Part – X
After colour
matching axial zero position is achieved and this will be reference point of 
future axial
measurement of HP,IP and LP casing. During Turbine supervisory  instrument calibration
rotor is
given to instrument group at axial zero position .
 After completion of colour matching of the
thrust bearing pads the casing alignment work 
can be taken
up. In case of spring loaded foundation after completing
all other works the HP / 
IP , IP/LP , LP/GEN , GEN/EXCITER couplings are to be
reopened and realigned after completing 
the reaming /honing . The rotors alignment are to be
checked with TG deck in floating condition 
as per the laid down procedure. After checking of
alignment /catenary the final couplings are to 
be tightened including their coupled run out and
swing check of rotors on HP front and Exciter 
end of the shaft.
The boxing
up of LP inner inner and LP inner outer casing can be taken up before starting 
the
alignment of HP-IP & LP rotor for coupling work.
After
completing the welding of HP inlet, HP exhaust, IP inlet, IP exhaust and other
piping of 
HP/IP casing
the final horn drop readings are recorded as per the laid down procedure 
mentioned in
the manual for horn drop check. However the IP casing horn drop is also to be 
recorded
with IP inlet upper half pipe welded with casing alone.
ASSEMBLY OF
BEARING AT SITE
The KWU/BHEL
design machine are supplied with four bearings out of which three are the 
journal
bearing and one is combined thrust and journal bearing on H.P. rear end of the 
shaft. All
the turbine bearing are self aligning type and they adjust themselves as per
the 
catenary of
the machine.
The function
of a journal bearing is to support the turbine shaft , but the thrust bearing 
support the
shaft as well as work as a fix point for the turbine shaft. The contact 
arrangements
between bearing and bearing supports are of two types i.e. sphere to sphere 
in HP front
and HP rear bearing and torus to cylindrical in other bearings.
The bearings
are supplied to site after ensuring their contact at works. During erection all
the bearing
are supplied to site in aligned and assemble condition in their individual 
pedestal
from the works. After alignment of the bearing in their pedestal the seat of
the b
earing are
doweled before dispatch to site.
In case of
Thrust and Journal bearing the seat of the bearing neither doweled from the 
works nor it
is recommended to be doweled at site. The bearings need preparation before 
placement of
module in position at site. This can be done even before the placement of 
pedestal in
position for grouting.
Assembly
Procedure is available in the erection manual of 500MW turbine.
CRITICAL
CHECKS OF TURBINE ERECTION.
BUMP TEST
The axial
clearance check is determined after radial clearance measurement has been 
completed.
In this case
the shaft is shifted in the “+” and “-” directions from its operating position
and 
the
dimensions with the shaft in limit position are measured using a depth gauge.
ROLL CHECK
In KWU
machine the minimum radial clearances HP, IP and LP casing are measured by 
actual by
moving the casing radial direction at site while rotor is rotated by hand. This
is a 
very  accurate and fast method of measuring the
minimum radial clearance of any of the 
casing.
The major
variation in these reading may cause vibration in the machine and obstruction
in 
barring gear
operation etc. Such facilities are not available in many other designs of
machine 
and causes
longer duration in erection and overhauling of the units.
After
completing the alignment of rotors the casing alignments are carried out by
roll check 
method but
equal importance should also be given to the centering of HP and IP casing.
The centering of casing may not be
fully sacrificed in comparison of rolling test readings and 
a
compromise between these two readings should be made. The roll
CATENARY AND
ALIGNMENTS 
The catenaries of the
machine are very important for a turbine and Generator assembly to 
achieve proper alignment
of various rotors and loading on their bearing. Any deviation may 
lead to various
operational problems in the machine like high shaft vibration, high bearing 
vibration, high Babbitt
metal temperature of the bearing etc. To avoid these problems it is 
necessary to maintain the catenaries
of the machine during erection and subsequent 
realignment/overhaul of
the unit. Many times it is observed that though the alignment of 
rotors are within limit
but the catenaries as a whole get deviated from the prescribed design 
value of the machine. In
order to avoid such derivation a need is felt to devise a procedure 
which shall ensure rotors
alignment along with proper catenaries of the machine. 
During first few years of
the operation of the unit the possibility to the disturbance of the 
catenaries are much more
due to settlement of the foundation frame. 
In each overhaul of the
unit the catenaries of the machine is to be corrected. The L.P. front 
and L.P. rear pedestal are
directly grouted here without any separate base plate. As such 
any correction on lifting
or lowering. These pedestals are not very convenient so if necessary 
the rotor may be lifted or
lowered with respect to pedestal seal bore and required 
catenaries may be
achieved. In extreme cases these pedestals may be even re grouted 
during major overhauls of
the unit to correct the catenaries of the machine. 
HORN DROP TEST
By horn drop test the loading of the
casing on each corner is determined. The horn drop test 
is repeated at various stages in
individual casing i.e. first without connection of any pipe 
lines the horn drop readings are
recorded then it is compared after welding of inlet, outlet 
and extraction pipe lines etc. The
horn drop readings are very important in HP & IP casing. 
First the proper horn drop readings
are made without connection of any pipe lines and then 
the reading are taken after welding of
all pipe lines on HP & IP casing. As such the influence 
of these major pipe lines are notices
on each corner of HP/IP casing by comparing the horn 
drop test readings. The horn drop test
will indicate the quality of work during 
assembly/welding of pipe lines with
the HP & IP casing.
This is a very important check and may
cause serious problem in operation of the machine 
like high vibration in the machine
failure of barring gear in hot/cold machine, obstruction 
during expansion of machine etc. In
horn drop test a drop is measured on an individual 
corner of the casing with the help of
a dial indicator by removing the support of individual 
corner and then it is compared with
the opposite corner. As such this gives an indication of 
indifferent loading of the casing. In
Russian design machine the value of direct dynoxmetre 
loadings are recorded in place of this
horn drop test.
SWING CHECK
The swing check is the measurement of
radial throw caused due to coupling face geometric 
form of the two rotor coupled
together. This is measured on opposite end of the coupling 
and at the free end of the rotor. The
higher swing check value may cause higher shaft 
vibration, higher bearing shell
temperature etc. The value of swing check depends on axial 
run out of coupling faces, the
diameter of the coupling and the length of the rotor. During 
the machining of rotors in the works
some tolerances are permitted by Designer's on the 
coupling faces of the rotor resulting
to some swing check values. The maximum swing check 
values permitted caused due to the
above tolerance for different diameter and length of the 
rotor can be worked out from the
enclosed graph. However it is recommended to keep the 
minimum swing check values for better
results during operation of the machine.
In a multi rotor Turbine-Generator
system it is essential to measure the swing check value in 
both extreme end and where the weight
of the rotors are light. For example 200/210 M.W. 
KWU machine with Russian Generator and
static excitation system the swing check values 
are measured on HP rotor front end
only. In 500 M.W. machine the swing check values are 
measured in H.P. front end and on
exciter rear end. After having general experience of 
number of 200 MW & 500 MW units, a
necessity is felt to measure swing check value on IP 
rotor front end also for better
results during operation of the units. This can be done initially 
during erection with temporary
coupling bolts on LP-IP coupling before reaming/honing of 
coupling. Any variation in swing check
values may be corrected without any hesitation 
during erection of machine. Any
compromise at erection stage may cause serious problem 
during operation of the unit and any
correction becomes much more tedious a later stage. 
The correction may be carried out
either by interchanging the coupling position or by 
correcting the coupling faces by
scrapping/cutting in consultation of Designers.
P.S If you are looking to earn few legitimate extra money from the comfort of your home then please click on the link given below
LINK 1 - PLEASE CLICK HERE
LINK 2 - PLEASE CLICK HERE
 
Dear Sir,
ReplyDeletePlease send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
My Email ID:phani.bhushanarao@gmail.com
With regards,
K.P.B.Rao.
Dear Sir,
ReplyDeletePlease send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
My Email ID:alokranjantpp@gmail.com
With regards,
alok ranjan
Hello Sir,
ReplyDeletePlease send me the pictorial presentation of LP erection. I wish to see the horn drop test photos. please mail me ankush.tomar@yahoo.com.
Thanking you
With best regards,
Ankush
Respected sir,
ReplyDeletePlease send me the Assembly report of LP Turbine mentioned in this page.
Thanks & Regards
R.Nageswara Rao
Respected Sir,
ReplyDeletePlease send the Assembly report of 660MW LP Turbine mentioned in this page end
Thanks & Regards
R.Nageswara Rao
Dear Sir,
ReplyDeletePlease send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
My Email ID:sha23nk@gmail.com
With regards,
Shashank
Dear Sir,
ReplyDeletePlease send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
My Email ID:bhavparmar@gmail.com
With regards,
Bhavesh
This comment has been removed by the author.
ReplyDeleteDear Sir,
ReplyDeletePlease share the "assembly report (pictorial) as prepared by BHEL engineer for 660 MW, we have come across the situation of failure of LP last stage blade in our unit-3 of BHEL SIEMENS design and undergoing overhauling at early stage.
Your pictorial presentation will add knowledge of assembling LP Turbine and serve as a guide.
My email'id is "ashutosh580@gmail.com", waiting for your quick response and thanks a lot in advance.
With Regards,
Ashutosh Gupta
TPP- SR. Engineer
Dear please send me the report at Ashwani.nitk@gmail.com
ReplyDeleteRegards
Dear Sir,
ReplyDeletePlease send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
My Email ID: swarupkumar2489@gmail.com
With regards,
Swarup
Dear Sir,
ReplyDeletePlease send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
My Email ID:yogeshyadav430@gmail.com
With regards,
yogesh
Dear Sir,
ReplyDeleteplease send me the report at patelchirag0011@gmail.com
Regards
Please send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
ReplyDeleteiamrangasamynew2018@gmail.com
This comment has been removed by the author.
ReplyDeletePls send checks conducted and procedures during turbine overhauling
ReplyDeleteSir please send me 660 mw bhel steam turbine o&m manual in pdf for my best knowledge .Kamleshsaharan4@gmail. Com
ReplyDeleteDear Sir,
ReplyDeletePlease send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST660 MW LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
My Email ID: nga_ahirrao@yahoo.com
With regards,
Ahirrao
Please Send me the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST 660 MW LP TURBINE IN PDF FORMAT, to mbujairp@gmail.com
ReplyDeleteThanks in advance
Dear Sir,
ReplyDeletePlease send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR 500 MW HP IP LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement.
My email:dcm10287+500mwvtps@gmail.com
With regards,
Chaitanya Durga
Sir pl send assembly PDF pictorial
ReplyDeleteWith regards,
Suraj
For above my e-mail is
ReplyDeleteSurajrnr10@gmail.com
SIR PLS SEND INFORMATION ABOUT ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR FIRST 660 MW LP TURBINE.
ReplyDeleteMY MAIL SHANMUKHARAO011@GMAIL.COM
With regards,
SHANMUKHARAO
Pl send me assembly report prepared by bhel engineer for first 660 me ko turbine
ReplyDeleteRegards
abhaidvc@gmail.com
Dear Sir,
ReplyDeletePlease send the ASSEMBLY REPORT (PICTORIAL) PREPARED BY BHEL ENGINEER FOR 500 MW HP IP LP TURBINE IN PDF FORMAT.This is for my knowledege enhancement. Also if possible then please send C&I documents related to 500MW and 660MW BHEL turbine.
My email: mondal.ebay03@gmail.com
With regards,
A MONDAL
Dear Sir,
ReplyDeleteMay please share the Assembly Report of 660 MW Turbine on SKMANCHAL@GMAIL.COM.
Regards,
Sanjay Kumar
Nice Post! Ncon turbine in India is one of the leading Power turbine manufacturers with standard quality. You can check them out or contact their expert turbine engineers.
ReplyDeletePlease send me the Assembly report of LP Turbine. turbine rotor
ReplyDelete