & IP Outer Casing

Tightness of bolts at IP Inlet connection

ASSEMBLY OF LP MODULE

In turbine package LP Turbine takes maximum time because the turbine comes in

loose and need to be assembled at site. The job is voluminous and need constant

supervision and measurement.

This assembly can be divided in following sub assemblies

-Assembly of girder and end walls.

-Assembly of LP inner- inner casing and LP inner outer casing lower half.

-Assembly / welding of LP outer casing.

Before starting assembly of LP casing in position, following works are also to be completed :

- Positioning and welding of LP casing centring pin of front and rear side.

- Positioning of key block of LP casing axial keys.
 

- Positioning of all internal of condenser.
 
Two nos. centring pins are to be located below LP front and LP rear pedestal. Necessary pipe
along with two sq. end plates are already provided in the foundation to take the radial load
of the LP casing:
Plumb the centre line from LP front and LP rear pedestal bore on both side over the square
plate of the foundation.
Establish accurate position of the pin and put a punch mark at a required height and mark a
circle and a controlling circle over all the four sq. Plates.
Diameter of the circle must be equal to pin dia. A template equivalent to pin diameter has
to be made for this purpose with about 20 mm thick plate . The template diameter should
be precise.
Make precise hole to match template on all four embedded plate. Ensure that the template
is fitted with minimum clearance and hole centres are perfect as per marking.
Drill hole of about 10 mm diameter on one of square plate of LP front and on one plate of LP rear
for air venting to avoid cracks during welding.
Insert both the pins and carry out the welding as per laid down procedure. Before welding
set correct axial position of the pins.
Insert key block on both the pins and weld their locking ring also. Ensure proper clearances in key
 
block before welding of its locking ring.
Check the welding by DP test.
ASSEMBLY OF GIRDER AND END WALL
Match side matching flange of girder with the surface plate.
Match seating flange of girder where it rests over the LP base plate.
Match and ensure correct positioning of axial key ways of girder.
Colour match side flanges of end wall.
Match and ensure  key block of end wall are parallel.
Place left and right girder with carrier plate, spacer and special packer on LP base plate.
 

Provisionally align and level the girders. Set height of the girder equivalent to machine
centre line maintaining catenaries of the machine.
Assemble locking plate of the front and rear end wall to facilitate its assembly with the
girders.
Assemble front and rear end wall with the girders and ensure perfect parting plane level
during tightening.
Align, level LP outer casing and ensure contact of packers by colour matching/machining of
spacer height.
Install LP casing radial and axial keys.
Assemble inner outer casing axial key blocks on left and right side of girder and dowel them.
Lock with tack welding all the vertical joint bolts.
Put a seal weld run between girder and end wall joint all around except on top face.
Weld girder and end wall parting plane joint with argon welding. Before welding make a V
groove with the help of a chisel and allow the projection of material on surface. Do not
make the groove by grinding.
Do colour matching with a surface plate on all four corner where argon welding have been
carried out.
ASSEMBLY OF LP INNER INNER AND LP INNER OUTER CASING LOWER HALF
Clean the casing and check all the threaded holes.
Do colour matching on all four corners of the casing where it rest over the girder.
Colour match all eight carrier plates of inner casing on both side.
Assemble all carrier plates on girder and do the colour matching with individual carrier
plate.
Prepare Gusset plate of front and rear side with temporary radial keys for fitting in LP inner
casing.
Level and lift LP inner outer casing and assemble/weld both the gusset plates with the help

of some temporary support.

Lower the casing in position over the carrier plates fitted with spacer and special packer.

Provisionally align the casing radial and axial position.

Support the gusset plate with the help of screw jack (about 10-15 tons) on front and rear

side by taking support from condenser stiffeners. Screw jack is to be unscrewed after box-

up.

Adjust the height of the LP inner outer casing as per centre line of the machine and then

level it with the help of instrument.

Ensure that all the eight packers have good contact. Loading of each packer is to be ensured.

Lower the casing by about 2 mm on all the eight packers with the help of shims for

placement of LP rotor to avoid any fouling during placement of rotor.

Fit and weld all gusset plate stiffener pipes except pipe between LP inner outer casing and

condenser. Till neck welding is over do not make any weld connections between condenser

and stiffeners.


LP Turbine placement of a 660MW unit.

HP Turbine with ESV and HPCV , IP Turbine , LP Turbine Lowe casing , Generator ETC is shown

Continued to part -ix

Thursday, 10 April 2014

ERECTION OF TURBINE GENERATOR PKG PART-VII, PLACEMENT OF HP MODULE ,IP MODULE- ABC OF THERMAL POWER PLANT.


PART- VII

PLACEMENT OF HP MODULE IN POSITION

Ensure matching of all the four palms of the module where it is resting on the pedestals.

Ensure matching and paralleling of front and rear key block of the HP casing.

Assemble all four jacking screw of HPC and ensure their free movement.


Clean journals and coupling of the HP rotor.
Record journal diameter, coupling hole sizes and spigot diameter of HP rotor.
Lift module in level condition and place it in position by keeping it 3 to 5 mm toward front pedestal side.
During placement of module use temporary packers similar to permanent and additionally support it by four jacking screws.
Ensure load on all four packers with the help of some additional shims if required.
Install temporary radial and axial keys of the casing.
Prepare HP rotor for alignment
PLACEMENT OF IP MODULE IN POSITION
Ensure matching of all the four palms of the module where it is resting on the pedestals.
Ensure matching and paralleling of front and rear key block of IP casing.
Assemble all four jacking screws of IP casing and ensure their free movement. If these jacking screw holes are provided with the bolts from factory then same are to be removed before placement of module.
Clean IP rotor on both sides including coupling and journal.
Record spigot /recess, journal diameter, and coupling hole sizes.
Lift the module in level condition and place the module in position by moving about 7 to 8 mm towards generator end. Use temporary packers for placement of module in position and additionally support the module with jacking screws.
Ensure load on all four packers with the help of some additional shims if required.
Provisionally align the casing on front and rear pedestal bore. Install temporary radial and axial keys of the casing with some shims.
Prepare IP rotor for alignment
Following measurements are carried out during positioning ,alighnment of  HP cylinder module.
Journal diameter and corresponding Bearing-bore.
Spigot and Recess dimensions of Couplings.
Out of flatness of coupling Faces (within 0.02 mm concave) & Coupling hole diameter.
Transverse & Axial alignment of HP Rotor with Bearings & seal bores during its Placement on the Bearings
Centring and axial position of HP casing w.r.t. rotor

Check parallelism during tightening of Breech-nut on HP Inlet Insert.
Assembly of Hydraulic turning Gear with HP Rotor. Check Clearances . Assembly of Emergency Governor.
HP rotor float and Roll check.
For measurements we use instruments ( calibrated to national standard)  Vernier Caliper, Micrometer , Dial gauge , Straight Edge , Depth Micrometer , Filler Gauge etc.
HP module of 660MW turbine is under placement.

660 MW IP module under placement.
Continued for Part-viii
P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE





Sunday, 6 April 2014

ERECTION OF TURBINE GENERATOR PKG PART-VI, PEDESTAL, BASE PLATE ERECTION, INSTRUMENTS - ABC OF THERMAL POWER PLANT.


Part –VI

GROUTING OF PEDESTALS AND LP BASE PLATES

 Technical Requirements of Grout material used for turbine pedestal grouting.

Compressive Strength, Non-Shrink  - the compressive strength at 28 days must be not lower than 50 N/mm² .

The early compressive strength at 24 hours must not be lower than 24 N/mm²

- the grout may not shrink. In addition a certain swell-rate is desired (volume increase within 24 hours: atleast 0.2%; according to ASTM C 827-95a). The grout must be water and oil resistant.

The basis of the grout must be cement. It may not contain metallic components and added chloride or other admixtures that may corrode steel.

After adding of water the grout must be in fluid state .In order to improve the flow a high water content should be preferred within the admissible range specified by the manufacturer. The grout should be workable for approximately 45minutes and shall not segregate after grouting.
The specified range of suitable grouting heights must be considered for each application. In case of

a too wide grouting height cracks may occur due to strong heat development. If the grouting height

is too narrow the flow of the grout may be not sufficient and air pockets may form. Where grouting

heights cannot be complied with, a different grout type suitable for the grouting height shall

generally be used. In exceptional cases, a grout may be used for a larger-than-specified grouting


height if a stone aggregate (e.g. quartz) with a specified maximum grain size is

added. The manufacturer's instructions should be followed exactly. In our case
we generally keep the heights between 50 to 70 mm.

The processing instructions and specifications of the grout manufacturer must be complied with. Particularly with regard to the amount of water to be added, the processing temperature, the mixing process, as well as the permissible grouting height. Only drinking water may be used for adding to the grout. Concrete mixers shall be suitably sized .The duration and intensity of the mixing process must also be sufficient .No vibrator shall be used in pouring the grout. Grout should be free  flow (working into place) may be aided by manual.

Fill 3 to 8 mm washed Pea-gravel in all the anchor bolts sleeves. These gravel are necessary to give damping effect to the anchor bolts during operation of the machine.

Seal anchor bolts holes after filling of gravel to avoid any entry of grout metal.  Cap ,tapes etc may be used for sealing .Clean foundation with compressed air. Make shuttering of all the pedestal and LP base plates. Use thick polythene sheet inside the shuttering to give better finish and avoid moisture absorption by shuttering.


Shuttering should be made with maximum care to avoid any leakage of grout concrete. All sides of the shuttering are to be sealed either with some sealing compound or with thick mixture of grout material to avoid leakage of grout material.
Foundation are to be kept wet for about 6 hrs. before grouting.
Non shrinkage cement duly approved by turbine manufacturer is to be used for grouting of the pedestals and base plate. In India we generally use Pagel cement from Pidilite , Conbextra GP 2 from Fosroc , SIKA 214 (ACC) and Five star cement company.
Use fresh stock of the grouting material only and check the strength of the material before use. Every batch of the supply should be tested through cube test if the supply is not of same batch. No material ( grout cement) to be used without testing.
During grouting, the mixture has to be poured from one end only and it has to flow to opposite end to avoid any blockage of air pocket.
Water curing is to be carried out for about 10 days duration.
All anchor bolts are to be stretched minimum after 21 days of grouting.
HP, IP & LP module placement work can be taken up after 24 hours of grouting of the pedestal and base plates.
For individual pedestal and base plate, grout mixture should be poured in one lot only.
It is recommended that supplier representative (technical) is present during grouting of pedestal and LP Base plates and grouting is to be done under their technical supervision.

BRIEF TECHNICAL SPECIFICATION OF BHEL MAKE 500MW (TURBINE)
LOAD ( RATED)                                                                        500 MW
MAX. UNDER VALVE WIDE OPEN (VWO) CONDITION            524.2
THREE CYLINDER REHEAT CONDENSING TURBINE                 500 MW
SINGLE FLOW HP TURBINE WITH 17 REACTION STAGES
DOUBLE FLOW IP TURBINE WITH 12 REACTION STAGES PER FLOW
DOUBLE FLOW LP TURBINE WITH 6 REACTION STAGES PER FLOW
2 MAIN STOP AND CONTROL VALVES ( ESVs and HPCVs)
2 REHEAT STOP AND CONTROL VALVES (IVs and IPCVs)
1 SWING CHECK VALVE IN COLD REHEAT LINE
2 BYPASS STOP AND CONTROL VALVES
EXTRACTION SWING CHECK VALVES :
EXTRACTION-1                                                                               NO VALVE
EXTRACTION-2                              1 SWING CHECK VALVE WITH ACTUATOR
EXTRACTION-3         1 SWING CHECK VALVE WITH ACTUATOR & 1 SWING   
                                    CHECK VALVE WITHOUT ACTUATOR     
EXTRACTION-4.1       2 SWING CHECK VALVE WITH ACTUATOR
EXTRACTION-4.2       2 SWING CHECK VALVE WITH ACTUATOR
EXTRACTION-5
1 SWING CHECK VALVE WITH ACTUATOR & 1 SWING CHECK VALVE WITHOUT ACTUATOR
EXTRACTION-6                                                                         NO VALVE
SPEED (RATED SPEED)                                                             50.0 /S
RANGE                                                                 47.5 TO 51.5 /S
STEAM PRESSURES                                                                 RATED*
INITIAL STEAM                                                                        166.7   BAR
BEFORE 1st HP DRUM STAGE                                                154.4   BAR
HP CYLINDER EXHAUST                                                          44.9     BAR
IP CYLINDER STOP VALVE INLET                                          40.3     BAR
EXTRACTION 6                                                                        44.9          BAR
EXTRACTION 5                                                                        17.5     BAR
EXTRACTION 4                                                                        7.2       BAR
EXTRACTION 3                                                                        2.58      BAR
EXTRACTION 2                                                                        1.329   BAR
EXTRACTION 1                                                                        0.257   BAR
LP CYLINDER EXHAUST                                                          0.1013 BAR
PRESSURE IN SEAL STEAM HEADER (ABOVE ATMOSPHERIC)  35 MBAR

STEAM TEMPERATURES                                                                RATED

INITIAL STEAM                                                                                   536.0
IP CYLINDER STOP VALVE INLET                                                      536.0
HP CYLINDER EXHAUST                                                                    340.0
EXTRACTION 6                                                                                    340.0
EXTRACTION 5                                                                                    413.9
EXTRACTION 4                                                                                    292.1
EXTRACTION 3                                                                                    187.3
EXTRACTION 2                                                                                    128.3
EXTRACTION 1                                                                                    66.5
LP CYLINDER EXHAUST                                                                     46.1
CONTINUED TO PART -VII 

 P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE