COMMON KNOWLEDGE OF PRESSURE PART WELDING FOR BOILER IN THERMAL POWER PLANT

There are few basic information required to carry out the erection / construction of

pressure parts of boiler. These items are described briefly below for ready reference.


The welding of all pressure parts and high pressure piping shall be in accordance

 with the following requirements:

Qualification of Weld Procedures



All the welding procedures adopted  shall be qualified in accordance with the latest

applicable requirements of Section IX of ASME code before the work is begun.

Certified welding procedures for welding of pressure parts and piping's  should

contain the type of material, material thickness, the joint details, the pre-heat

temperature maintained, the post weld heat treatment given and the welding current

and the voltage used during qualifications of welding procedures.

Welder's Qualification                 


Only welders, qualified in accordance with the latest applicable requirements of

the Indian Boiler Regulations, shall be permitted to perform any welding work

on the pressure parts. In addition to such statutory qualification requirements,

the welders shall also perform a satisfactory pre-production qualification test to

be conducted at site in consultation with site welding engineer . The services of

an independent testing laboratory can be retained  to perform welder qualification

tests for welders.

All the welders carrying out welding at site, shall carry an identification badge,

which shall indicate the category and the grade of welding for which they have

been tested and authorised to carry out welding. All such badges shall be presented

on demand to the inspection authority.


All records of the welding procedures, the welder's qualification tests and

the welders' performance details for the work performed shall be maintained .

The names of all the welders who made each weld on the boiler pressure parts and

piping within the jurisdiction of the Indian Boiler Regulations shall be maintained .

The certified copies of any or all the above documents shall be submitted to

authority on demand. Marking of welded joints to be done as per norms.

HEAT TREATMENT


Pre-heating, post-heating and post - weld stress relief operations of all welds, shall be

performed in accordance with the requirements of applicable code. Local post weld

stress relieving heat - treatments shall be adopted only in cases where it is normally

impracticable to subject the entire assembly as such for stress relieving operations.

Heating may be by means of electric induction coils or electric resistance coils.

Oxyacetylene flame heating or exothermic chemical heating methods will not be

permitted. Complete recording of the temperatures through out the stress relieving

cycle of the material and the weld subjected to heat treatment shall be made by means

of a potentiometric recorder. Recorders other than those of potentiometric type shall

not be used for such temperature recording during stress relieving operations.


After setting up the weld joint for heat treatment operation, signatures shall be obtained

on the strips chart of the recorder prior to starting of heat treatment cycle. The right

hand corner of the strip chart at the starting point of the heat treatment cycle shall

contain details like the weld number, material, diameter and thickness, method of

heating adopted, prescribed ranges of heat treatment temperatures, date of heat treatment,

reference to item number of the Field welding Schedule.


FIELD WELDING SCHEDULE

Field welding schedule should contain following information:


a) Drawing No (s)

b) Location of the weld

c) Size of the weld (outside diameter and thickness)

d) Type of joints

e) Material specifications

f) Size of fillet on backing ring, when the type of joint is with backing ring

g) Electrode/ filler metal specifications

h) Number of welds per unit

i) Quantity of filler metal per weld

j) Indication of required Non-destructive Examination (NDE) for each weld

k) Pre-heat temperatures for welding

l) Process of welding

m) Post-welding heat treatment temperature ranges, duration, entitled 'Qualification of Weld Procedures' .

Continued to part-III

P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE







Tuesday, 2 April 2013

CONSTRUCTION PLAN FOR PRESSURE PARTS- SCHEDULE FOR 11MONTHS PART -IIn


Continued from last dispatch about erection plan for pressure Part of

super critical boilers



6th month erection schedule

Furnace Rear wall Interim Header

Furnace  Rear wall  Intermediate Header
Furnace lower buck stays

Upper furnace key buck stays

Lower Furnace key buck stays

Low Temperature Re Heater inlet header

Low Temperature Re Heater coils lower



7th month erection schedule

Furnace Lower Spiral  Rear  wall panels

Furnace guides

Economiser outlet header ( after pre-assembly)

Economiser outlet terminal tubes (after pre-assembly)

Economiser miscellaneous items  supports, suspension etc

8th month erection schedule

Circulation system for feed water

Furnace loose tubes for connecting furnace corners , burner panel etc

Pressure Parts attachment items

Economiser coil upper assembly ( after pre- assembly

Economiser intermediate plain tube ( after pre-assembly)

Recirculation pump and its piping etc (coming under Trim piping group)

9th month erection schedule

Furnace front ,rear and side (L & R) header lower after pre-assembly

Furnace bottom support after pre-assembly

Expansion movement attachment, seal boxes arrangement etc

Super heater & Re heater spacer tubes

Economiser inlet header ( after pre-assembly)

Economiser coil assembly lower ,Economiser Feed pipe and link etc

Economiser outlet link etc

10th and 11th month schedule

LRSB ( long retractable soot blower) mounting on furnace

wall de slagger mounting on furnace

Temperature probe

Root valves for vent and drains

Boiler Recirculation Pump and piping

Starting of trim piping line ( soot Blower piping)

Attachment work like door ,peep hole etc ,Supports of economiser line etc

Mixing vessel , CBD and IBD tank , piping , vent piping etc.


Schedule mentioned above is tentative and hold good for matching supply . This can be 

varied as per requirement of site as per availability of material. We have not mentioned

the pre- fabrication of crown plates. This is a major activities and can be started with

ceiling girder pre-assembly if material (alloy steel ) plates are  available. The pre- 

fabrication involves welding , pre-heating and post heating also. For pressure parts

erection we require 10 to 12  electrical winches  ( 2 nos 10 T , 4 to 6 nos 5T ,rest 

can be 3T) with 10000 mtrs wire rope 12 mm 19mm will be required . The winches 

are to be positioned side of the main column. The level of winches should be 1 M

above the ground level so that winches remain unaffected due to accumulated water

below. Large number of max puller ,chain pulley blocks will be required ( more than

100 numbers). 

Welding of pressure parts start from zero dates of pressure parts at pre-assembly bed.

We are not going to discuss about welding here as this is specialised subject but

information required for construction will be shared.





P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 
LINK 2 - PLEASE CLICK HERE










Sunday, 31 March 2013

CONSTRUCTION PLAN OF PRESSURE PART ERECTION -SCHEDULE 11MONTH FOR BOILER


After receipt of sequential material and timely pre-assembly of Boiler Pressure Parts planning for 

erection of the pressure parts is to be taken up. For Pressure Part erection ( beside cranes )  Electrical 

winches , Max puller , chain pulley block etc are required . Capacity of the above equipment will be as 

per requirement of the system. We have planned our erection activities in such a way that hydraulic test 

(drain able) is achieved by 12th month from start of pressure part erection.

First month of erection plan:

Collector vessel with internals, attachment and supports

Separator vessel with internals, attachment and supports

Furnace upper front wall header

Furnace upper sidewall header L & R

Super Heater Radiant Roof inlet header

Re hater header supports and suspension

All suspension for the above

2nd month erection plan

Collector vessels with internals, attachment and supports

Furnace upper vertical wall

Furnace riser pipes /links
( If the riser comes in one piece then it will longer length and having twist and turn in its layout . It will be advisable to lift it at the earliest to avoid difficulties in erection. But if it comes in two or three 
pieces then it can be done afterwards also.)

Super heater final spaced inlet header after Pre-assembly at bed

Super heater back pass side wall inlet header L & R

Super heaters extended side wall inlet headers

Super heater final spaced outlet header

Super heater Radiant roof outlet header

All suspension and structural arrangement

Riser pipes ,desh link ,SH connecting pipes –saturated etc

Re heater vertical panel outlet header pre assemble with terminal tubes L&R

Re heater cross over links etc.

Re heater vertical platen inlet header after per-assembly with terminal tubes

3rd month erection plan

Furnace upper rear screen / hanger Outlet header after Pre-assembly

Furnace vertical side wall panels L & R

Furnace side risers & Furnace rear riser

Furnace Front riser and Furnace screen tubes ( after Pre-assembly)

Furnace Hanger tubes (after pre-assembly)

Furnace corner tubes upper and lower

Furnace upper Buck stays

Super heater platen inlet header ( after pre-assembly)

Super heater platen outlet header ( after pre-assembly)

Super heater front outlet header ( after Pre-assembly)

Super heater vertical platen coil L & R (after pre-assembly)

Super heater steam cooled wall rear upper and inter panel L&R

Super heater steam cool rear wall panel lower L & R

Super heater cool side wall panel upper L & R

Super heater steam cool side wall upper left and inter left

Super heater steam cool side wall upper right and inter right

Super heater rear roof panels L & R  after pre-assembly

Super heater Radiant wall roof panel + attachment after pre-assembly

Low temperature Re-heater outlet header after pre-assembly

Low temperature Re-heater outlet terminal tubes after pre-assembly

4th month erection plan

Furnace front wall interim header ( after pre-assembly)

Furnace side wall interim header ( after pre-assembly)

SOFA panel opening panel

Furnace upper spiral front wall Panel (pre-assembly)

Furnace upper spiral side wall panels - L&R

Furnace extended wall panels

Separator collector link pipes

Furnace Intermediate Header Supports front

Furnace Intermediate Header support -Rear

Furnace Spiral Wall supports Misc items

Furnace upper inter buck stays

Rear arch Buck stays

Upper back  pass buck stays

Back pass lower rear header

Super heater Back pass front wall inlet header

Super heater front wall outlet header

Super heater final spaced assembly L & R

Super heater upper and lower panels

Super heater steam cool side wall panels L & R

Low temperature Re heater pendent assembly

5th month erection schedule


Burner Panels
Furnace Lower Spiral

Furnace Lower Spiral Front wall panels

Furnace vertical wall panels rear ( after ore-assembly)

Mixing Sphere

Furnace Intermediate Header Support  Sides L&R

Furnace wall  Supports front

Furnace wall   Supports Sides L & R

Furnace lower inter Buck stays

SH Extended Side wall outlet header (after pre-assembly)

SH vertical platen coil left & right.

Re Heater Vertical  Platen  Coil L & R

Low Temperature Re Heater coils upper (after pre-assembly)

Low Temperature Re Heater coils inter ( after Pre- assembly)

RH vertical platen coil assy left & RH vertical platen front coil assembly right.





( CONTINUED TO PART II)


P.S If  you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below

LINK 1 - PLEASE CLICK HERE 

LINK 2 - PLEASE CLICK HERE














Wednesday, 27 March 2013

CONSTRUCTION PLAN FOR MATERIAL OF PRESSURE PART INSUPER CRITICAL BOILER


Following Pressure Part items are required at the beginning of starting of pre-assembly

Works. If we assume start of erection of Boiler structure is Zero date. Then these 

 materials are required at site from 5th month of structural erection. It has been observed

 that  Ceiling Girder  with Welded beams and Rolled beams erection gets completed

within six month. Completion of C.G erection is the starting date of Pressure Part erection. 

Super Heater Final spaced inlet header

Super Heater Platen inlet header

Super Heater Final spaced outlet header

Super Heater Platen outlet header

Super Heater final spaced assembly – Terminal Tube.

Super Heater Vertical Platen – Terminal Tube

Super Heater final spaced assembly – Terminal Tube

Super Heater Vertical Platen Coil -Terminal Tube

Re Heater vertical platen inlet header

Low Temperature Re Heater outlet header

Re Heater Vertical Platen outlet header

Re Heater Vertical Platen Inlet & Outlet - Terminal tubes ( L & R)

Low Temperature Re Heater Outlet terminal tubes

Following items will be required sequentially on Pre-assembly bed. This will help

to maintain pace for Pressure Part erection. Material required 2nd month onwards

are given below.

Furnace upper Rear outlet Header

Furnace front wall and side wall interim header.

Furnace spiral upper front & rear wall panels.                                                                                       

Furnace upper spiral wall panels - L & R.

Furnace screen tube and hanger tube

SH front wall outlet header.

SH Radiant wall roof panel + attachments.

SH rear roof panels left & right

Furnace vertical wall panels rear

LTRH upper coil and LTRH intermediate Coil

Furnace rear wall interim header

Furnace upper wall

SH extended side wall

LTRH inlet header

Economiser outlet header

Economiser coil assembly- outlet terminal tubes

Economiser coil assembly –upper ( L & R )

Economiser interim plain tube       (L &  R )

Furnace front ,Rear and side header.

Furnace Bottom supports

Economiser inlet header

Economiser coil assembly lower – inlet terminal tubes.(L&R)

Above materials are required at site from 2nd month to 7th month so that pre-assembly

works can be completed.

In India for a sub critical Boiler ( 500 MW) takes 09 to 11 months for readiness of drainable

Hydraulic test from start of Pressure Part erection. For other developed countires Hydraulic

test is being done for non- drainble and drainable portion. There are advantages and dis advantages

for both the system. The same will be elaborated afterwards. Materials requirement for super

critical boiler is based on 12 month cycle for drainable Hydraulic test.

To achieve this we need to start preparing pre-assembly bed from 5th month of structural erection.

At least four beds are required outside the boiler cavity and two number bed inside cavity. The

bed area should be  near to the actual space of erection with the facility of transporting 18 M 

panels ,coils , headers etc . Four numbers hydra cranes , one number 18 MT crawler crane , one

number 50 MT crawler crane to be deployed for the job at both the places. If it is possible a

temporary rail line can be laid to transport the material from  outside bed to boiler cavity area.

Therefore a proper layout plan to be prepared before start of pressure part erection. There will

be lot of space problem and conflict with other works . Few photographs are being attached .


We have not been able to establish railway line but we have achieved to create nuber of beds

for pre-assembly outside boiler .


This pre-assembly bed is inside cavity. otherwise it is impossible to transport the same from outside.